PR: FD2060-15-00157 PWS REVISION: 0 1

Performance-based Work Statement for

Depot level Repair of the Electromechanical Linear Actuators.

29 October 2015

1.0 Description of Services

1.1 Objective(s): This PWS is for the depot level Repair of the Electromechanical Linear

Actuators. The national stock number (NSN) is 1680-00-412-4397GA and part numbers (P/N)

65A124. The extent of Repair work required shall be determined by the initial inspection/functional checkout and the disassembly/assembly required to return these items to a serviceable end item that shall efficiently serve its intended purpose. No government personnel or equipment shall be used for testing after repair of items. Delivery schedule shall be met for all requirements through CAVAF reporting. Each asset shall be Repair and returned to the

Government in serviceable condition. Original design of the end items and parts thereof, or the design functional capabilities of the end items, shall not be changed, modified or altered unless such changes are authorized in writing by the Procuring Contracting Officer (PCO).

1.2 Benefit to United States Air Force (USAF): Having serviceable assets will allow the TH-

1H Aircraft to perform the mission assigned. Without serviceable assets the Aircraft will be grounded.

2.0 Services Summary

Performance Objective PWS

Reference

Performance Threshold

Meet delivery schedule for all requirements.

4.0 After receipt of repairable assets, the contractor

shall repair and ship assets to the Government in accordance with the contracts delivery schedule.

Repair and return assets to the Government in serviceable condition.

4.2.13

There shall be no more than two (2) Product

Quality deficiency Reporting (PQDR) annually during the period of performance of contract.

CAV-AF Reporting 4.6 The Contractor shall report production using

CAV-AF. The Contractor shall provide data on the actions conducted for each unit. The

Contractor shall report daily or as actions occur.

3.0 Government Property and Services:

3.1 Contractor Responsibility: The Contractor shall be responsible for Government property in their possession in accordance with the Federal Acquisition Regulation (FAR) and applicable

PR: FD2060-15-00157 PWS REVISION: 0 2

supplements including, but not limited to, FAR Part 45, Government Property; FAR 52.245-1, Government Property; and Defense Federal Acquisition Regulation Supplement (DFARS) Part

245, Government Property. The FAR and applicable supplements can be accessed at the site below.

http://farsite.hill.af.mil

3.2 Government Property to be provided: The only Government property to be provided will be the actual reparable items. All other materials used to accomplish these repairs will be owned by the Contractor.

4.0 Technical Requirements. The contractor is required to perform depot level Repair of the

Electromechanical Linear Actuators. After receipt of repairable assets, the contractor shall repair and ship assets to the Government in accordance with the contracts delivery schedule. If the repair action cannot be completed in accordance with the contracts delivery schedule, notification to the Government must be made within three (3) workdays of not meeting the delivery date. Notification shall include the reason for not meeting the delivery schedule, what the contractor will do to preclude the delay from happening again and the date the item will be returned to a serviceable condition.

4.1 Period and Place of Performance

4.1.1 Contract/Order Period of Performance: The period of performance for the contract is for five (5) years.

4.1.2 Place of Performance: These services shall be performed at the contractors facility.

4.2. Maintenance Records

4.2.1. Maintenance Records, Forms, and Publications: AFTO Form 349, AFTO 95

Maintenance Data Collection Record is required and shall be IAW T.O. 00-20-2.

(CDRL A001, DI-MISC-81371A/T)

4.2.2. Depot Maintenance Production Report: The contractor shall submit the report IAW the

CDRL. (CDRL A002, DI-ALSS-80728A/T)

4.2.3 Condemnation and Repair: The contractor shall be required to repair all end items unless the Procuring Contracting Officer (PCO) through the Administrative Contracting Officer (ACO) provides written direction. Requests for condemnation shall be submitted in writing through the

ACO to the PCO within ten calendar days following initial inspection/functional testing.

Condemnations shall not be requested due to unavailability of replacement parts.

Condemnations may only be granted if the item inducted for repair manifests one or more of the following conditions:

a. Physical damage that affects greater than 75 percent of the material within the end item (i.e., crushed).

http://farsite.hill.af.mil/

PR: FD2060-15-00157 PWS REVISION: 0 3

b. Burn damage that affects greater than 80 percent of the internal electrical components and connections of the end item.

c. Repair cost is greater than 75 percent of the cost for a new end item.

d. Beyond Economical Repair (BERs): Requests for condemnations

Shall be submitted in writing to the Government PCO within five workdays of the intent to condemn.

Condemnation authority shall be requested when the cost to Repair the asset exceeds 75 percent of the unit’s replacement cost. The contractor shall not charge the full repair cost, but only the firm fixed price associated with negotiated BERs CLIN.

The PCO retains the right to request enlarged color photographs of any proposed condemned end item. These photographs shall clearly portray the extent of damage to the end item and/or effects of overheating. One photograph shall be of the entire end item showing the part number and serial number. The results of any electrical testing performed on the end item shall also be submitted for review. The contractor may be required to submit the proposed condemned end item to Government technical representative for evaluation, confirmation, and/or disposition instructions.

4.2.4. The Government is authorized to replace condemned end items with replacement reparable end items of the same NSN at no additional cost. The contractor is authorized reclamation from condemned units. The contractor shall request authorization from the PCO prior to reclaiming any items from the condemned unit. The contractor shall report the use of reclaimed items to the

PCO.

4.2.5. Accessory and Component Reuse, Repair and Replacement: Items received which are misidentified, misdirected or have Air Force recoverable subassemblies missing shall be reported through the ACO to the PCO, to 411 SCMS/GULD for disposition instructions. Missing

Repairable Expendability, Reparability, Recoverability Code (ERRC) T subassemblies or ERRC

Code T subassemblies that are generated as part of the Next Higher Assembly (NHA) and subsequently require condemnation, will be replaced by the government. The replacement item may be repairable or serviceable. The Repair (if required) and the installation of the replacement item into the NHA will be accomplished at no additional cost IAW T.O. 00-25-234.

4.2.6. Upon approval by the Government, the contractor is authorized to cannibalize Repair Shop

Replaceable Unit (SRU) necessary to accomplish timely Repair to meet production schedule and/or accomplish Repair of Mission Capable (MICAP) requirements. All cannibalized components will be returned to a pre-cannibalized condition. The contractor shall maintain a record of part numbers cannibalized including the serial number of the units from which the part was removed and installed.

PR: FD2060-15-00157 PWS REVISION: 0 4

4.2.7. Facility Requirements. The contractor shall provide a repair facility. The facility shall serve as the depot to carry out the repair and will include contractor owned test equipment, fixtures, adapters and workbenches needed for repair of the assets.

4.2.8. Repairable components will be repaired to Original Equipment Manufacturer (OEM) specifications.

4.2.9. Quality. The Contractor’s quality program shall be established and maintained IAW FAR

52.246-11 or equivalent. The Contractor’s quality program shall meet the requirements of ISO

9001:2008. When requested, the contractor shall assist the cognizant Contract Administration

Office in evaluating Product Quality Deficiency Reports (PQDR) and exhibits for defects reported on items Repaired under this contract to determine the root cause for deficiencies.

These defects may be reported from field or depot organizations. Corrective action to prevent repeat discrepancies shall be an integral part of the contractor’s Quality Program. The contractor shall establish and maintain a program to accomplish the requirements set forth in Air Force T.O.

00-35D-54. There shall be no more than two (2) (PQDR) annually during the performance of this contract repair effort.

4.3 Item Unique Identification (IUID)

4.3.1 IUID REQUIREMENTS: In accordance with DFARS 252-211.7003(a), Item

Identification and Valuation / Definitions, “DoD unique item identification’ means a system of marking items delivered to DoD with unique item identifiers that have machine-readable data elements to distinguish an item from all other like and unlike items.” Unique item identification is required for all items that meet the criteria established by DFARS 211.274-2, Policy for unique item identification.

4.3.2 IUID MARKING PLAN: The Contractor shall mark items in accordance with DFARS

211.274-2, DFARS 252-211.7003, and Military Standard (MIL-STD)-130N, Department of

Defense Standard Practice / Identification Marking of U.S. Military Property. The plan must be approved by the Government Engineering organization, prior to implementation. (CDRL A003, Item Unique Identification (IUID) Marking Plan DI-MGMT-81803)

4.3.3 IUID REGISTRY: In accordance with the Department of Defense Guide to Uniquely

Identifying Items Assuring Valuation, Accountability and Control of Government Property, the

Government user will add item(s) to the Department of Defense (DoD) IUID Registry. The

Government user or Contractor representative responsible for causing “life cycle events” (i.e., abandoned, consumed, destroyed by accident, destroyed by combat, donated, exchanged – repair, exchanged – sold, exchanged – warranty, expended – experimental/target, expended – normal use, leased, loaned, lost, reintroduced, retired, scrapped, sold – foreign government, sold – historic, sold – nongovernment, sold – other federal, sold – state/local, and stolen) will update the item record(s) in the DoD IUID Registry.

4.3.4 IUID MARKING ACTIVITY AND VERIFICATION REPORT: The contractor shall provide an IUID Marking Activity and Verification Report. A key attribute for the report is the

PR: FD2060-15-00157 PWS REVISION: 0 5

Verification column which indicates pass/fail for each item’s Data Matrix Symbol Quality.

(CDRL A004, Item Unique Identification (IUID) Marking Activity, Validation and Verification

Report DI-MGMT-81804)

4.4 Packaging

4.4.1 The Contractor shall package and mark end items and components in accordance with the contract (basic or order, as applicable) Air Force Materiel Command (AFMC) Form 158, Packaging Requirements; MIL-STD-129P, Department of Defense Standard Practice / Military

Marking for Shipment and Storage; MIL-STD-130N, Department of Defense Standard Practice /

Identification Marking of U.S. Military Property; and MIL-STD-2073-1D, Standard Practice for

Military Packaging. The Contractor shall ensure that classified material is packaged, marked and shipped in accordance with DoD 5220.22-M, National Industrial Security Program Operating

Manual (NISPOM). The Contractor shall package and mark material in accordance with other applicable Government regulations including, but not limited to, those regarding security, safety and environmental concerns.

4.4.2 The Contractor shall package and mark material for movement, shipment, receipt and storage in a manner that ensures the protection and preservation of the material for shipment to and storage at the destination. The Contractor shall package electronic parts susceptible to static discharge damage in accordance with MIL-STD-1686C, Military Standard: Electrostatic

Discharge Control Program for Protection of Electrical and Electronic Parts, Assemblies and

Equipment (Excluding Electrically Initiated Explosive Devices).

4.4.3 In accordance with MIL-STD-2073-1D, shipping containers received, which meet the requirements of the AFMC Form 158 and are suitable for return shipment of serviceable assets, shall be reclaimed and stored for reutilization. Unsuitable shipping containers shall be disposed of and replaced with new containers that meet the requirements of the AFMC Form 158.

4.5 Counterfeit Electronics Parts: Not applicable, not electronic parts.

4.6 Commercial Asset Visibility-Air Force (CAV-AF): The Contractor shall report production using CAV-AF. The Contractor shall provide data on the actions conducted for each unit. The

Contractor shall report daily or as actions occur. If CAV-AF training is required, Contractor personnel may send an email to: 406scms.cav.af.ar@robins.af.mil.

(CDRL A005, DI-MGMT-81634C, Commercial Asset Visibility Air Force (CAVAF) /

Government Furnished Material Report)

5.0 General Information

5.1 Continuation of Mission-Essential Services During a Crisis

5.1.1 Designation of Services as Mission-Essential: In accordance with DFARS 237.7602(a), The Continuation of Essential Contractor Services / Policy, DFARS 252.237-7023(a)(2), and

Air Force Instruction (AFI) 10-403, Deployment Planning and Execution, paragraph 1.9.1.33.2, mailto:406scms.cav.af.ar@robins.af.mil

PR: FD2060-15-00157 PWS REVISION: 0 6

the Functional Commander (FC) or civilian equivalent has determined these services are not mission-essential and will not continue in the event of a crisis.

5.2 Security Requirements

5.2.1 Actual knowledge and/or generation of classified information and/or Controlled

Unclassified Information (CUI) are not expected to be necessary for performance of the contract/order. Contractor personnel are required to comply with security requirements to preclude potential security incidents or violations. If a change in the security classification of the contract/order becomes necessary after contract/order award, the Contractor shall make a reasonable effort to continue performance of tasks under the contract/order in compliance with the change in security classification in accordance with FAR 52.204-2, Security Requirements.

5.2.2 Government Security Regulations: The Contractor shall ensure personnel; information, system, property, facility and international security requirements are met. The Contractor shall comply with Government security regulations including, but not limited to, Department of

Defense (DoD) 5200.2-R, Personnel Security Program; DoD 5220.22-M, National Industrial

Security Program Operating Manual (NISPOM); DoD Directive (DoDD) 5205.02E, DoD

Operations Security (OPSEC) Program; DoD Manual 5205.02-M, DoD Operations Security

(OPSEC) Program Manual; and Robins Air Force Base Integrated Defense Plan (RAFB IDP) 31-

101.

5.2.3 Operations Security (OPSEC): The purpose of OPSEC is to reduce the vulnerability of

USAF missions to adversary collection and exploitation of critical information. The Contractor shall ensure compliance with DoDD 5205.02E and DoD Manual 5205.02-M to protect U.S.

Government interests.

5.2.4 Security Clearance: Contractor clearances are not required under this contract.

Contractor personnel shall not be authorized access to classified information and/or CUI and classified items or be permitted to work on classified projects and/or programs without a valid security clearance and a need-to-know. If security clearances become necessary after contract/order award, the Contractor shall ensure applicable Contractor personnel obtain valid security clearances appropriate to the access required for proper accomplishment of contract/order requirements.

5.2.5 Security Incident or Violation: The Contractor shall immediately notify the Government

Security Office of any potential or actual security incident or violation including potential or actual unauthorized disclosure or compromise of classified information and/or CUI.

5.2.6 Security of Contractor System(s): Not Applicable

5.2.7 Access to Government System(s): The Government will provide Contractor personnel access to system(s) necessary to perform tasks under the contract/order. The Contractor shall ensure Contractor personnel who require access to an unclassified or classified Government AIS have the appropriate background check or security investigation conducted. The Government will provide system access subject to approval of the DD Form 2875, System Authorization

PR: FD2060-15-00157 PWS REVISION: 0 7

Access Request (SAAR). Upon completion/termination of the contract/order or transfer/termination of Contractor personnel, the system account(s) will be closed.

5.2.8 Access to Government Facility: Not Applicable.

5.3 Environmental Management System (EMS)

5.3.1 Executive Order (E.O.) 13423, Strengthening Federal Environmental, Energy, and

Transportation Management, and E.O. 13514, Federal Leadership in Environment, Energy, and

Economic Performance, establish the requirement for an EMS.

5.3.2 In accordance with the Assistant Secretary of the Air Force (SAF) Policy Letter, Conformance with Air Force Environmental Management System (EMS) Requirements for

Contracts Performed on Air Force Installations, dated 11 Dec 06, and the Air Force Materiel

Command/Vice Commander (AFMC/CV) Policy Letter, Conformance with Air Force

Environmental Management System (EMS) Requirements for Contracts Performed on Air Force

Installations, dated 1 Aug 07, Contractor personnel who perform work on any USAF installation shall comply with the EMS requirements established by the installation.

5.3.3 These services shall be performed only at the Contractor’s facility; therefore, the EMS requirement does not apply. Globe Motors Inc.2275 Stanley Ave. Dayton, OH. 45404,CAGE:

25140.

5.4 Green Procurement Program (GPP)

5.4.1 Under Secretary of Defense (USD) Memorandum, Establishment of the DoD Green

Procurement Program, dated August 27 2004, establishes the requirement for a GPP. The GPP is a mandatory federal acquisition program that focuses on the purchase and use of environmentally preferable products and services. In accordance with FAR 23.404, Agency Affirmative

Procurement Programs, the GPP requires 100% of purchases of Environmental Protection

Agency (EPA)-designated products, included in the Comprehensive Procurement Guidelines

(CPG) list, contain recovered materials unless the item cannot be acquired competitively within a reasonable timeframe, meet appropriate performance standards, and/or be acquired at a reasonable price. In accordance with FAR 23.101, Sustainable Acquisition Policy / Definition, the GPP requirement applies to all acquisitions, including services, using U.S. Government appropriated funds.

5.4.2 The prime Contractor shall ensure subcontractors comply with the GPP requirement.

5.5 Safety Requirements

5.5.1 Contractor Compliance: The Contractor shall comply with Government Safety and

Health regulations including, but not limited to, Public Law 91-596, Occupational Safety and

Health Act (OSHA), and DoDD 4715.1E, Environmental, Safety, and Occupational Health

(ESOH). OSHA and ESOH requirements shall be incorporated into the Contractor’s safety program.

PR: FD2060-15-00157 PWS REVISION: 0 8

5.5.2 Voluntary Protection Program (VPP): The USAF is a participant in the OSHA VPP.

Contractor personnel performing work on a USAF installation shall participate in the local VPP.

Additional information regarding VPP is available at the site below.

http://www.osha.gov/dcsp/vpp/index.html

5.5.3 Mishap Notification/Investigation

5.5.3.1 In accordance with AFI 91-204, Safety Investigations and Reports, paragraph 2.4.6.1.1, the Contractor shall report mishaps involving damage or injury to USAF interests. In accordance with AFI 91-204, paragraph 1.3.1.1, damage or injury includes: damage to DoD property;

occupational illness to DoD military or civilian personnel; injury to on- or off-duty DoD military personnel; injury to on-duty DoD civilian personnel; and damage to public or private property or injury or illness to non-DoD personnel caused by USAF operations.

5.5.3.2 In accordance with AFI 91-204, paragraph 2.4.6.1.1, the Contractor shall ensure the

USAF [Safety Office] and the applicable contract management authority are notified of mishaps.

The Contractor shall contact the Multi-Function Team (MFT) [Contracting Officer’s

Representative (COR), if available, or another MFT member] by telephone within eight (8) business hours. The MFT will notify the Safety Office and the PCO.

5.5.3.3 In accordance with AFI 91-204, paragraph 2.4.6.1.2, the Contractor shall cooperate with

USAF safety investigations.

5.6 Safety and Health

5.6.1 While performing work under this contract the Contractor shall comply with all applicable federal, state and local regulations regarding occupational safety and health. The Contractor shall notify the Government Representative (GR), within eight hours of any damage to

Government property where the dollar value exceeds $500,000.00 and within two business days, for any damage to Government property less than $500,000.00 during the execution of the contract.

5.6.2 Mishap notifications shall contain, at a minimum, the following information:

1) Contract, Contract Number, Name and Title of Person(s) Reporting

2) Date, time and exact location of accident/incident

3) Brief narrative of accident/incident (Events leading to accident/incident)

4) Cause of accident/incident, if known

5) Estimated cost of accident/incident (material and labor to repair/replace)

6) Nomenclature of equipment and personnel involved in accident/incident

7) Corrective actions (taken or proposed)

8) Other pertinent information http://www.osha.gov/dcsp/vpp/index.html

PR: FD2060-15-00157 PWS REVISION: 0 9

5.6.3 If requested by the designated GR, the Contractor shall immediately secure the mishap scene/damaged property and impound pertinent maintenance and training records, until released by the Procuring Safety Office.

5.7 Inspection of Services

5.7.1 In accordance with FAR 52.246-4, Inspection of Services - Fixed-Price, the Government reserves the right to inspect Contractor performance. Globe Motors Inc.2275 Stanley Ave.

Dayton, OH. 45404,CAGE: 25140.

5.7.2 In accordance with FAR 52.246-4, the Contractor shall maintain an inspection process acceptable to the Government. The Contractor and shall maintain records of inspections which shall be made available to the Government as long as the contract requires.

5.8 Trafficking in Persons

5.8.1 The Contractor shall comply with FAR 52.222-50, Combating Trafficking in Persons.

Additional information about Trafficking in Persons is available at the site for the Department of

State’s Office to Monitor and Combat Trafficking in Persons below.

http://www.state.gov/j/tip

5.8.2 In accordance with the Defense Contingency COR Handbook section on Combating

Trafficking in Persons, the COR must inform the PCO if the Contractor fails to comply with the requirements of FAR 52.222.50. The PCO must convey the information to DoD Combat

Trafficking in Persons (CTIP) Law Enforcement and Support / Office of Under Secretary of

Defense (OUSD) Personnel and Readiness (P&R) Defense Human Resources Activity (DHRA).

5.9 Contract Manpower Reporting : Not Applicable

5.10 Invoicing/Payment and Receipt/Acceptance

5.10.1 In accordance with DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports, the Contractor shall submit/process payment requests (invoices, Receiving Reports or combos) and receipt/acceptance documents via Wide Area Workflow

(WAWF). Additional information regarding WAWF is available at the site below.

https://wawf.eb.mil

5.10.2 CDRL deliverables may be submitted using WAWF or be submitted directly to the applicable MFT member in accordance with the CDRL. The CDRL will determine submittal requirements; however, separately priced data must be accepted in WAWF in order for the

Contractor to receive payment, and both separately priced and non-separately priced data must be accepted in WAWF in order for the contract line item to be closed out.

5.10.3 Services will be accepted by the DCMA.. .

http://www.state.gov/j/tip https://wawf.eb.mil/

PR: FD2060-15-00157 PWS REVISION: 0 10

6.0 Appendices

6.1 Appendix 1, References

Publication Title of Publication

Date of Publication Section(s) that Apply

AFI 10-403 Deployment Planning and Execution

20 September 2012

Change 1 – 29 April 2013 http://www.e-publishing.af.mil/

Paragraph

1.9.1.33

AFI 91-204 Safety Investigations and Reports

9 August 2012 reissued 8 April 2013

Paragraphs

1.3.1.1, 2.4.6.1.1-

2.4.6.1.2

AFMC/CV

Policy Letter

Conformance with Air

Force Environmental

Management System

(EMS) Requirements for

Contracts Performed on

Air Force Installations

1 Aug 07

Entire

00-25-234

With change 38

General Shop Practice

Requirement for the

Repair Maintenance and Test of Electrical

Equipment

Aug 1998, Sep 2009 Entire

Assistant

Secretary of the Air Force

Policy Letter

Conformance with Air

Force Environmental

Management System

(EMS) Requirements for

Contracts Performed on

Air Force Installations

11 Dec 06 Entire

DoD 5200.2-R Personnel Security

Program

1/1/87

Change 1 - 2/12/1990

Change 2 - 7/14/1993

Change 3 - 2/23/1996 http://www.dtic.mil/whs/directives

/corres/pub1.html

DoDD 4715.1E Environmental, Safety, and Occupational Health

March 19, 2005 http://www.dtic.mil/whs/directives

Entire http://www.e-publishing.af.mil/ http://www.e-publishing.af.mil/ http://www.dtic.mil/whs/directives/corres/pub1.html http://www.dtic.mil/whs/directives/corres/pub1.html

PR: FD2060-15-00157 PWS REVISION: 0 11

(ESOH) /corres/pub1.html

DoDD

5205.02E

DoD Operations

Security (OPSEC)

Program

June 20, 2012

DoD Manual

5205.02-M

DoD Operations

Security (OPSEC)

Program Manual

November 3, 2008

E.O. 13423 Strengthening Federal

Environmental, Energy, and Transportation

Management

January 24, 2007 http://www.gpo.gov/fdsys/pkg/FR-

2007-01-26/pdf/07-374.pdf

E.O. 13514 Federal Leadership in

Environment, Energy, and Economic

Performance

5 October 2009 http://www.whitehouse.gov/assets/ documents/2009fedleader_eo_rel.p df

FAR and supplements

Federal Acquisition

Regulation http://farsite.hill.af.mil

Sections applicable to contract and

PWS

OSD

Memorandum

Enterprise-wide

Contractor Manpower

Reporting Application

Nov 28 2012 http://www.acq.osd.mil/dpap/polic y/policyvault/Enterprise-wide_Contractor_Manpower_Rep orting_Application_memorandum.

pdf

Public Law 91-

Occupational Safety and

Health Act of 1970

December 29, 1970 as amended through January 1, http://www.osha.gov/pls/oshaweb/ owadisp.show_document?p_id=27

43&p_table=OSHACT

SAF/AQ

Memorandum

Implementation of FY11

NDAA Section 8108, Contractor Inventory

Nov 13 2012 https://cs.eis.af.mil/airforcecontrac ting/knowledge_center/Documents

/AFFARS_Library/5337/2012-11-

13_saf-aq-memo.pdf

USD Establishment of the August 27 2004 Entire http://www.dtic.mil/whs/directives/corres/pub1.html http://www.dtic.mil/whs/directives/corres/pub1.html http://www.dtic.mil/whs/directives/corres/pub1.html http://www.dtic.mil/whs/directives/corres/pub1.html http://www.dtic.mil/whs/directives/corres/pub1.html http://www.gpo.gov/fdsys/pkg/FR-2007-01-26/pdf/07-374.pdf http://www.gpo.gov/fdsys/pkg/FR-2007-01-26/pdf/07-374.pdf http://www.whitehouse.gov/assets/documents/2009fedleader_eo_rel.pdf http://www.whitehouse.gov/assets/documents/2009fedleader_eo_rel.pdf http://www.whitehouse.gov/assets/documents/2009fedleader_eo_rel.pdf http://farsite.hill.af.mil/ http://www.acq.osd.mil/dpap/policy/policyvault/Enterprise-wide_Contractor_Manpower_Reporting_Application_memorandum.pdf http://www.acq.osd.mil/dpap/policy/policyvault/Enterprise-wide_Contractor_Manpower_Reporting_Application_memorandum.pdf http://www.acq.osd.mil/dpap/policy/policyvault/Enterprise-wide_Contractor_Manpower_Reporting_Application_memorandum.pdf http://www.acq.osd.mil/dpap/policy/policyvault/Enterprise-wide_Contractor_Manpower_Reporting_Application_memorandum.pdf http://www.acq.osd.mil/dpap/policy/policyvault/Enterprise-wide_Contractor_Manpower_Reporting_Application_memorandum.pdf http://www.osha.gov/pls/oshaweb/owadisp.show_document?p_id=2743&p_table=OSHACT http://www.osha.gov/pls/oshaweb/owadisp.show_document?p_id=2743&p_table=OSHACT http://www.osha.gov/pls/oshaweb/owadisp.show_document?p_id=2743&p_table=OSHACT

PR: FD2060-15-00157 PWS REVISION: 0 12

Memorandum DoD Green

Procurement Program http://www.wbdg.org/pdfs/dod_gp p_082704.pdf

Publication Title of Publication Date of Publication Sections that

Apply

00-35D-54 USAF Deficiency

Reporting, Investigation, and

Resolution

Nov 2011 Entire

AFJI 63-108 Government-Industry

Data Exchange Program

(GIDEP)

15 May 1980

AS5553A

Fraudulent /Counterfeit

Electronics Parts;

Avoidance, Detection, Mitigation, and

Disposition

Revision A

2013-01-21 none Department of Defense

Guide to Uniquely

Identifying Items

Assuring Valuation, Accountability and

Control of Government

Property, Version 2.5

September 15, 2012 www.acq.osd.mil/dpap/UID/attac hments/DoDUIDGuideVer2_5.pdf

DoD 5220.22-

M

National Industrial

Security Program

Operating Manual

(NISPOM)

February 28, 2006

Change 1 - March 28, 2013

GIDEP

Operations

Manual S0300-

BT-PRO-010

Government-Industry

Data Exchange Program

September 2009 http://www.gidep.org/

Chapter 2, Participation

Requirements

MIL-STD-129P Department of Defense /

Standard Practice /

Military Marking for

Shipment and Storage

15 December 2002

Change 1 - 15 January 2004, Change 2 - 10 February 2004, Change 3 - 29 October 2004, Entire http://www.wbdg.org/pdfs/dod_gpp_082704.pdf http://www.wbdg.org/pdfs/dod_gpp_082704.pdf http://www.e-publishing.af.mil/ http://www.acq.osd.mil/dpap/UID/attachments/DoDUIDGuideVer2_5.pdf http://www.acq.osd.mil/dpap/UID/attachments/DoDUIDGuideVer2_5.pdf http://www.dtic.mil/whs/directives/corres/pub1.html http://www.gidep.org/

PR: FD2060-15-00157 PWS REVISION: 0 13

Change 4 - 19 September 2007 http://www.acq.osd.mil/log/sci/ait/

MIL-STD-129PCH4.pdf

MIL-STD-

130N

Department of Defense /

Standard Practice /

Identification Marking of U.S. Military Property

17 December 2007

Change 1 – 16 November 2012 http://www.acq.osd.mil/dpap/pdi/ uid/docs/MIL-Std130N_Ch1.pdf

2073-1D

Department of Defense /

Standard Practice for

Military Packaging

15 December 1999, Notice 1, 10 May 2002

1686C

Department of Defense

Standard Practice /

Electrostatic Discharge

Control Program for

Protection of Electrical and Electronic Parts, Assemblies and

Equipment (Excluding

Electrically Initiated

Explosive Devices)

25 Oct 1995

00-20-2 Maintenance Data

Documentation

Nov 2012 Entire

RAFB IDP

31-101

Robins Integrated

Defense Plan

January 2012 Entire http://www.acq.osd.mil/log/sci/ait/MIL-STD-129PCH4.pdf http://www.acq.osd.mil/log/sci/ait/MIL-STD-129PCH4.pdf http://www.acq.osd.mil/dpap/pdi/uid/docs/MIL-Std130N_Ch1.pdf http://www.acq.osd.mil/dpap/pdi/uid/docs/MIL-Std130N_Ch1.pdf

File details come from the government source that posted it. Updated .