JUSTIFICATION FOR OTHER THAN FULL ANO OPEN COMPETITION

I. ContractingActivity

United States Air Force

AFSC/PZA

3001 Staff Drive

Tinker AFB, Ok. 73145

Purchase Request (PR) FD20301500473

II. Nature and/or description of the action being processed.

This individual Justification and Approval (J&A) authorizes the use of other than full and open competition procedures to obtain a follow-on, firm-fixed price Indefinite Delivery Requirements-type contract. The contemplated contract is for repair of the B-2 Fuel Control Vent Valve from Parker-Hannifin Corporation, Commercial and Government Entity code 59211. In accordance with (!AW)

FAR Part 16, a 1-year basic contract with four, 1-year options is considered to be appropriate for this acquisition. The estimated total value of thls award is with an estimated award date of October 31, 2017.

Previous Contract Number: FA8119-10-D-0013 Date of Award 09/30/2010 Completion Date 09/29/2015 Basis of Award: Sole Source

This contract will be established using a best estimated quantity (BEQ).

111, Description of supplies/services required to meet agency needs

Repair: An end item repair is the action taken to return the end item to a servlceabte condition by replacing all exposed consumable items and only the damaged recoverable parts that do not meet the specified inspection criteria. Repair consists of end item testing to determine deficiencies, disassembly as required to support maintenance actions required, thorough cleaning, refurbishment or replacement of all disturbed components not meeting inspection criteria replacement of all disturbed components not meeting inspection criteria, replacement of all soft parts {seals, gaskets,etc.) exposed during repair, re-assembly of assemblies and subassemblies, performance of all adjustments and alignments, test and calibration of subassemblies and end items, and final inspection (e.g. safety wiring, painting, affixing decals) IAW the applicable publlcation and approved test documentation.

Dollar values listed below reflect the anticipated total contract cost. Under the contemplated contract, Parker-Hannifin Corporation will provide the repair of the 8-2 Manifold Valve Assembly, (Fuel Control Vent Valve) as described below. This acquisition is for a non-personal service. The total estimated award amount is .

Contract Summary

Estimated Year Estimated Dates Dollars

Basic 31 Oct17- 30 Oct 18

Option l 310ct18-30Nov19

Option II 31 Oct 19 30 Oct 20

Option Ill 31 Oct 20 30 Oct 21

Option IV 31 Oct 21- 30 Oct 22

Total Contract 31 Oct 17 30 Oct 22