SOW - Bldg 323C Rm 331 - Wall Demo Draft.pdf

PDF 353 KB Posted

Attached to
Interior Office Renovation and Wall Removal - Offutt AFB
Solicitation number
FA7014-27-CP-0001
Issued by

About this file

This is a Statement of Work (SOW) for a Task Order for interior office renovation and wall removal at Offutt Air Force Base, Nebraska, Building 323C, Room 331. The project is a Firm-Fixed-Price Design-Build Minor Construction contract to remove two designated interior partition walls (approximately 20 linear feet total) from an estimated 11-foot by 9-foot office space and restore the area to an open-concept layout.

The Contractor must provide all labor, materials, equipment, management, supervision, and transportation to complete selective demolition and architectural/electrical make-good work. Key tasks include: site assessment and utility verification to identify structural, plumbing, communications, and electrical elements within the walls; erection of full-height temporary poly dust barriers with HEPA-filtered negative air machines; safe removal of drywall, framing studs, baseboards, trim, and door assemblies; legal disposal of demolition debris off-installation; de-energization and relocation of electrical circuits and low-voltage lines to perimeter walls in compliance with NFPA 70; repair and modification of the suspended acoustic tile ceiling grid and replacement of damaged tiles; inspection and repositioning of fire sprinkler heads and emergency fixtures per NFPA 13 and NFPA 101; floor slab preparation, patching, and installation of matching flooring material with seamless transitions; and drywall patching to Level 4 finish, priming, and painting with low-VOC commercial-grade latex paint, plus installation of matching resilient wall base.

The work will be performed in an occupied administrative facility requiring maintenance of emergency egress routes, limitation of noise-generating activities to designated off-peak or after-hours windows as coordinated with the Contracting Officer and Facility Point of Contact, daily HEPA vacuuming and cleanup of transit paths, and compliance with OSHA standards and USACE EM 385-1-1. Any utility interruptions must be submitted in writing at least five business days prior to the requested shutdown. All Contractor personnel must comply with base security requirements and obtain temporary visitor/contractor badges. Required Personal Protective Equipment includes ANSI-approved hard hats, safety glasses with side shields, hearing protection during demolition, and steel-toed boots. A 10-pound ABC dry chemical fire extinguisher and fully stocked first-aid kit must remain on-site.

Within five business days of Task Order award, the Contractor shall submit a simplified Construction Planning Chart/Bar Chart Schedule depicting the sequence of work in seven phases: mobilization and site protection; electrical make-safe and rough-in disconnection; wall demolition and debris disposal; ceiling, sprinkler, and mechanical adjustments; drywall patching, finishing, and flooring infill; prime and finish painting with base trim installation; and final cleaning, punch list inspection, and closeout. Prior to beginning construction, the Contractor must submit: a Work and Demolition Plan; a Safety Plan/Activity Hazard Analysis covering utility lockout/tagout, dust control, and debris handling; and Material Product Data including flooring, drywall compounds, finish paint samples, acoustic ceiling tile cut sheets, and electrical device specifications. The Contractor's on-site Superintendent or Quality Control representative shall conduct daily oversight and provide concise daily reports summarizing work completed, personnel count, inspections performed, and field challenges. Should concealed utilities or unexpected conditions be discovered, work shall pause and an RFI shall be submitted to the Contracting Officer.

Upon completion, a joint pre-final inspection walkthrough will be conducted with the Contracting Officer and Facility POC to generate a punch list of any minor discrepancies. The Contractor shall complete all punch list corrective actions within three calendar days of receipt, followed by a final inspection for Government acceptance. The Contractor must thoroughly clean the work area, including wiping perimeter surfaces, dusting light fixtures, HEPA vacuuming floors, and removing all poly barriers, tape residue, and excess materials. A one-year workmanship warranty covering all construction workmanship, drywall finishes, and electrical work applies from the date of Government final acceptance in accordance with FAR 52.246-21. The Contractor shall provide a marked-up sketch or drawing indicating the revised open floor layout and relocated positions of electrical outlets, lighting switches, and junction boxes.

View the file

Other files

File Type Posted
Wall Removal.png PNG image
SS - Bldg 323C Rm 331 Wall Removal.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

TASK ORDER FOR INTERIOR OFFICE

RENOVATION & WALL REMOVAL

Project: Office Space Modernization & Wall Removal (One Office Size (Estimate of 11' x 9')) Location: Offutt Air Force Base, Nebraska / Bldg 323C, Room 331 Contract Type: Firm-Fixed-Price (FFP) / Design-Build Minor Construction

PART 1 – GENERAL SCOPE OF WORK

1.1 Purpose and Objective

The Contractor shall provide all labor, management, supervision, tools, materials, equipment, and transportation necessary to perform selective interior demolition and architectural/electrical make-good for an approximate 11 ft. x 9 ft. office footprint within Bldg 323C Room 331. The primary objective is the safe removal of two (2) designated interior walls to eliminate spatial separation and establish an open-concept layout, complete with all associated ceiling, electrical, mechanical, and architectural finish restorations.

1.2 Description of Work

The Contractor shall perform the following specific tasks:

1. Site Assessment & Utility Verification: Conduct pre-demolition investigations to confirm whether the two (2) designated partition walls contain structural load-bearing elements, plumbing lines, communications cabling, or active electrical branch circuits.

2. Dust Containment & Environmental Controls: Erect full-height temporary poly dust barriers (floor-to-ceiling) with zippered access and maintain HEPA-filtered negative air machines as needed to prevent dust, debris, and fumes from migrating into adjacent occupied areas.

3. Selective Demolition:

• Demolish and safely remove two (2) interior partition walls totaling approximately 20 linear feet (measuring along the 11' and 9' segments).

• Carefully remove existing drywall/gypsum board, metal/wood framing studs, baseboards, trim, and door assemblies (if present within the two walls).

• Legally haul away and dispose of all demolition debris off-installation in compliance with local, state, and federal environmental disposal regulations.

4. Electrical & Low-Voltage Rough-In / Relocation:

• De-energize, trace, and safely disconnect all wiring, outlets, switches, and communication/data lines embedded within the walls to be removed.

• Re-route or blank off existing circuits into perimeter walls or ceiling junction boxes in compliance with NFPA 70 (National Electrical Code).

• Reinstall light switches or convenience receptacles at designated new perimeter wall locations to maintain code compliance and functional room control.

5. Ceiling & Life Safety Systems Coordination:

• Repair and modify the existing suspended acoustic tile ceiling grid spanning the former wall partitions.

• Replace damaged grid tees and install matching ceiling tiles to provide an uninterrupted, continuous ceiling plane across the expanded space.

• Inspect existing fire sprinkler head spacing and emergency egress/lighting fixtures; adjust or reposition heads/fixtures if required to comply with NFPA 13 and NFPA 101 for the unified room configuration.

6. Floor Infill & Transitions:

• Prepare the exposed floor slab beneath the removed walls, removing adhesives, fasteners, and anchor bolts.

• Patch and level the slab substrate.

• Patch and install matching flooring material (e.g., carpet tile, luxury vinyl tile, or VCT) and seamless transition strips to ensure an even, trip-free finish matching adjacent floor areas.

7. Wall Finishes, Drywall Patching, and Paint:

• Repair adjacent intersecting drywall where the demolished walls tied into existing permanent structures.

• Tape, mud, sand, and finish drywall seams to a smooth Level 4 finish.

• Prime and paint all patched areas and contiguous perimeter walls with commercial-grade, low-

VOC latex paint (color and sheen to match existing facility standards or as specified by the Contracting Officer).

• Install matching resilient wall base (cove base) along newly opened wall boundaries.

PART 2 – SITE OPERATIONS & FACILITY

RESTRICTIONS

2.1 Occupied Facility Protocols

The work will be executed within an occupied administrative facility. The Contractor shall:

• Maintain unhindered emergency egress routes, corridors, and exit doors at all times.

• Limit noise-generating activities (e.g., power saws, hammer drills, structural chipping) to designated off-peak or after-hours windows as coordinated with the Contracting Officer (CO) and Facility Point of Contact (POC).

• Keep all shared public areas, hallways, and staging zones clean and free of trip hazards. Perform daily HEPA vacuuming and sweep-down of transit paths.

2.2 Utility Interruption and Coordination

Any required interruption to building services (electrical branch circuits, fire alarm, or fire suppression drainage/isolation) shall be submitted in writing to the Contracting Officer and Facility Manager at least five (5) business days prior to the requested shutdown. Unscheduled power or safety outages are strictly prohibited.

2.3 Security & Personnel Access

All Contractor personnel and delivery drivers must comply with base and facility entry security requirements. The Contractor shall submit all required personnel information for background screening and obtain temporary visitor/contractor badges prior to on-site mobilization. Badges must be always displayed and returned upon completion of the contract.

2.4 Safety and Health (EM 385-1-1 / OSHA)

• The Contractor shall maintain full compliance with OSHA construction safety standards and the current edition of USACE EM 385-1-1.

• All on-site personnel must wear required Personal Protective Equipment (PPE), including ANSI-approved hard hats, safety glasses with side shields, hearing protection during demolition, and steel-toed boots.

• A functional 10-lb ABC dry chemical fire extinguisher and a fully stocked first-aid kit must remain directly on-site throughout execution.

PART 3 – PROJECT MANAGEMENT,

SUBMITTALS & QUALITY CONTROL

3.1 Project Schedule

Within five (5) business days following Task Order award, the Contractor shall submit a simplified Construction Planning Chart / Bar Chart Schedule depicting the anticipated sequence of work:

8. Mobilization & Site Protection / Dust Barriers

9. Electrical Make-Safe & Rough-in Disconnection

10. Wall Selective Demolition & Debris Disposal

11. Ceiling Grid, Sprinkler, & Mechanical Adjustments

12. Drywall Patching, Finishing, & Flooring Infill

13. Prime & Finish Painting / Base Trim Installation

14. Final Cleaning, Punch List Inspection, and Closeout

3.2 Key Submittals

Prior to beginning construction or procurement of materials, the Contractor shall submit the following for Government review and approval:

• Work & Demolition Plan: Brief outline of demolition sequence, dust containment methods, and debris disposal route.

• Safety Plan / Activity Hazard Analysis (AHA): Site-specific safety measures covering utility lockout/tagout (LOTO), dust control, power tool safety, and debris handling.

• Material Product Data:

• Flooring patch/carpet tiles and adhesives (low-VOC).

• Drywall compounds and finish paint samples/cut sheets.

• Acoustic ceiling tile cut sheets matching existing patterns.

• Electrical devices, cover plates, and conduit fittings.

3.3 Quality Control & Daily Reporting

The Contractor’s on-site Superintendent or designated Quality Control representative shall conduct daily oversight to ensure workmanship complies with industry standards and the approved plans. The Contractor shall provide a concise daily report summarizing work completed, on-site personnel count, inspections performed, and any encountered field challenges.

3.4 Requests for Information (RFIs) & Differing Site Conditions Should concealed utilities, structural studs, or unexpected conditions be discovered within the walls during selective demolition, work in the immediate affected area shall pause. The Contractor shall promptly submit an RFI to the Contracting Officer detailing the issue and recommending technical solutions.

PART 4 – CLOSEOUT, INSPECTIONS &

WARRANTIES

4.1 Pre-Final and Final Punch-Out Inspections

• Pre-Final Inspection: Upon completion of all wall removal, patch-and-repair, painting, and electrical work, the Contractor shall conduct a joint walkthrough with the Contracting Officer and Facility POC.

A punch list of minor discrepancies (if any) will be generated.

• Final Acceptance: The Contractor shall complete all punch list corrective actions within three (3) calendar days of receipt. A final inspection will be held to confirm final acceptance.

4.2 Cleaning and Demobilization

The Contractor shall thoroughly clean the work area prior to final inspection. This includes wiping down all perimeter surfaces, dusting light fixtures, HEPA vacuuming floors, removing all poly barriers, tape residue, and excess materials, and restoring adjacent rooms to their original operational state.

4.3 Warranty and Record Deliverables

• Workmanship Warranty: The Contractor shall guarantee all construction workmanship, drywall finishes, and electrical work for a minimum period of one (1) year from the date of Government final acceptance, in accordance with FAR 52.246-21.

• Record Information / Red-Lines: The Contractor shall provide a marked-up sketch or drawing indicating the revised open floor layout and the relocated positions of electrical outlets, lighting switches, and junction boxes.

Office Size (Estimate of 11' x 9')

STATEMENT OF WORK (SOW)
TASK ORDER FOR INTERIOR OFFICE RENOVATION & WALL REMOVAL
PART 1 – GENERAL SCOPE OF WORK
1.1 Purpose and Objective
1.2 Description of Work
PART 2 – SITE OPERATIONS & FACILITY RESTRICTIONS
2.1 Occupied Facility Protocols
2.2 Utility Interruption and Coordination
2.3 Security & Personnel Access
2.4 Safety and Health (EM 385-1-1 / OSHA)
PART 3 – PROJECT MANAGEMENT, SUBMITTALS & QUALITY CONTROL
3.1 Project Schedule
3.2 Key Submittals
3.3 Quality Control & Daily Reporting
3.4 Requests for Information (RFIs) & Differing Site Conditions
PART 4 – CLOSEOUT, INSPECTIONS & WARRANTIES
4.1 Pre-Final and Final Punch-Out Inspections
4.2 Cleaning and Demobilization
4.3 Warranty and Record Deliverables