Attachment_1_Pricing_Matrix.xlsx
XLSX spreadsheet 38 KB Posted
- Solicitation number
- FA8117-19-R-0037
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA811719R0037.pdf | ||
| DID_81832.pdf | ||
| 2949919_CDRL1_REPORT.pdf | ||
| DID_80969.pdf | ||
| DID_80229D.pdf | ||
| DID_80441C.pdf | ||
| 2918710_TRNSPDATA_REPORT.pdf | ||
| DID_81634C.pdf | ||
| 2918709_PKGRQMT_REPORT.pdf | ||
| DID_80639D.pdf | ||
| DID_81534A.pdf | ||
| 2918719_SP_PACKAGING.pdf | ||
| 2943961_PWS.pdf | ||
| DID_81838.pdf | ||
| DID_81995.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| Source Selection Information - See FAR 2.101 and 3.104 |
| T-38 Displacement Gyroscope |
| Attachment 1 - Pricing Matrix |
| Instructions to complete this Pricing Matrix: |
| 1 | Offerors are to input the proposed unit prices on this Pricing Matrix spreadsheet, TEP Worksheet, Column F, in ALL yellow highlighted cells. |
| 2 | Rounding: All dollar amounts shall be rounded to two decimal places. |
| 3 | The extended price will be automatically calculated by multiplying the proposed unit price by the estimated quantity. |
| 4 | A subtotal price will be automatically calculated at the bottom of each year. |
| 5 | The Total Evaluated Price (TEP) will automatically calculate at the top of the TEP Worksheet. |
| 6 | If deemed necessary, the Offeror may provide additional rationale in the "Additional Rationale (Optional)" worksheet |
TEP
| TEP (Total Evaluated Price) |
| USE DATA BELOW TO PROVIDE QUOTE |
| PERIOD OF PERFORMANCE | PRICE |
| ESTIMATED TOTAL PRICE FOR BASE PERIOD | $0.00 |
| ESTIMATED TOTAL PRICE FOR OPTION YEAR I | $0.00 |
| ESTIMATED TOTAL PRICE FOR OPTION YEAR II | $0.00 |
| ESTIMATED TOTAL PRICE FOR OPTION YEAR III | $0.00 |
| ESTIMATED TOTAL PRICE FOR OPTION YEAR IV | $0.00 |
| ESTIMATED TOTAL PRICE FOR 52.217-8 | $0.00 |
TOTAL EVALUATED PRICE (TEP) = (BASE + 4 OPTION YEARS and 52.217-8) $0.00
| BASE PERIOD (28 May 2020 - 27 May 2021) | |||||
| CLIN | NSN | CLIN DESCRIPTION | UNIT | UNIT PRICE | TOTAL PRICE |
| 0001 | 6615-01-131-5317 | Repair of T-38 Displacement Gyroscope | 60 | $0.00 | |
| 0002 | 6615-01-131-5317 | No Fault Found | 1 | $0.00 | |
| 0003 | 6615-01-131-5317 | Beyond Economic Repair | 1 | $0.00 | |
| 0004 | 6615-01-131-5317 | Over and Above | 1 | TBN | TBN |
| 0005 | 6615-01-131-5317 | Over and Above Expedite Fee | 1 | TBN | TBN |
| 0006 | N/A | Contract Data Requirements List (CDRL) | 1 | NSP | NSP |
| BASE PERIOD TEP | $0.00 | ||||
| OPTION I (28 May 2021 - 27 May 2022) | |||||
| CLIN | NSN | CLIN DESCRIPTION | UNIT | UNIT PRICE | TOTAL PRICE |
| 1001 | 6615-01-131-5317 | Repair of T-38 Displacement Gyroscope | 48 | $0.00 | |
| 1002 | 6615-01-131-5317 | No Fault Found | 1 | $0.00 | |
| 1003 | 6615-01-131-5317 | Beyond Economic Repair | 1 | $0.00 | |
| 1004 | 6615-01-131-5317 | Over and Above | 1 | TBN | TBN |
| 1005 | 6615-01-131-5317 | Over and Above Expedite Fee | 1 | TBN | TBN |
| 1006 | N/A | Contract Data Requirements List (CDRL) | 1 | NSP | NSP |
| OPTION I PERIOD TEP | $0.00 | ||||
| OPTION II (28 May 2022 - 27 May 2023) | |||||
| CLIN | NSN | CLIN DESCRIPTION | UNIT | UNIT PRICE | TOTAL PRICE |
| 2001 | 6615-01-131-5317 | Repair of T-38 Displacement Gyroscope | 48 | $0.00 | |
| 2002 | 6615-01-131-5317 | No Fault Found | 1 | $0.00 | |
| 2003 | 6615-01-131-5317 | Beyond Economic Repair | 1 | $0.00 | |
| 2004 | 6615-01-131-5317 | Over and Above | 1 | TBN | TBN |
| 2005 | 6615-01-131-5317 | Over and Above Expedite Fee | 1 | TBN | TBN |
| 2006 | N/A | Contract Data Requirements List (CDRL) | 1 | NSP | NSP |
| OPTION II PERIOD TEP | $0.00 | ||||
| OPTION III PERIOD (28 May 2023- 27 May 2024) | |||||
| CLIN | NSN | CLIN DESCRIPTION | UNIT | UNIT PRICE | TOTAL PRICE |
| 3001 | 6615-01-131-5317 | Repair of T-38 Displacement Gyroscope | 48 | $0.00 | |
| 3002 | 6615-01-131-5317 | No Fault Found | 1 | $0.00 | |
| 3003 | 6615-01-131-5317 | Beyond Economic Repair | 1 | $0.00 | |
| 3004 | 6615-01-131-5317 | Over and Above | 1 | TBN | TBN |
| 3005 | 6615-01-131-5317 | Over and Above Expedite Fee | 1 | TBN | TBN |
| 3006 | N/A | Contract Data Requirements List (CDRL) | 1 | NSP | NSP |
| OPTION III PERIOD TEP | $0.00 | ||||
| OPTION IV PERIOD (28 May 2024 - 27 May 2025) | |||||
| CLIN | NSN | CLIN DESCRIPTION | UNIT | UNIT PRICE | TOTAL PRICE |
| 4001 | 6615-01-131-5317 | Repair of T-38 Displacement Gyroscope | 48 | $0.00 | |
| 4002 | 6615-01-131-5317 | No Fault Found | 1 | $0.00 | |
| 4003 | 6615-01-131-5317 | Beyond Economic Repair | 1 | $0.00 | |
| 4004 | 6615-01-131-5317 | Over and Above | 1 | TBN | TBN |
| 4005 | 6615-01-131-5317 | Over and Above Expedite Fee | 1 | TBN | TBN |
| 4006 | N/A | Contract Data Requirements List (CDRL) | 1 | NSP | NSP |
| OPTION IV PERIOD TEP | $0.00 | ||||
| 52.217-8 CLAUSE (6 MONTH EXTENSION) | |||||
| CLIN | NSN | CLIN DESCRIPTION | UNIT | UNIT PRICE | TOTAL PRICE |
| TBD | 6615-01-131-5317 | Repair of T-38 Displacement Gyroscope | 24 | $0.00 | |
| TBD | 6615-01-131-5317 | No Fault Found | 1 | $0.00 | |
| TBD | 6615-01-131-5317 | Beyond Economic Repair | 1 | $0.00 | |
| TBD | 6615-01-131-5317 | Over and Above | 1 | TBN | TBN |
| TBD | 6615-01-131-5317 | Over and Above Expedite Fee | 1 | TBN | TBN |
| N/A | Contract Data Requirements List (CDRL) | 1 | NSP | NSP | |
| NOTE: Evaluation of options shall not obligate the Government to exercise such options. The six (6) month Extension Period is not to be considered part of Option Four (4) Period and will be a separate option exercise if it is utilized. | 6 MO EXT PERIOD TEP | $0.00 |
Additional Rationale (Optional) Offerors: If additional rationale is deemed pertinent to support the pricing in your pricing matrix, please provide it here.
File details come from the government source that posted it. Updated .