SUBMITTAL REGISTER SUMMARY
This is a Submittal Register for federal construction contract WWYK190217 titled "Repair Perimeter Fence, FMO to SW Corner of Housing" located at Tinker Air Force Base. The document serves as a comprehensive tracking matrix for all required contractor submittals throughout the project lifecycle, organized by specification section and submittal type. The register contains 139 line items specifying required submittals with their associated activity numbers, transmittal numbers, submittal descriptions, specification sections, paragraph references, and classification designations (Government or A/E reviewer approval required).
The register encompasses preconstruction submittals including health and safety plans, environmental compliance documentation, construction schedules, quality control plans, and site staging requests; product data and shop drawings for fence assemblies, electrical systems, lighting infrastructure, and site work; test reports for grounding systems, material testing, and field quality control; certificates of compliance and training documentation; manufacturer's instructions and operation/maintenance manuals; and closeout submittals including as-built drawings, record drawings, and certification of designated items. Key specification sections addressed include general requirements (00-series), site work and demolition (02 and 31 series), fence systems (32 series including chain link and ornamental fencing), electrical systems (26 series), and utility infrastructure (33 and 34 series). Submittals marked with "G" designation require Government approval, with specific timing requirements noted in remarks columns, such as weekly schedule updates, monthly hazardous material usage reports during construction, and debris management reports. The document provides a structured framework for contractor compliance and project documentation throughout all phases of the fence repair and site rehabilitation work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Att11_190217_Drawings.pdf | ||
| Att9_190217_SOW.pdf | ||
| Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
Line Activ ity #
Transm ittal #
Specification Section
SD
# Submittal Description Item Submitted Paragraph #
Classification:
GOVT or A/E
Reviewer Submit
Approval Needed
By
Material Needed
By Action Code
Date Of Action
Date FWD to APPR / Auth
Date RCD From
CONTR
Date FWD To Other Revwr
Date RCD From Other Reviewer
Action Code
Date Of Action
Mailed To CONTR/ Date
RCD From
APPR
Authority Remarks
1 00 70 00 07 Certificates Welding, Cutting and Brazing Permit 1.4 G
2 00 71 00 01 Preconstruction Submittals Health and Safety Plan 1.3 G
3 00 71 00 07 Certificates Safety Meetings 1.3
4 00 71 00 07 Certificates FOD Awareness and Prevention Training 1.4
5 00 72 00 01 Preconstruction Submittals Restoration Plan 1.3.2 G
6 00 72 00 01 Preconstruction Submittals Storm Water Pollution Prevention Plan 1.3.3.2 G
7 00 72 00 01 Preconstruction Submittals AF Form 3952 Chemical/Hazardous Material Request/Authorization 1.4 G
8 00 72 00 01 Preconstruction Submittals Environmental Management System Awareness Training 1.10
9 00 72 00 03 Product Data Affirmative Procurement Documentation or Green Statement 1.3.9 G Provide only one. Reference specification for additional information
10 00 72 00 07 Cerificates Fire Ant Federal Compliance Agreement or state phyto-sanitary certificate 1.3.4.1
11 00 72 00 07 Cerificates Monthly Hazardous Material Usage Report 1.4 G Provide 1st week of each month during construction
12 00 72 00 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data Sheets 1.4
13 00 72 00 11 Closeout Submittals Notice of Termination (ODEQ Form 640-572) 1.3.3.2 G
14 00 72 00 - Attch 5 01 Preconstruction Submittals Construction Debris Analysis Plan 1.2.3 G
15 00 72 00 - Attch 5 07 Certificates Monthly Debris Management Report 2 G Provide 1st week of each month during construction
16 00 72 00 - Attch 11 01 Preconstruction Submittals Tree Planting/Removal Permit 1.1 G
17 00 72 00 - Attch 11 01 Preconstruction Submittals Tree Protection Plan 2.1 G
18 01 32 16.00 20 01 Preconstruction Submittals Baseline Construction Schedule 1.2 G Provide within 10 days of NTP.
19 01 32 16.00 20 07 Certificates Monthly Updates 1.4 Provide 1st week of each month during construction, or as directed by CO
20 01 32 16.00 20 07 Certificates 3-Week Look Ahead Schedule 1.6 Provide weekly with the Contract Progress Report
21 01 33 00 01 Preconstruction Submittals Submittal Register 1.8 G
22 01 45 00.00 10 01 Preconstruction Submittals Quality Control (QC) Plan 3.2 G
23 01 45 00.00 10 06 Test Reports QC Documentation 3.9 Provide weekly with the Contract Progress Report
24 01 50 00 01 Preconstruction Submittals Request for Contractor Staging Area 1.1 G
25 01 50 00 01 Preconstruction Submittals Photographic Record 1.3
26 01 78 00 03 Product Data Warranty Letter 1.7.1
27 01 78 00 03 Product Data Warranty Tags 1.7.3
28 01 78 00 03 Product Data Spare Parts Data 1.5
29 01 78 00 08 Manufacturer's Instructions Instructions 1.7.1
30 01 78 00 10 Operation and Maintenance Data Operation and Maintenance Manuals 3.4 G
31 01 78 00 11 Closeout Submittals Working As-Built Drawings 3.1 G Provide (2) electronic sets (optical media) and (2) hard copies
32 01 78 00 11 Closeout Submittals Record Drawings 3.3 G Provide (2) electronic sets (optical media) and (1) hard copy
33 01 78 00 11 Closeout Submittals Certification of EPA Designated Items 2.3 G
34 01 78 00 11 Closeout Submittals Certification Of USDA Designated Items 2.4 G
35 SOW 07 Certificates Contract Progress Report(s) 2.4 G Provide weekly throughout life of contract. Utilize AF Form 3065, Contract Progress Report (or equal)
36 02 41 00 1 Preconstruction Submittals Demolition Plan 1.2.2 G 37 02 41 00 1 Preconstruction Submittals Existing Conditions 1.9 38 02 41 00 7 Certificates Notification 1.6 G 39 26 20 00 2 Shop Drawings Panelboards 2.8 G 40 26 20 00 3 Product Data Receptacles 2.7 41 26 20 00 3 Product Data Meter Base Only 2.14 G 42 26 20 00 3 Product Data Surge Protective Devices 2.15 G 43 26 20 00 6 Test Reports 600-volt Wiring Test 3.5.2 G 44 26 20 00 6 Test Reports Grounding System Test 3.5.4 G 45 26 20 00 10 Operation and Maintenance Data Electrical Systems 1.5.1 G 46 26 56 00 2 Shop Drawings Luminaire Drawings 1.5.1.1 G 47 26 56 00 2 Shop Drawings Pole Drawings 1.5.1.2 G 48 26 56 00 3 Product Data Luminaires 2.2 G 49 26 56 00 3 Product Data Light Sources 2.3 G 50 26 56 00 3 Product Data LED Drivers 2.4 G 51 26 56 00 3 Product Data Luminaire Warranty 1.7.1 G 52 26 56 00 3 Product Data Lighting Controls Warranty 1.7.2 G 53 26 56 00 3 Product Data Pole Warranty 1.7.3 G 54 26 56 00 3 Product Data Poles 2.6 G 55 26 56 00 3 Product Data Brackets 2.6.2 56 26 56 00 3 Product Data Obstruction Marker Luminaires G 57 26 56 00 5 Design Data Luminaire Design Data 1.5.2 G 58 26 56 00 5 Design Data Photometric Plan 1.5.4 G 59 26 56 00 6 Test Reports Pressure Treated Wood Pole Quality 1.5.3 G 60 26 56 00 8 Manufacturer's Instructions Poles 2.6 61 26 56 00 10 Operation and Maintenance Data Lighting System 1.8.1 G
(d)
CONTRACTOR
ACTION
CONTRACTOR SCHEDULE
DATES APPROVING AUTHORITY
TITLE: WWYK190217
SUBMITTAL REGISTER
JOB NAME: REPAIR PERIMETER FENCE, FMO TO SW CORNER OF HOUSING
LOCATION: TINKER AFB
CONTRACT NO:
CONTRACTOR:
Submittal Register_v3_03/07/22
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
Line Activ ity #
Transm ittal #
Specification Section
SD
# Submittal Description Item Submitted Paragraph #
Classification:
GOVT or A/E
Reviewer Submit
Approval Needed
By
Material Needed
By Action Code
Date Of Action
Date FWD to APPR / Auth
Date RCD From
CONTR
Date FWD To Other Revwr
Date RCD From Other Reviewer
Action Code
Date Of Action
Mailed To CONTR/ Date
RCD From
APPR
Authority Remarks
(d)
CONTRACTOR
ACTION
CONTRACTOR SCHEDULE
DATES APPROVING AUTHORITY
62 31 00 00 1 Preconstruction Submittals Dewatering Work Plan 1.6.3 G 63 31 00 00 3 Product Data Utilization of Excavated Materials 3.8 G
64 31 00 00 3 Product Data Opening of any Excavation or Borrow Pit 3.3
65 31 00 00 6 Test Reports Testing 3.12 G 66 31 00 00 6 Test Reports Borrow Site Testing 2.1 G 67 31 00 00 7 Certificates Testing 3.12 68 31 11 00 1 Preconstruction Submittals Herbicide Application Plan 3.1.1 69 31 11 00 3 Product Data Tree Wound Paint 2.1.1 70 31 11 00 3 Product Data Herbicides 1.3.2 G 71 31 11 00 7 Certificates Qualifications 1.3.2 G 72 31 11 00 11 Closeout Submittals Pest Management Report 3.5.1 73 32 31 13 2 Shop Drawings Fence Assembly 2.1 G
74 32 31 13 2 Shop Drawings Location of Gate, Corner, End, and Pull Posts 3.2.2.1 G
75 32 31 13 2 Shop Drawings Gate Assembly 2.1 G 76 32 31 13 2 Shop Drawings Gate Hardware and Accessories 2.3.6 G 77 32 31 13 2 Shop Drawings Erection/Installation Drawings Part 3 G 78 32 31 13 3 Product Data Fence Assembly 2.1 G 79 32 31 13 3 Product Data Gate Assembly 2.1 G 80 32 31 13 3 Product Data Gate Hardware and Accessories 2.3.6 G 81 32 31 13 3 Product Data Zinc Coating 2.4.1 G 82 32 31 13 3 Product Data PVC Coating 2.1 G 83 32 31 13 3 Product Data Fabric 2.2.1 G 84 32 31 13 3 Product Data Stretcher Bars 2.2.6 G 85 32 31 13 3 Product Data Concrete 2.4.2 G 86 32 31 13 4 Samples Fabric 2.2.1 G 87 32 31 13 4 Samples Posts 2.2.2 G 88 32 31 13 4 Samples Braces 2.2.3 G 89 32 31 13 4 Samples Line Posts 2.2.2.1.1 G 90 32 31 13 4 Samples Sleeves 2.2.5 G 91 32 31 13 4 Samples Top Rail 2.2.3.1 G 92 32 31 13 4 Samples Bottom Rail 2.2.3.3 G 93 32 31 13 4 Samples Tension Wire 2.2.8 G 94 32 31 13 4 Samples Stretcher Bars 2.2.6 G 95 32 31 13 4 Samples Gate Posts 2.3.1 G 96 32 31 13 4 Samples Gate Hardware and Accessories 2.3.6 G 97 32 31 13 4 Samples Padlocks 2.3.5 G 98 32 31 13 4 Samples Wire Ties 2.2.4 G 99 32 31 13 7 Certificates Certificates of Compliance 1.3.1
100 32 31 13 8 Manufacturer's Instructions Fence Assembly 2.1 101 32 31 13 8 Manufacturer's Instructions Gate Assembly 2.1 102 32 31 13 8 Manufacturer's Instructions Hardware Assembly 2.1 103 32 31 13 8 Manufacturer's Instructions Accessories 2.1 104 32 31 13 11 Closeout Submittals Recycled Material Content 3.3 105 32 31 13.53 2 Shop Drawings Fence Installation Drawings 3.2.1 G 106 32 31 13.53 3 Product Data Fabric 2.1.1.1 107 32 31 13.53 3 Product Data Posts 2.1.2 108 32 31 13.53 3 Product Data Chain Link Braces 2.1.3 109 32 31 13.53 3 Product Data Line Posts 2.1.3 110 32 31 13.53 3 Product Data Sleeves 111 32 31 13.53 3 Product Data Rails 2.1.3 112 32 31 13.53 3 Product Data Tension Wire 113 32 31 13.53 3 Product Data Barbed Wire 2.2.1.2 114 32 31 13.53 3 Product Data Barbed Wire Supporting Arms 2.1.2.2 115 32 31 13.53 3 Product Data Latches 2.1.4.3 116 32 31 13.53 3 Product Data Hinges 2.1.4.3 117 32 31 13.53 3 Product Data Stops 2.1.4.3 118 32 31 13.53 3 Product Data Keepers 2.1.4.3 119 32 31 13.53 3 Product Data Padlocks 2.1.6 120 32 31 13.53 3 Product Data Wire Ties 2.2.1.1 121 32 31 13.53 3 Product Data Ornamental Fence Systems 122 32 31 13.53 3 Product Data Swing Gates 2.1.5.1 123 32 31 13.53 3 Product Data Fence Fabric Reinforcement 2.3 124 33 71 01 3 Product Data Conductors 2.5 G 125 33 71 01 3 Product Data Insulators G 126 33 71 01 3 Product Data Wood Poles 2.2.1 127 33 71 01 6 Test Reports Field Test Plan G 128 33 71 01 6 Test Reports Field Quality Control 3.4 G 129 33 71 01 6 Test Reports Ground Resistance Test Reports 1.5.3 G 130 33 71 01 6 Test Reports Sag and Tension Test G 131 33 71 01 6 Test Reports Low-Voltage Cable Test 3.4.3 G 132 33 71 01 6 Test Reports Acceptance Checks and Tests 3.4.4 133 33 71 01 7 Certificates Wood Poles 2.2.1 G 134 33 71 01 7 Certificates Wood Crossarms 2.3.1 G 135 33 71 01 9 Manufacturer's Field Reports Operation and Maintenance Manuals 1.6 G 136 33 71 01 9 Manufacturer's Field Reports Operation and Maintenance Manuals 1.6.1 G 137 33 71 01 10 Operation and Maintenance Data Operation and Maintenance Manuals 1.6 G 138 33 71 01 10 Operation and Maintenance Data Operation and Maintenance Manuals 1.6.1 G 139 34 71 13.16 8 Manufacturer's Instructions End Anchorage
Submittal Register_General Requ
File details come from the government source that posted it. Updated .