IAC_MAC_New_Major_Milestones_19July17.ppt
PPT presentation 284 KB Posted
- Attached to
- AFICA IAC MAC - DRAFT RFP Federal contract opportunity
- Solicitation number
- FA8075-17-R-0001
About this file
This document provides a projected schedule and key dates for the Air Force IAC MAC procurement. The draft RFP was posted on March 31st, with questions due by April 18th. An updated second draft RFP and answers to questions on the first draft will be released on July 19th. The final RFP will be issued on October 3rd, with past performance proposals due November 2nd and technical, cost and other proposals due November 17th. Evaluations will take place from March to April 2018, with discussions from April to May if needed. The estimated award date is September 30th, 2018. The contracting agency is the Air Force Installation Contracting Agency at Offutt Air Force Base, for the Defense Technical Information Center's Information Analysis Center Multiple Award Contract.
IAC MAC New Major Milestones. Estimating Final RFP will be posted in or around 3 October 2017.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| IAC_MAC_Draft_2nd_RFP_FBOPosted_19Jul17.docx | DOCX document | |
| IAC_MAC_Draft_RFP_Qs_and_Answers_19Jul17.xls | XLS spreadsheet | |
| IAC_MAC_Draft_RFP_FBO_Amend2_20Apr17.docx | DOCX document | |
| IAC_MAC_Draft_RFP_FBO_Amend1_7Apr17.docx | DOCX document | |
| IAC_MAC_Draft_RFP.docx | DOCX document | |
| IAC_MAC_Draft_RFP_Qs&As.xls | XLS spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Projected Schedule for IAC MAC As of 19 July 2017
| Action | Date |
| Draft RFP | 31 Mar 2017 |
| 2nd Draft RFP & Q & As from 1st Draft | 19 July 2017 |
| Final RFP | 3 Oct 2017 |
| Past Performance Proposals Received | 2 Nov 2017 (30 days) |
| Tech, Cost & Other Proposals Received | 17 Nov 2017 (45 days) |
| Initial Evaluation Brief | Mar/Apr 2018 |
| Conduct Discussions (as necessary) | Apr 18 – May 18 |
| Estimated Award Date | 30 Sept 2018 |
Posted to FedBizOpps 19 July 2017.
File details come from the government source that posted it. Updated .