Attachment 5 is a federal contract document detailing rework and repair procedures for nonconforming material, dated January 2012. The document provides specific definitions and requirements for contractors handling materials that do not meet original specifications, distinguishing between "rework" (completely reprocessing material to conform to requirements) and "repair" (reprocessing material to bring it into a usable condition without fully meeting all specifications).
Key procedural requirements include: contractors must document and submit rework procedures to the Government Quality Assurance Representative (QAR) for review, submit repair procedures via DD Form 1694 to the Contracting Officer for approval, provide explanations for nonconformances and prevention strategies, and include reinspection provisions that supersede original Technical Data Package requirements. The document emphasizes that these rework and repair requirements apply throughout the supply chain, including contractors, suppliers, vendors, and subcontractors, with the goal of maintaining quality control and accountability in material processing.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA8213-25-R-3023.pdf | ||
| Packaging SOW.pdf | ||
| Section M CADPAD.pdf | ||
| CDRLs_FD20202551832.pdf | ||
| JHCS_COMBINED.pdf | ||
| Statement of Objectives.pdf | ||
| SPI_F001192033.pdf | ||
| SOW_REMAN_FD20202551832.pdf | ||
| REPSHIP.pdf | ||
| CADPAD Item Marking Instruction Ver 1.6.pdf | ||
| Section L CADPAD.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5
(ES7034)
REWORK AND REPAIR OF NONCONFORMING MATERIAL
Jan 2012 (version)
(a) Rework and Repair are defined as follows:
(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
(c) Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.