Revised_Printer_SOW_Final.pdf
PDF 47 KB Posted
- Attached to
- Flat Bed LED Printer Federal contract opportunity
- Solicitation number
- FA860119QA029
About this file
Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Synopsitation_Document_Cover_Page.pdf | ||
| Clauses_-_FA860119QA029.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
National Museum of the United States Air Force
Flat Bed Printer
26 February 2019
OBJECTIVE
The NMUSAF requires a flat bed printer capapble of significant production and the ability to print on numerous surfaces IAW this Statement of Work.
1.0 GENERAL
The contractor shall provide a printer BRAND NAME OR EQUAL to the following:
a. AGFA Anapurna Model 2540i LED True Flat Bed UV Printer
b. Software equal to Smart Asanti Workflow software
c. Color Management better than or equal to the X-rite i1 Publish Pro.
d. Comptaible with Fiery software system
e. Rectractable registration pin
f. Minimum of 6 vacuum zones.
g. Warranty of at least 36 months
h. Full turn-key installation including all shipping and setup with 4 days of on-site workflow/color training immediately after installation
i. One additional day of follow-up training approximately 45 days after installation.
2.0 DELIVERY
a. Delivery FOB within 60 days of contract award.
b. The printer shall be delivered to:
Exact address to be determined
WPAFB, OH 45433
3.0 DELIVERY PROCEDURES COMMERCIAL VEHICLES
All vehicles larger than a large pick-up truck are required to be inspected by the Wright- Patterson Air Force Base Commercial Vehicle Delivery Gate (CVDG) prior to entering the installation. Vehicles to be inspected include, but are not limited to, the following:
1. Step van/panel truck
2. Tractor/trailer, box, and flatbed containing cargo
3. Tanker trucks
4. Box Trucks
5. Tour buses
6. Garbage/recycled waste trucks
7. Concrete trucks/mixers, dump trucks
8. Cranes, recreational vehicles, petroleum tanker
This inspection will be conducted at Gate 16A located off State Route 444.
The following are exceptions to vehicles utilizing the CVDG:
1. If the vehicle has the product inside (concrete and asphalt trucks) and timely delivery is necessary due to product deterioration it does not need to enter the CVDG. To bypass the CVDG, the contractor shall submit a list containing drivers’ names, social security numbers and the state in which the driver's license is held for those drivers who will be entering the base. This shall be accomplished 24 hours prior to requested entry time. If entry is requested on Monday, this list must be submitted by Friday at 1630 hours. All lists shall be submitted to the 88th ABW/CE Directorate contract inspector. The only gates that may be used under this exemption shall be 15A, 26A, 38A, and gate 1B. If the driver's name is not on the list, he/she will not be allowed access to the installation through these gates and the base will not assume liability for denied access.
2. If a delivery vehicle must exit, and then re-enter the base to complete its route, the vehicle shall be resealed upon exiting the base. After initially passing through the commercial vehicle delivery gate, trucks shall be resealed at Gates 15A, 38A and 22B. The resealing of the trucks will allow them to continue to any other area of the installation (Areas A, B, or Kittyhawk) without reprocessing through the CVDG. To receive resealing assistance, the drivers shall physically stop at one of the three authorized gates and request the installation entry controller to reseal their truck and provide the next location of their delivery. The controller will reseal the truck and give the delivery driver a pre-clearance form. The driver shall present the pre-clearance form to the entry controller at the next point of installation entry. This reentry can be through any base gate.
3. Wright Patterson Integrated Defense Plan, paragraph 3.10.12.9.2. All irregular deliveries will be sent to the CVDG for inspection. All visitors, which include contractors and commercial vendors without proper background checks and contractor passes, will not be allowed on WPAFB unless escorted by the receiving agency. This will take place after the individual(s) are issued a pre-clearance form at the CVDG. After successful completion of the vehicle inspection, the receiving agency will escort the individual to and from their destination on WPAFB. An inspector at the CVDG will contact the receiving agency, informing them to send an escort to the CVDG. Escorts will remain with the vehicle at all times while it is on WPAFB.