ES7034.pdf
PDF 38 KB Posted
- Attached to
- Vernier Rocket Motor REMAN
- Solicitation number
- FA8213-26-R-3004
About this file
This document is an Attachment detailing the Rework and Repair requirements for nonconforming material, dated January 2012. The attachment provides precise definitions and procedures for two key processes: Rework (completely reprocessing nonconforming material to meet all contract requirements) and Repair (partially reprocessing nonconforming material to make it usable while not fully meeting all specifications). Contractors are required to document and submit both rework and repair procedures for government review, including a description of the cause of nonconformances and preventative actions. The procedures must include a reinspection provision that takes precedence over Technical Data Package requirements and provides government assurance that reprocessed items meet necessary standards. This requirement applies throughout the entire supply chain, including contractors, suppliers, vendors, and subcontractors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SPI_F001192033.pdf | ||
| CADPAD Item Marking Instruction - Ver 1.6.pdf | ||
| Section M CADPAD.pdf | ||
| JHCS_MT32.pdf | ||
| Statement of Objectives.pdf | ||
| JHCS_MD98.pdf | ||
| REPSHIP.pdf | ||
| FA8213-26-R-3004.pdf | ||
| CDRLs_FD20202551832.pdf | ||
| Packaging SOW.pdf | ||
| SOW REMAN_FD2020-25-51832.pdf | ||
| Section L CADPAD.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5
(ES7034)
REWORK AND REPAIR OF NONCONFORMING MATERIAL
Jan 2012 (version)
(a) Rework and Repair are defined as follows:
(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
(c) Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.