Questions answers5016.doc
DOC document 25 KB Posted
- Attached to
- 5 AXIS VERTICAL GRINDING MACHINE
- Solicitation number
- FA8224-08-R-5016
About this file
QUESTIONS AND ANSWERS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 08R50160004.pdf | ||
| Purchasespec5axis(6)3-10-08.doc | DOC document | |
| Purchasespec5axis030408(6).doc | DOC document | |
| 08R50160003.pdf | ||
| AMEND000208-R-5016.pdf | ||
| REVISEDSPECIFICATIONS5016.pdf | ||
| Amendment08-R-5016.pdf | ||
| PastPerformance5AXIS.doc | DOC document | |
| 5AXISPURCHASESPECS.pdf | ||
| FA8224-08-R-5016.doc | DOC document | |
| 1423'S5AXIS.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS
SOLICITATION FA8224-08-R-5016
Question
1. Section 10.3 last paragraph "The contractor shall be required to remove the old machine, clean, cosmoline, palletize, cover with 8 mil visqueen or other covering suitable for outside storage and move it to a location outside of the building as designated by group manager.
Answer
1. The paragraph "The contractor shall be required to remove the old machine, clean, cosmoline, palletize, cover with eight mil visqueen or other covering suitable for outside storage and move it to a location outside of the building as designated by the Group Manager. " Should be removed. I had planned on taking care of removing the old machine.
Question
2. Section 11.0 Will Hill AFB provide the necessary tooling if any is required to perform test off site?
Answer
2. The second question about 11.0 is answered in 10.4 "The contractor shall be responsible to furnish all tools and equipment required to install the machine and perform the tests specified in this specification. The Government shall furnish no tools or equipment."