FA820626R0022_0002.pdf
PDF 249 KB Posted
- Attached to
- Minuteman III ICBM, Cable Assembly Federal contract opportunity
- Solicitation number
- FA820626R0022
About this file
This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the Department of the Air Force, Directorate of Contracting at Hill Air Force Base, Utah. The amendment extends the solicitation due date from March 16, 2026, to March 31, 2026, at 5:00 PM. The solicitation number is FA8206-26-R-0022, and this is Amendment 0001. The contracting officer is Justin M Raleigh, who can be reached at justin.raleigh.1@us.af.mil or (801) 777-3753.
The contract requirement involves the procurement of cable assemblies as firm fixed-price items with four line items: (1) one first article CABLE ASSEMBLY SPB Connect ECSG P1001 to W4A P2552 (NSN 6150-00-406-2757 AH) with delivery required by July 31, 2026; (2) 49 production units of the same cable assembly with delivery required by April 28, 2027; (3) one first article CABLE ASSEMBLY SPB Connect Programmer P5014 to W4A P2550 (NSN 6150-00-450-8175 AH) with delivery required by July 31, 2026; and (4) 49 production units of the second cable assembly with delivery required by April 28, 2027. Additional line items include first article data test CDRLs and a Counterfeit Protection Plan, both not separately priced. The contract includes first article approval requirements with both contractor testing (FAR 52.209-3) and government testing (FAR 52.209-4) provisions, with 120-calendar-day submission and evaluation periods specified. Delivery location is Hill Air Force Base, Building 849W, and the contract includes employment eligibility verification requirements per FAR 52.222-54. Supporting documentation includes data requirements, engineering drawings, packaging specifications, a Statement of Work, transportation requirements, and CDRL specifications attached to the solicitation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA820626R0022_0003.pdf | ||
| FA820626R0022.pdf | ||
| FA820626R0022_0001.pdf | ||
| EDL_6150004508175AH.pdf | ||
| Transportaion.pdf | ||
| SOW.pdf | ||
| CDRL_FA_CPP_A001_A002_A003.pdf | ||
| FA820626R0022.pdf | ||
| Packaging.pdf | ||
| EDL_6150004062757AH.pdf | ||
| Data_Requirments_6150004508175AH.pdf | ||
| Data_Requirments_6150004062757AH.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
J
2. AMENDMENT/MODIFICATION NO.
FA8206-26-R-0022-0001
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO.
FD20202600022
5. PROJECT NO (If applicable)
FA820626R0022
6. ISSUED BY CODE
DEPARTMENT OF THE AIR FORCE, DIRECTORATE OF CONTRACTING
AFSC OL H PZACA
6050 GUM LANE BLDG 1215
HILL AIR FORCE BASE UT 84056-5825
BUYER: Justin M Raleigh/PZACA justin.raleigh.1@us.af.mil Phone: (801) 777- 3753
7. ADMINISTERED BY (If other than item 6) CODEFA8206
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE
X
9A. AMENDMENT OF SOLICITATION NO.
FA820626R0022
9B. DATED (SEE ITEM 11)
2-FEB-2026
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
ROUTINE
15A. NAME AND TITLE OF SIGNER (Type or print)
15B. CONTRACTOR/OFFEROR
BY ________________________________________________________
(Signature of person authorized to sign)
15C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16B. UNITED STATES OF AMERICA
BY ____________________________________________________
(Signature of Contracting Officer)
16C. DATE SIGNED
FACILITY CODE
NSN 7540-01-152-8070
PREVIOUS EDITION UNUSABLE
30-105 STANDARD FORM 30 (REV. 10-83)
PRESCRIBED BY GSA
FAR (48 CFR) 53.243
X
X The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers X is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods. ( a ) By completing Items 8 and 15, and returning copies of the amendment; ( b ) By acknowledging receipt of this amendment on each copy of the offer submitted; or ( c ) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified. 31-MAR-2026 5:00 PM
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
FA8206-26-R-0022-0001
Continuation of block 14. DESCRIPTION OF AMENDMENT/
MODIFICATION
The purpose of this 02 amendment is to extend solicitation due date as follows:
From: TO:
16 March 2026 31 March 2026
FA820626R00220001
PART I THE SCHEDULE
SECTION B
SUPPLIES OR SERVICES AND PRICES/COSTS
First Article NSN: 6150004062757AH
Item No.
Firm Fixed Price Quantity U/I Unit Price Amount
1 EA
CLIN ACRN ACRN Total
0001 AA
NSN: 6150004062757 AH
First Article CABLE ASSEMBLY,SPEC SPB Connect ECSG P1001 to W4A P2552 (A) Standard cable, rubber cable covering Manufacturer Part Number 07868 69C49443G1 Associated Document(s) Line Item(s)
FD20202600022 01 0001
Priority: R
Inspection: Origin Acceptance: Destination Quality Assurance: Standard Inspection Applicability: None ;
IUID Required: Yes Physical Item Markings:
Class I ODS Substance Application/Use Quantity None None None Type / Ship To PACRN Mark For
A FB2029 PAB
Type / Ship To Quantity (U/I) On or Before Req No / Pri
Required Delivery
A FB2029 1 EA 31 JUL 2026
Proposed Delivery
A FB2029 1 EA
TAC: FRS3
Production Articles NSN: 6150004062757AH
Item No.
Firm Fixed Price Quantity U/I Unit Price Amount
49 EA
CLIN ACRN ACRN Total
0002 AA
NSN: 6150004062757 AH
CABLE ASSEMBLY,SPEC
SPB Connect ECSG P1001 to W4A P2552 (A) Standard cable, rubber cable covering Manufacturer Part Number 07868 69C49443G1 Associated Document(s) Line Item(s)
FD20202600022 01 0002
Priority: R
Inspection: Origin Acceptance: Origin Quality Assurance: Standard Inspection Applicability: None ;
IUID Required: Yes
Transportation From Continental United States CONUS (CONUS) Sources
TYPE / SHIP TO CODE F.O.B.
A FB2029 ORIGIN
Class I ODS Substance Application/Use Quantity None None None Type / Ship To PACRN Mark For A FB2029 PAB Account 9 Type / Ship To Quantity (U/I) On or Before Req No / Pri
Required Delivery
A FB2029 49 EA 28 APR 2027
Proposed Delivery
A FB2029 49 EA
TAC: FRS3
First Article NSN: 6150004508175AH
Item No.
Firm Fixed Price Quantity U/I Unit Price Amount
1 EA
CLIN ACRN ACRN Total
First Article NSN: 6150004508175AH
0003 AA
NSN: 6150004508175 AH
First Article CABLE ASSEMBLY,SPEC SPB Connect Programmer P5014 to W4A P2550 (B) Standard cable, rubber cable covering Manufacturer Part Number 07868 69D49201G1 Associated Document(s) Line Item(s)
FD20202600022 01 0003
Priority: R
Inspection: Origin Acceptance: Destination Quality Assurance: Standard Inspection Applicability: None ;
IUID Required: Yes Physical Item Markings:
Class I ODS Substance Application/Use Quantity None None None Type / Ship To PACRN Mark For
A FB2029 PAA
Type / Ship To Quantity (U/I) On or Before Req No / Pri
Required Delivery
A FB2029 1 EA 31 JUL 2026
Proposed Delivery
A FB2029 1 EA
TAC: FRS3
Production Articles NSN: 6150004508175AH
Item No.
Firm Fixed Price Quantity U/I Unit Price Amount
49 EA
CLIN ACRN ACRN Total
0004 AA
NSN: 6150004508175 AH
CABLE ASSEMBLY,SPEC
SPB Connect Programmer P5014 to W4A P2550 (B) Standard cable, rubber cable covering Manufacturer Part Number 07868 69D49201G1 Associated Document(s) Line Item(s)
FD20202600022 01 0004
Priority: R
Production Articles NSN: 6150004508175AH
Inspection: Origin Acceptance: Origin Quality Assurance: Standard Inspection Applicability: None ;
IUID Required: Yes Physical Item Markings:
Transportation From Continental United States CONUS (CONUS) Sources
TYPE / SHIP TO CODE F.O.B.
A FB2029 ORIGIN
Class I ODS Substance Application/Use Quantity None None None Type / Ship To PACRN Mark For A FB2029 PAA Account 9 Type / Ship To Quantity (U/I) On or Before Req No / Pri
Required Delivery
A FB2029 49 EA 28 APR 2027
Proposed Delivery
A FB2029 49 EA
TAC: FRS3
CDRLS A001A002
Item No.
Not Separately Priced Quantity U/I Unit Price
1 LO NSP
Data First Article Data Test CDRLS A001A002 Associated Document(s) Line Item(s)
FD20202600022 01 0005
Priority: R
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Type / Ship To Quantity (U/I) IAW 14231 Req No / Pri
Required Delivery
A FB2029 1 LO IAW 14231
CDRLS A001A002
Proposed Delivery
A FB2029 1 LO
Counterfiet Protection Plan CDRL A003
Item No.
Not Separately Priced Quantity U/I Unit Price
1 LO NSP
Data
CPP
Associated Document(s) Line Item(s)
FD20202600022 01 0006
Priority: R
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Type / Ship To Quantity (U/I) IAW 14231 Req No / Pri
Required Delivery
A FB2029 1 LO IAW 14231
Proposed Delivery
A FB2029 1 LO
SHIP TO / PLACE OF PERFORMANCE
TYPE/CODE: + CNOTE
MARK FOR: (See Individual Line Item) REQUISITION NUMBER: (See Individual Line Item) REQUISITION PRIORITY: (See Individual Line Item)
AWARD NUMBER:
TYPE/CODE: A FB2029
FB2029 OO ALC DDHU CNTRL RCV
CP 385 519 8898
5851 F AVE BLDG 849W
HILL AFB UT 84056
HILL AIR FORCE BASE 49 840565713
USA
MARK FOR: (See Individual Line Item) REQUISITION NUMBER: (See Individual Line Item) REQUISITION PRIORITY: (See Individual Line Item)
AWARD NUMBER:
PART I THE SCHEDULE
SECTION G
CONTRACT ADMINISTRATION DATA
ACCOUNTING AND APPROPRIATION DATA (AUG 1998)
Accounting and Appropriation Chargeable ACRN Funds Citation Amount Chargeable
AA 97 X4930 .FC04 64 6 47 GH AM133G 01N000 00000 ERRCNP 503000 F03000 $0.00
PSR: K42203 FSR: 001679 DSR: 083201 CIN: F2DCCW5356A1030000AA
ACRN TOTAL $ 0.00
PART II CONTRACT CLAUSES
SECTION I
CONTRACT CLAUSES
52.209-3 FIRST ARTICLE APPROVAL--CONTRACTOR TESTING (SEP 1989)
(IAW FAR 9.308-1(a)(1), FAR 9.308-1(b)(1))
(a) The Contractor shall test 1 unit(s) of Lot/Item 0001/0003 as specified in this contract. At least 30 calendar days before the beginning of first article tests, the Contractor shall notify the Contracting Officer, in writing, of the time and location of the testing so that the Government may witness the tests.
(b) The Contractor shall submit the first article test report within ___120___ calendar days from the date of this contract to __David Cheney__ marked "FIRST ARTICLE TEST REPORT: Contract No. FA820625P0022 Lot/Item No. ___0001/0003___”
Within ___120___ calendar days after the Government receives the test report, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval shall state any further action required of the Contractor.
A notice of disapproval shall cite reasons for the disapproval.
(c) If the first article is disapproved, the Contractor, upon Government request, shall repeat any or all first article tests. After each request for additional tests, the Contractor shall make any necessary changes, modifications, or repairs to the first article or select another first article for testing. All costs related to these tests are to be borne by the Contractor, including any and all costs for additional tests following a disapproval. The Contractor shall then conduct the tests and deliver another report to the Government under the terms and conditions and within the time specified by the Government. The Government shall take action on this report within the time specified in paragraph (b) above. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule, or for any additional costs to the Government related to these tests.
(d) If the Contractor fails to deliver any first article report on time, or the Contracting Officer disapproves any first article, the Contractor shall be deemed to have failed to make delivery within the meaning of the Default clause of this contract.
(e) Unless otherwise provided in the contract, and if the approved first article is not consumed or destroyed in testing, the Contractor may deliver the approved first article as part of the contract quantity if it meets all contract requirements for acceptance.
(f) If the Government does not act within the time specified in paragraph (b) or (c) above, the Contracting Officer shall, upon timely written request from the Contractor, equitably adjust under the changes clause of this contract the delivery or performance dates and/or the contract price, and any other contractual term affected by the delay.
(g) Before first article approval, the acquisition of materials or components for, or the commencement of production of, the balance of the contract quantity is at the sole risk of the Contractor. Before first article approval, the costs thereof shall not be allocable to this contract for
(1) progress payments, or
(2) termination settlements if the contract is terminated for the convenience of the Government.
(h) The Government may waive the requirement for first article approval test where supplies identical or similar to those called for in the schedule have been previously furnished by the offeror/contractor and have been accepted by the Government. The offeror/contractor may request a waiver.
(The above Clause/Provision has been modified.)
52.209-4 FIRST ARTICLE APPROVAL--GOVERNMENT TESTING (SEP 1989)
(IAW FAR 9.308-2(a)(1), FAR 9.308-2(b)(1))
(a) The Contractor shall deliver 1 units(s) of Lot/Item 0001/0003 within 120 calendar days from the date of this contract to the Government at See Line Items for first article tests. The shipping documentation shall contain this contract number and the Lot/Item identification. The characteristics that the first article must meet and the testing requirements are specified elsewhere in this contract.
(b) Within 120 calendar days after the Government receives the first article, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval shall state any further action required of the Contractor.
A notice of disapproval shall cite reasons for the disapproval.
(c) If the first article is disapproved, the Contractor, upon Government request, shall submit an additional first article for testing. After each request, the Contractor shall make any necessary changes, modifications, or repairs to the first article or select another first article for testing. All costs related to these tests are to be borne by the Contractor, including any and all costs for additional tests following a disapproval. The Contractor shall furnish any additional first article to the Government under the terms and conditions and within the time specified by the Government. The Government shall act on this first article within the time limit specified in paragraph (b) above. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule or for any additional costs to the Government related to these tests.
(d) If the Contractor fails to deliver any first article on time, or the Contracting Officer disapproves any first article, the Contractor shall be deemed to have failed to make delivery within the meaning of the Default clause of this contract.
(e) Unless otherwise provided in the contract, the Contractor—
(1) May deliver the approved first article as a part of the contract quantity, provided it meets all contract requirements for acceptance and was not consumed or destroyed in testing; and
(2) Shall remove and dispose of any first article from the Government test facility at the Contractor's expense.
(f) If the Government does not act within the time specified in paragraph (b) or (c) above, the Contracting Officer shall, upon timely written request from the Contractor, equitably adjust under the Changes clause of this contract the delivery or performance dates and/or the contract price, and any other contractual term affected by the delay.
(g) The Contractor is responsible for providing operating and maintenance instructions, spare parts support, and repair of the first article during any first article test.
(h) Before first article approval, the acquisition of materials or components for, or the commencement of production of, the balance of the contract quantity is at the sole risk of the Contractor. Before first article approval, the costs thereof shall not be allocable to this contract for
(1) progress payments, or
(2) termination settlements if the contract is terminated for the convenience of the Government.
(i) The Government may waive the requirement for first article approval test where supplies identical or similar to those called for in the schedule have been previously furnished by the Offeror/Contractor and have been accepted by the Government. The Offeror/Contractor may request a waiver.
(The above Clause/Provision has been modified.)
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (JAN 2025)
(IAW FAR 22.1803)
(c) Web site. Information on registration for and use of the EVerify program can be obtained via the Internet at the Department of Homeland Security Web site: https://www.eVerify.gov .
PART III LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J
LIST OF ATTACHMENTS
Form Number Description/File Name Date Number of Pages Data_Requirments_6150004062757AH.pdf
Data_Requirments_6150004508175AH.pdf
EDL_6150004062757AH.pdf
EDL_6150004508175AH.pdf
Packaging.pdf
SOW.pdf
Transportaion.pdf
CDRL_FA_CPP_A001_A002_A003.pdf