2nd Post RFP Release QA_C-5 Supplemental Depot Capability_round 2.pdf

PDF 88 KB Posted

Attached to
C-5M SUPPLEMENTAL DEPOT CAPABILITY (SDC) Federal contract opportunity
Solicitation number
FA8525-22-R-0003
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center

About this file

This document contains questions and answers regarding a Request for Proposal for C-5M Supplemental Depot Capability services. The solicitation seeks a contractor to provide up to 16 Programmed Depot Maintenance or Unscheduled Depot Level Maintenance events over five years for the C-5M aircraft. Services include Programmed Depot Maintenance, inspections, modifications and repairs. Questions covered in the document relate to flow day requirements, government furnished property, historical replacement rates data, and clarification of quantities in provided appendices. The Department of the Air Force Materiel Command Lifecycle Management Center is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to C-5M SUPPLEMENTAL DEPOT CAPABILITY (SDC), newest first.
File Type Posted
FA8525-22-R-0003 0005.pdf PDF
FA8525-22-R-0003 0004.pdf PDF
FA8525-22-R-0003 0003.pdf PDF
Post RFP Release QA_ C-5 SDC Solicitation FA8525-22-R-0003.pdf PDF
24_C-5 SDC Section L updated.pdf PDF
11_C-5 FPIF Application.xlsx XLSX spreadsheet
FA8525-22-R-0003 0002.pdf PDF
13 -2 Wage Determination Additional locations Houston_Peach_ Palaski_ GA_Herkimer_Oneida_NY_ Manatee_Sarasota_FL.pdf PDF
13-1_ Updated Wage Determination_ update 1.pdf PDF
FA8525-R-0003 0001.pdf PDF
20 C-5 Present_Past Performance Relevancy Table.pdf PDF
13 C-5 SDC Consolidated Wage Determination 11 April 2022.pdf PDF
09 C-5 SDC Packaging Requirements.pdf PDF
08_C-5 SDC Transportation Requirements.pdf PDF
18 C-5 Consent Form.pdf PDF
11 C-5 FPIF Application.pdf PDF
03_C-5M Programmed Depot Maintenance (PDM) Work Specification-Appendix A.pdf PDF
FA8525-22-R-0003.pdf PDF
24_C-5 SDC Section L.pdf PDF
22_C-5 Pricing Model_Pricing Example.xlsx XLSX spreadsheet
21 C-5 PPI Tool Instructions.pdf PDF
19_C-5 Transmittal Letter.pdf PDF
16_C-5 Past Performance Questionaire.pdf PDF
15 C-5 Bidders Library DD Form 2345 Militarily Critical Technical Data Agreement March 2016.pdf PDF
14_C-5 SDC QASP.pdf PDF
10_C-5 GFP Attachment.pdf PDF
07_C-5 SDC Contract Security Classification Specifications.pdf PDF
06_C-5 SDC CDRL A001 thru A034.pdf PDF
05 C-5 SDC Sources of Supply Flow Chart- Appendix C.pdf PDF
04_C-5 AFTO Form 103_Catalog M Tasks-Appendix B.pdf PDF
01_SDC Pricing Model.xlsx XLSX spreadsheet
25_C-5 SDC Section M.pdf PDF
23_C-5 Pre-award Survey Checklist (1).pdf PDF
17_C-5 Client Authorization Letter.pdf PDF
12_C-5 Cross Reference Matrix.pdf PDF
02_C-5 Supplemental Depot Capability (SDC) PWS.pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

# RFP Document Sec # RFP Wording Question to the Government Government Response

1 Q&A's General Question When will responses to questions submitted on or prior to 31 May 2022 be made available, and will those responses include all non-proprietary questions and answers submitted by all competitors?

Responses to Questions submitted prior to the 31 May deadline were posted to Sam.gov on Friday, 24 June 2022.

Solicitation, Amendment 1

Part I, Section H, H-001 C-5 SDC PDM Flow Day Requirements;

and, H-002 (B) Target Flow Days for Each Induction

For Aircraft 4 in the table in the H-001 clause the Flow Day Metric is 390 Days. In table H-002, however, the Target Flow Days is identified as 290 Days.

Would the Government please confirm that the flow days for Aircraft 4 should be 390 Days in both tables?

The flow day requirement is 390 days. An amendment is in work to correct the table in H-002.

3 PWS Section 3.2.1 Government Furnished Material For those items identified as Government Furnished Material, is the Government providing these items at no cost or should Contractors be including the estimated cost of those items in their pricing (ERRC Code T items)?

The Government will provide items listed on the GFP listing at no cost.

It will be the awardee's responsibility to maintain that equipment in a serviceable condition while in their possession.

4 Data Library Appendix A

30 - 100 Percent Replacement 75 - 100 Percent Replacement 100% Replacement DLA Managed Items

General Questions regarding Data provided

1 - Would the Government please explain why there are a significant number of parts listed at greater than 100% replacement?

2- For the line items where quantities are greater than quantity 1, is the replacement percentage indicative of the percentage of replacement for the total quantity or is it reflective of replacement of the full quantity per aircraft at the percentage rate noted?

(i.e. In the 100% Replacement DLA Table (line item 2), is the historical replacement value at 33% reflective of replacing 1 each 33% of the time or does it reflect replacing a quantity of 2 each 33% of the time?)

3 - For the items identified as 0% replacement, is it safe for offerors to assume that we do not need to include cost for these items in our material pricing or should we develop some type of risk factor for these items, should any of them need to be replaced?

The information provided in the spreadsheets identified was provided to offeror's as information only, in an attempt to be as transparent with industry as possible, with data we have collected for historical replacement rates. 1- There should not be any actual replacement percentages above 100%. For any that are represented as above 100% in the spreadsheet provided, these should be capped at 100% replacement.

2- For the data that has been provided, If the QPA is 2 or more, than the replacement percentage factor is based on the QPA.

3- The Government will not direct any offeror on how to interpret the information that was provided or in how to utilize the data for pricing purposes. It is up to each individual offeror to determine their own stance on risk, etc. in developing their pricing.

Bidder's Library:

Appendix A - 100% Replacement AF- Managed Items

FY22_GFM

Appendix A - 100% Replacement DLA- Managed Items FY22

Appendix A - 30-100 Percent Replacement

Appendix A - 75-100 Percent Replacement

All pages in all four documents (lists)

Issue:

Duplication of Part Numbers / National Stock Numbers (NSNs)

In evaluating the material of the four documents (lists) provided, we identified numerous duplicate Part Numbers / NSNs.

Should the contractor include these duplicates in our pricing submission with the proposal?

The information provided in the spreadsheets identified was provided to offeror's as information only, in an attempt to be as transparent with industry as possible, with data we have collected for historical replacement rates. The Government will not direct any offeror on how to interpret the information that was provided or in how to utilize the data for pricing purposes. It is up to each individual offeror to determine their own stance on risk, etc. in developing their pricing.

Any duplicate entries should be considered an error.

Bidder's Library:

Appendix A - 75-100 Percent Replacement

All pages Issue:

Clarification on quantities

In evaluating the material on the four lists provided, we understand the different quantities of material that in the 75-100% list, column AX (Average REP%) is the average quantities; but in column AY (Highest REP%) is more than 100% replacement per aircraft.

Please clarify that the quantities in the Highest REP% columns are correct.

There should not be any actual replacement percentages above 100%.

For any that are represented as above 100% in the spreadsheet provided, these should be capped at 100% replacement.

Bidder's Library:

Appendix A - 30-100 Percent Replacement

All pages Issue:

Clarification on quantities

In evaluating the material on the four lists provided, we understand the different quantities of material that in the 30-100% list, column AJ (Average REP%) is the average quantities; but in column AK (Highest REP%) is more than 100% replacement per aircraft.

Please clarify that the quantities in the Highest REP% columns are correct.

There should not be any actual replacement percentages above 100%.

For any that are represented as above 100% in the spreadsheet provided, these should be capped at 100% replacement.

C-5 Supplemental Depot Capability (SDC) Post RFP Release Q&A, Round 2

L3Harris Questions