Amendment to incorporate questions and answers and to extend the due date for proposals.

View the file

Other files

File Type Posted
10-Q-0238-0003.pdf PDF
FA8125-10-Q-0238-0002.pdf PDF
The normal operating height as the maximum height should be 14.docx DOCX document
TO 35-1-3.pdf PDF
FA8125-10-Q-0238.pdf PDF
SLEP Tail Stand SOW.pdf PDF
SLEP Tail Stand Specs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F3YCDL0099A001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

To add questions and answ ers and to extend the due date for proposals

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 21-Apr-2010

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA8125-10-Q-0238

X 9B. DATED (SEE ITEM 11)

15-Apr-2010

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

21-Apr-2010

CODE

OC-ALC/PKEA

LEIGH ANN NUNN/405-739-5194

3001 STAFF DR 2S76

TINKER AFB OK 73145-3303

FA8125 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

FA8125-10-Q-0238

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 23-Apr-2010 10:00 AM to 30-Apr-2010 10:00 AM.

The following have been added by full text:

QUESTIONS AND ANSWERS

E-3 Tail Stand Questions and Answers as of 19 April 2010

Questions:

1. Reference plan view on the drawing: Will a second stair be required on the left-hand side of the platform? If no stair is required, is the 4 ft x 4 ft landing still required? Please clarify the 4 x 4 landing without stair.

2. Drawing: Reference 8 ft x 6'-3 platform area on Left-Hand side: Is a similar platform section (8 x 6-3) required on the Right-Hand side?

3. What are the preferred materials of construction----Steel or aluminum? If aluminum is used what is the paint requirement?

4. In the drawing there is a cowl on a track. What is the purpose and how much weight must it bear?

5. I was going to quote the stand fabricated from aluminum. Is this acceptable?

6. What should the deck be ?

7. I was going to hinge the steps/ships ladder. Is this OK?

8. I am assuming that the guardrails in the location of the aircraft clearance are to adjust horizontally not vertically. Is this correct?

9. What is a slider?

10. I was going to put bumpers on the end of the slider and the ends and first 12 inches of the adjustable guardrails. Is this correct?

11. I was not going to include any type of controller for the pneumatic screw jacks. Is this correct?

12. Is there a requirement for explosion proof electrical?

13. Can the decking material be standard grating or should it be a solid material.

14. Please clarify the paint requirements, I have not been able to locate or download a copy of Tech. Order 35-1-3.

15. Contractor shall include as part of the stand adjustable sliders with bumpers which can extend from the floor of the stand to the surface of the aircraft. See section B-3 of attached drawing for location.

16. The SOW specifies the use of pneumatically driven screw jacks. We are unfamiliar with that type of lifting mechanism and have been unable to source them. We have been able to locate motor-driven screw jacks but nothing air-powered.

Answers:

1. A stair on the left hand side is not necessary. The platform is for access to the horizontal stabilizer.

2. A second platform is not required on the right side. Other operations will take place in that section of the aircraft which would have interference from another platform.

3. Most of the stands we have purchased before are made primarily of steel with some aluminum parts that are non-load-bearing. The steel components need to be painted. I don't believe aluminum parts need to be painted.

4. That is a tail access stand that must support 500 lbs.

5. Most stands I have seen are made with steel. However, we did not specify the construction material in the statement of work. However the contractor wants to meet the requirements.

6. This is up to the contractor. However they want to meet the load requirements. Metal decking would suffice. This is how most of our stands are constructed.

7. It would seem that the steps need to be hinged in order to translate as the stand height adjusts.

8. The guardrails do need to adjust horizontally.

9. A slider is a floor extension that can extend and retract.

10. Bumpers are needed on the sliders and the adjustable guardrails.

11. The pneumatic screw jacks need to have some means of operation. This can be as simple as an up or down switch.

12. There is only a requirement to keep all electrical a minimum of 18 inches from the ground.

13. This is up to the contractor. However they want to meet the load requirements. Metal decking would suffice. This is how most of our stands are constructed.

14. T.O. 35-1-3 is available online and is attached.

15. The sliders are able to extend out from the floor horizontally toward the aircraft to make up the gap between the stand and the aircraft. This is for fall protection purposes so that personnel cannot fall through the gap. The ends need to have bumpers on them so that they cannot damage the aircraft if used improperly.

16. This is not a typo. We are requesting pneumatically driven screw jacks. We have this equipment in use now and is the preferred method. The same compressed air supply for the connections on top of the stand can also be used for the pneumatic screw jacks.