Questions and Answers to the Site Visit Requests For Information. Solicitation FA8601-12-R-0049 Project 040216.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation # FA8601-12-R-0049; Project # 040216

Maintain, Repair Windows & Exterior – Historic Facility 20056

Pre-Proposal Site Visit RFIs

1. How much space will be allotted for staging/parking/storage during the project?

Response: A limited number of parking spaces will be reserved for contractors staging/storage use during the project. Reserved spaces for automobile parking will not be granted. The contractor will be permited to utilize space in the contractors trailer yard off Thirteenth Street (on base) for a limited number of trailers and storage. Prior to start of construction the contractor is required to submit a construction plan for coordination of staging & storage.

2. Will the copper gliding need to be replaced once it is removed?

Response: Refer to Elevation General Notes, Note “C” on sheet A2.01. The notes require the contractor to repair/reinstall any copper trim/fascia adjacent to the windows that it is securely fastened. It is not the Governments intent to replace or have the contractor provide any new copper trim.

3. Will the contractor be responsible for moving the materials located in the DLA occupied workspace in order to work on the windows?

Response: The contractor will not be responsible for moving stored items within the building for access to the windows. Refer to general note # 9 sheet A0.01.

4. Does the exterior and windows of the building have any asbestos or lead related issues that the contractor needs to be aware of?

Response: The windows shall be removed per the requirements for lead paint and asbestos containing caulk noted on the environmental sheets G1.01 – G2.03. Enviromental test data is not available for the specific lead/asbetos levels however the contractor shall provide all services required to comply with the environmental notes and specifications for any items disturbed from the window replacement project.