A-15 attachment 2 B129 AGE Shop - Specification.pdf
PDF 13 MB Posted
- Attached to
- Renovate/Add for AGE Shop/Offices B129 Federal contract opportunity
- Solicitation number
- FA671220B002
About this file
This document outlines a federal contract opportunity to renovate and add to an aircraft general equipment shop and offices at Pittsburgh Air Reserve Station. The solicitation is designated as a 100% HUBZone small business set-aside with a single award to be made. The project consists of renovating portions of Hangar 129 including remodeling shops, offices, bathrooms, storage rooms, and adding a 550 square foot addition for an aircraft jack stand tester. The contract value is estimated between $250,000 to $500,000 with a performance period of 270 calendar days. The solicitation will be posted on or around June 17, 2020 with offers due by July 17, 2020. The contract will be a firm-fixed-price awarded under NAICS code 236220 for construction of nonresidential structures with a size standard of $36.5 million in average annual receipts.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| F-1- B129 AGE Shop - IFC Submittal - 06-18-2020.pdf | ||
| A-15-attachment 3 Tech Spec B129 JLSS 170011.pdf | ||
| Solicitation - FA671221B0001.pdf | ||
| A1-Design B129 JLSS 170011.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For Official Use Only
PROJECT
MANUAL
SPECIFICATIONS
Renovate/Add for AGE Shop/Offices, B-129
JLSS 17-0011
Contract FA6712-17-D-0001
GTP 210-168
Construction Bid Set
Prepared By:
CDM Smith Inc.
503 Martindale St., Suite 400
Pittsburgh, PA 15212
911th Airlift Wing
Moon Township, PA
October 8, 2019
911th Airlift Wing, Renovate/Add for AGE Shop/Offices, B129 Contents
JLSS-17-0011 00 01 10-1
911th Airlift Wing
Renovate/Add for AGE Shop/Offices, B129
JLSS 17-0011
Technical Specifications
PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP
DIVISION 00 - PROCUREMENT REQUIREMENTS
000000 Cover Sheet
000110 Table of Contents
Balance of Requirements provided by 911th
SPECIFICATIONS GROUP
GENERAL REQUIREMENTS SUBGROUP
DIVISION 01 - GENERAL REQUIREMENTS
010100 Summary of Work
011400 Work Restrictions
013200 Construction Progress Documentation
013400 Submittal Procedures
014000 Quality Requirements
014100 Environmental Protection
014100a Final Hazmat Survey Report
015000 Temporary Facilities and Controls
015950 Safety Requirements
017300 Closeout Procedures
017389 Cutting and Patching
017830 Project Record Documents
018130 Green Procurement Requirements
018130a Green Procurement Reporting Form
FACILITIES CONSTRUCTION SUBGROUP
DIVISION 02 - EXISTING CONDITIONS
024119 Selective Demolition
DIVISION 03 - CONCRETE
030131 Modifications to Existing Concrete
031000 Concrete Formwork
031500 Concrete Joints and Joint Accessories
032000 Concrete Reinforcement
033000 Cast-In-Place Concrete
Construction Bid Set
JLSS-17-0011 00 01 10-2
DIVISION 03 - CONCRETE (CON’T)
033500 Concrete Finishes
036000 Grout
DIVISION 04 - MASONRY
042000 Unit Masonry
DIVISION 05 - METALS
051200 Structural Steel
053123 Steel Roof Deck
054000 Cold-Formed Metal Framing
055000 Miscellaneous Metals
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
061053 Miscellaneous Rough Carpentry
064000 Architectural Woodwork
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
072163 Continuous Insulation Support System
074213 Metal Wall Panels
075323 EPDM Roofing
079200 Joint Sealants
DIVISION 08 - OPENINGS
081113 Hollow Metal Doors and Frames
083323 Overhead Coiling Doors
087100 Door Hardware
DIVISION 09 - FINISHES
092116 Gypsum Board Assemblies
093013 Ceramic Tiling
095113 Acoustical Panel Ceilings
096513 Resilient Base and Accessories
096523 Resilient Flooring
097700 Special Wall Surfacing
099100 Painting
DIVISION 10 - SPECIALTIES
101400 Signage
102113 HPDE Toilet Compartments
102800 Toilet Accessories
105113 Metal Lockers
DIVISION 11 - DIVISION 20 - NONE
JLSS-17-0011 00 01 10-3
FACILITIES SERVICES SUBGROUP
DIVISION 21 - FIRE SUPPRESSION
211313 Wet-Pipe Sprinkler Systems
DIVISION 22 - PLUMBING
220517 Sleeves and Sleeve Seals for Plumbing Piping
220518 Escutcheons for Plumbing Piping
220523.12 Ball Valves for Plumbing Piping
220529 Hangers and Supports for Plumbing Piping and Equipment
220553 Identification for Plumbing Piping and Equipment
220719 Plumbing Piping Insulation
221116 Domestic Water and Compressed Air Piping
221316 Sanitary Waste and Vent Piping
DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
230553 Identification for HVAC Piping and Equipment
230593 Testing, Adjusting, and Balancing for HVAC
230713 Duct Insulation
232300 Refrigerant Piping
233113 Metal Ducts
233300 Air Duct Accessories
233346 Flexible Ducts
233423 HVAC Power Ventilators
DIVISION 26 - ELECTRICAL
260519 Low-Voltage Electrical Power Conductors and Cables
260523 Control-Voltage Electrical Power Cables
260526 Grounding and Bonding for Electrical Systems
260529 Hangers and Supports for Electrical Systems
260533 Raceway and Boxes for Electrical Systems
260544 Sleeves and Sleeve Seals for Electrical Raceways and Cabling
260553 Identification for Electrical Systems
262726 Wiring Devices
265119 LED Interior Lighting
265213 Emergency and Exit Lighting
DIVISION 27 – DIVISION 28 - NONE
SITE AND INFRASTRUCTURE SUBGROUP
DIVISION 31 - EARTHWORK
310515 Soils and Aggregates for Earthwork
312000 Earthwork
312319 Dewatering
312333 Trenching and Backfilling
312500 Erosion and Sedimentation Control
JLSS-17-0011 00 01 10-4
DIVISION 32 - SITE IMPROVEMENTS
321313 Concrete Paving
321723 Pavement Markings
DIVISION 33 – UTILITIES
330513 Manholes and Structures
334100 Storm Utility Drainage Piping
DIVISION 34 - DIVISION 39 - NONE
PROCESS EQUIPMENT SUBGROUP
DIVISION 40 - DIVISION 49 - NONE
911th Airlift Wing, Renovate/Add for AGE Shop/Offices, B129 Summary of Work
JLSS-17-0011 01 01 00 - 1
SECTION 01 01 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 TITLE OF WORK
A. Project includes one work scope at 911th Airlift Wing/LGC, 2550 Defense Avenue, Pittsburgh
IAP ARS, Moon Township, PA 15108-4495 as follows:
1. Renovate/Add for AGE Shop/Office, Building B129; Government’s Project Number JLSS
17-0011.
1.3 DEFINITIONS
A. Provide shall mean: to furnish all materials/equipment, to install all labor and services and to make the item of work or equipment fully complete, operable, and acceptable to intended use.
B. The words "Project Coordinator" used in some of these specifications shall refer to the
"Contracting Officer".
C. The word “Owner” shall refer to the “Government”.
D. The word “Architect” shall refer to the “Contracting Officer.”
E. The word “Engineer” shall refer to the “Contracting Officer.”
F. The word “Inspector” shall refer to the “Contracting Officer.”
G. Any referenced standards used are to be the latest version at the time of bidding.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The following Paragraphs are a general Summary of the Work. Review entire set of Contract
Documents for a comprehensive referencing of required work.
B. This project includes major two work scopes: restoration and modernization repair; and new building addition.
1. Renovate a portion of an existing one-story building with a mezzanine that consists of a larger high bay shop area and maintenance bay that is surrounded by office type spaces at one building perimeter. The project incorporates selective demolition and new work that includes general construction, plumbing, HVAC, and electrical work. In summary, the following work scopes include:
a. Remove existing interior walls and room finishes as indicated on Drawings.
b. Construct interior walls with metal studs and drywall, which shall be painted.
c. Provide new hollow metal doors, door frames, and hardware.
JLSS-17-0011 01 01 00 - 2
d. Provide new room finishes, which includes floors, base, walls, and ceilings.
e. Provide new wire mesh partitions to shop areas.
f. Provide casework, metal lockers, m toilet compartments, and toilet accessories.
g. Provide indoor equipment parking and tool crib.
h. Revise HVAC duct system per revised floor plan.
i. Remove existing plumbing fixtures and provide new fixtures.
j. Remove, replace, alter fire sprinkler system at effected areas. Center heads in ceiling tiles where applicable.
k. Provide new electrical wiring, devices, outlets, and lighting fixtures.
l. Provide new communications system, including wiring, data, telephone, fire alarm, and internet along with related racks, blocks, switches, and appurtenances.
2. Construct a minor single-story addition of approximately 550 square feet to accommodate an aircraft jack stand tester. In summary, the following work scopes include:
a. Perform excavation and construct new concrete footings, foundations, and concrete on-grade floor slab.
b. Construct exterior walls to match existing wall materials that include unit masonry and metal wall panels with related perimeter metal trim, and rain drainage.
c. Provide structural steel framing members, metal roof deck, rigid insulation, and roofing membrane.
d. Provide overhead coiling door, hinged doors, and door hardware.
e. Provide room finishes as scheduled on Drawings.
f. Provide unit heater, extend fire sprinkler system, electrical conduit, wiring, receptacles, and lighting.
g. Provide lightning protection system.
3. Perform related site work that includes new bollards, create outdoor equipment storage area on concrete paving adjacent to Building B129, concrete paving restoration, catch basin, and ductile iron storm water piping. Include provisions to collect exterior surface drainage and connect to storm sewer.
4. Protect and relocate moveable storage system to B411 in a separate phase of construction to coordinate with completion of B411 project so that construction work will not affect this area.
C. Construct tester facility project complying with DoD anti-terrorism and force protection requirements per unified Facilities Criteria.
1.5 CONTRACT METHOD
A. Construct the Work identified in Contract Documents under a single lump sum, fixed price contract for all project work.
1.6 CONTRACTOR USE OF PREMISES AND RESPONSIBILITIES
A. Coordinate use of premises under direction of Contracting Officer.
B. Assume full responsibility for protection and safekeeping of products under this Contract.
C. Work periods may be limited in duration without additional compensation to the Contractor aside from an extension to the performance period for lost time.
JLSS-17-0011 01 01 00 - 3
D. Contractor shall be responsible for protecting installed Work and existing building and infrastructure materials and systems that remain. Do not work on or damage existing Building
B129 areas and components not in the project work scope.
E. Work is prohibited on UTA training weekends, which typically occurs the first and third weekends each month.
F. Obtain and pay for use of additional storage or work areas needed for operations under this
Contract.
G. Refer to Division 01 Section “Work Restrictions” for additional project requirements.
H. Following existing and stored materials in Building 129 will be removed by the Government prior to it being turned over to the Contractor to perform the Contract Work:
1. Aircraft maintenance components stored in the High Bay area.
1.7 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
1.8 GOVERNMENT’S OCCUPANCY REQUIREMENTS
A. Repair Work required by this Contract relates to interior and exterior work scopes and does not require direct action in interior spaces occupied by Government workers.
B. Government Occupancy: Government will not occupy Building B129 during the entire construction period. Government will occupy adjacent buildings and other areas at the site, including aircraft areas during Renovate Facility for AFE Contract Work.
1. Maintain access to existing walkways, corridors, means of egress, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.
2. Provide not less than 3 working days’ notice to Contracting Officer of activities that will affect Government’s operations.
C. Completed Areas of Construction:
1. Contracting Officer will prepare one Certificate of Substantial Completion for the entire
Contract Work.
2. Contractor shall be responsible for cleanup and related maintenance in all work areas, until
Substantial Completion.
JLSS-17-0011 01 01 00 - 4
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
END OF SECTION
911th Airlift Wing, Renovate/Add for AGE Shop/Offices, B129 Work Restrictions
JLSS 17-0011 01 14 00 - 1
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 CONTRACTOR USE OF PREMISES AND RESPONSIBILITIES
A. Coordinate use of premises under direction of Contracting Officer. Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.
Cooperate with 911th Airlift Wing personnel during construction operations to minimize conflicts and facilitate 911th Airlift Wing usage. The contractor shall assume that the building will be occupied during normal work hours and on UTA weekends.
1. Limits: Confine construction to areas indicated on construction drawings and/or as designated by the Contracting Officer. Confine storage area as designated by the Contracting
Officer.
2. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to 911th Airlift Wing employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
3. Perform the work so as not to interfere with 911th Airlift Wing operations.
4. Building Occupancy During Construction:
a. A portion of the building pertinent to the Simulator operation will be occupied.
Maintain life safety systems and egress for occupied building areas.
b. Areas for AGE activities will not be occupied.
B. Assume full responsibility for protection and safekeeping of products under this Contract.
C. Work periods may be limited in duration without additional compensation to the Contractor aside from an extension to the performance period for lost time. Work schedule shall be as follows:
1. Normal work hours shall be between 0700 to 1600 (7:00 AM to 4:00 PM), Monday through
Friday, with no work on federal holidays.
2. Any deviations from the normal working hours must be approved 3 working days in advance by the Contracting Officer.
D. The Contractor shall be responsible for protecting all remaining permanent equipment.
E. Work is prohibited on UTA training weekends, which typically occurs the first and third weekends each month.
911th Airlift Wing, Renovate/Add for AGE Shop/Offices, B129 Work Restrictions
JLSS 17-0011 01 14 00 - 2
F. Obtain and pay for use of additional storage or work areas needed for operations under this contract.
G. Comfort stations are not provided by 911th Airlift Wing.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
911th Airlift Wing, Renovate/Add for AGE Shop/Offices, B129 Construction Progress Documentation
JLSS 17-0011 01 32 00-1
SECTION 01 32 00
CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SCOPE OF WORK
A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Submittals Schedule.
2. Construction Progress Schedule.
3. Contract Progress Report.
4. Daily construction reports.
5. Field condition reports.
6. Special reports.
B. Related Sections include the following:
1. Division 01 Section "Submittal Procedures" for submitting schedules and reports.
2. Division 01 Section "Quality Requirements" for submitting a schedule of tests and inspections.
3. Division 01 Section "Closeout Procedures" for submitting photographic negatives as
Project Record Documents at Project closeout.
1.3 SUBMITTALS
A. Submittals Schedule: Submit (4) four copies of schedule. Arrange the following information in a tabular format:
1. Scheduled date for first submittal.
2. Specification Section number and title.
3. Submittal category (action or informational).
4. Name of subcontractor.
JLSS 17-0011 01 32 00-2
5. Description of the Work covered.
6. Scheduled date for Contracting Officer’s final release or approval.
B. Construction Progress Schedule: Submit original and (2) two printed copies.
C. Contract Progress Report: Submit original and (2) two printed copies.
D. Daily Reports: Submit electronically to Contracting Officer.
E. Field Condition Reports: Submit (2) two copies at time of discovery of differing conditions.
F. Special Reports: Submit (2) two copies at time of unusual event.
1.4 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.
B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 - PRODUCTS
2.1 SUBMITTALS SCHEDULE
A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, ordering, manufacturing, fabrication, and delivery when establishing dates.
1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and
Contractor's Construction Schedule.
2. Initial Submittal: Submit concurrently with preliminary bar-chart schedule. Include submittals required during the first 30 days of construction. List those required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.
3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's
Construction Schedule.
JLSS 17-0011 01 32 00-3
2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Procedures: Comply with procedures contained in The Associated General Contractor’s
Construction Planning and Scheduling.
B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final
Completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by modification.
C. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following:
1. Activity Duration: Define activities in time frame coordinated with Contracting Officer.
2. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule.
Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.
3. Submittal Review Time: Include review and resubmittal times indicated in Division 01
Section "Submittal Procedures" in schedule. Coordinate submittal review times in
Contractor's Construction Schedule with Submittals Schedule.
4. Startup and Testing Time: Include not less than (10) ten days for startup and testing.
5. Substantial Completion: Indicate completion in advance of date established for
Substantial Completion, and allow time for Contracting Officer’s administrative procedures necessary for certification of Substantial Completion.
D. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
1. Phasing: Arrange list of activities on schedule in order that the work will be accomplished.
E. Products Ordered in Advance: Include a separate activity for each product. Include delivery date indicated in Section 01 01 00 "Summary of Work." Delivery dates indicated stipulate the earliest possible delivery date.
1. Work Restrictions: Show the effect of the following items on the schedule:
a. Coordination with existing construction.
b. Limitations of continued occupancies.
c. Uninterruptible services.
d. Partial occupancy before Substantial Completion.
e. Use of premises restrictions.
f. Seasonal variations.
g. Environmental control.
JLSS 17-0011 01 32 00-4
F. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule.
2.3 CONSTRUCTION CONTRACT PROGRESS SCHEDULES AND REPORTS
A. AF Form 3064, Contract Progress Schedule, shall be submitted in original and two copies.
Computer generated schedules may be used at the discretion of Contracting Officer. When approved, the original shall be retained by the contracting office. Signed copies shall be provided to the Civil Engineer and the Contractor.
B. Separate progress reports (AF Form 3065, Contract Progress Report) covering the same period shall be prepared by the Civil Engineer or their designee and the Contractor, and submitted twice monthly. The periods shall be the same as stated on the Contract Progress Schedule. At the discretion of the Contracting Officer, this time period may be extended to monthly for projects of 180 days or more. This decision shall be documented in the contract file.
2.4 REPORTS
A. Daily Construction Report (DCR): It is very important to record each day’s Work and resources used; especially those that are impacting the Project Schedule. Prepare a daily construction report recording at minimum the following information concerning events at
Project site:
1. Contract Number, Name of Project, Prime Contractor.
2. Report Number (sequentially starting with 1) and date.
3. Temperature; general description, range (low- high), precipitation and if it affected work.
4. Any delays in work progress (all items needed on-hand, any equipment down for repairs).
5. List of Subcontractors at Project site, hours on site and area of responsibility.
6. Number of personnel at Project site. Indicate trades and (foreperson, journey person, or apprentice.
7. Indicate General description of work going on (Ex; XZY Corp, Carpenter (1-F, 2-J, 1-A);
installed blocking at roof perimeter).
8. Accidents.
9. Meetings, inspections, and significant decisions.
10. Unusual events (refer to special reports).
11. Stoppages, delays, shortages, and losses.
12. Materials received (complete, damage, correct).
13. Emergency procedures.
JLSS 17-0011 01 32 00-5
14. Concrete placed; include mix tickets attached to report. Tickets to show type of mix, sup-plier, time left plant, time started to mix, time of placement).
15. Orders and requests of the Contracting Officer.
16. Change Orders received and implemented.
17. Services connected and disconnected.
18. Equipment or system tests and startups, pass/ fail information.
19. Tests and their results.
20. Partial Completions and occupancies.
21. Substantial Completions authorized.
22. Other general comments, as needed.
23. Signed and dated; signature of Superintendent or acting Supt. certifies that the report is true and accurate, and that work is in compliance with contract plans and specifications.
24. Use form approved by Contracting Officer and provide electronically to the Contracting
Officer before COB the following day unless another submission time is authorized.
B. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare a detailed report. Submit with a request for information
(RIF). Include a detailed description of the differing conditions, together with recommendations for changing the Contract documents.
2.5 SPECIAL REPORTS
A. General: Submit special reports directly to Contracting Officer within one day of an occurrence. Distribute copies of report to parties affected by the occurrence.
B. Reporting Unusual Events: When an event of an unusual and significant nature occurs at
Project site, whether or not related directly to the Work, prepare and submit a special report.
List chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Contracting Officer in advance when these events are known or predictable.
PART 3 - EXECUTION
3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
JLSS 17-0011 01 32 00-6
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
3. As the Work progresses, indicate Actual Completion percentage for each activity.
B. Distribution: Distribute copies of approved schedule to Contracting Officer, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1. Post copies in Project meeting rooms and temporary field offices.
2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.
911th Airlift Wing, Renovate/Add for AGE Shop/Offices, B129 Submittal Procedures
JLSS 17-0011 01 34 00-1
SECTION 01 34 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SCOPE OF WORK
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals.
1.3 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
B. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer’s receipt of submittal.
1. Initial Review: Allow fourteen (14) calendar days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. Contracting Officer will advise Contractor when a submittal being processed must be delayed for coordination.
2. Allow fourteen (14) calendar days for processing each resubmittal.
3. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Use for Construction: Use only final submittals with mark indicating action taken by Contracting
Officer in connection with construction.
JLSS 17-0011 01 34 00-2
PART 2 PRODUCTS
2.1 SUBMITTALS
A. General: Prepare and submit Submittals required by individual Specification Sections.
1. Number of Copies: Submit four (4) copies of each submittal, unless otherwise indicated.
Contracting Officer will return two (2) copies. Mark up and retain one returned copy as a
Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Standard color charts.
e. Manufacturer's catalog cuts.
f. Wiring diagrams showing factory-installed wiring.
g. Printed performance curves.
h. Operational range diagrams.
i. Mill reports.
j. Standard product operating and maintenance manuals.
k. Compliance with recognized trade association standards.
l. Compliance with recognized testing agency standards.
m. Application of testing agency labels and seals.
n. Notation of coordination requirements.
C. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from the same material to be used for the Work, cured and finished in manner specified, and physically identical with the product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials;
complete units of repetitively used materials; swatches showing color, texture, and pattern;
color range sets; and components used for independent testing and inspection.
D. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
E. Safety Data Sheets (SDS): Submit information directly to Contracting Officer.
JLSS 17-0011 01 34 00-3
PART 3 EXECUTION
3.1 CONTRACTOR'S REVIEW
A. Review each submittal and check for compliance with the Contract Documents. Sign submittal under a cover letter before submitting to Contracting Officer.
B. Failure of the contractor to provide any required documents under the contract may result in withholding a retainage pursuant to the Payments Under Fixed-Price Construction Clause, FAR
52.232-5.
3.2 CONTRACTING OFFICER’S ACTION
A. General: Contracting Officer will not review submittals that do not bear Contractor's approval stamp and will return them without action.
B. Contracting Officer will review each submittal, make marks to indicate corrections or modifications required, and return it. Contracting Officer will mark submittal appropriately to indicate action taken.
JLSS 17-0011 01 34 00-4
THIS PAGE INTENTIONALLY LEFT BLANK
911th Airlift Wing, Renovate/Add for AGE Shop/Offices, B129 Quality Requirements
JLSS 17-0011 01 40 00 - 1
SECTION 01 40 00
QUALITY REQUIREMENTS
PART 1 GENERAL
RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
SCOPE OF WORK
A. This Section includes administrative and procedural requirements for quality assurance and quality control.
B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the
Contract Document requirements.
1. Specific quality-control requirements for individual construction activities are specified in the Sections that specify those activities. Requirements in those Sections may also cover production of standard products.
2. Specified tests, inspections, and related actions do not limit Contractor's quality-control procedures that facilitate compliance with the Contract Document requirements.
3. Requirements for Contractor to provide quality-control services required by Contracting
Officer are not limited by provisions of this Section.
C. See individual Specification Sections for specific test and inspection requirements.
D. This Section requires taking quality related actions during design, fabrication, and installation of products, materials, and systems. Completed work shall carry a minimum 365-day manufacturers and installers warranty from date of Substantial Completion, unless otherwise specified in other
Specification Sections.
DEFINITIONS
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and ensure that proposed construction complies with requirements.
B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that completed construction complies with requirements.
C. Mockups: Full-size, physical example assemblies to illustrate finishes and materials. Mockups are used to verify selections made under Sample submittals, to demonstrate appearance and, where indicated, qualities of materials and execution, and to review construction, coordination, testing, or operation; they are not Samples.
D. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.
JLSS 17-0011 01 40 00 - 2
SUBMITTALS
A. Qualification Data: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
B. Schedule of Tests and Inspections: Prepare in tabular form and include the following:
1. Specification Section number and title.
2. Description of test and inspection.
3. Identification of applicable standards.
4. Identification of test and inspection methods.
5. Number of tests and inspections required.
6. Time schedule or time span for tests and inspections.
7. Entity responsible for performing tests and inspections.
8. Requirements for obtaining samples.
9. Unique characteristics of each quality-control service.
C. Reports: Prepare and submit certified written reports that include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples and tests or inspections.
5. Names of individuals making tests and inspections.
6. Description of the Work and test and inspection method.
7. Identification of product and Specification Section.
8. Complete test or inspection data.
9. Test and inspection results and an interpretation of test results.
10. Ambient conditions at time of sample taking and testing and inspecting.
11. Comments or professional opinion on whether tested or inspected Work complies with the
Contract Document requirements.
12. Name and signature of laboratory inspector.
JLSS 17-0011 01 40 00 - 3
13. Recommendations on retesting and reinspecting.
D. Permits, Licenses, and Certificates: For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.
QUALITY ASSURANCE
A. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this
Project.
B. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
C. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance.
D. Testing Agency Qualifications: An agency with the experience and capability to conduct testing and inspecting indicated, as documented by ASTM E 548, and that specializes in types of tests and inspections to be performed.
E. Mockups: Before installing portions of the Work requiring mockups, build mockups for each form of construction and finish required to comply with the following requirements, using materials indicated for the completed Work:
1. Build mockups in location and of size indicated or, if not indicated, as directed by
Contracting Officer.
2. Notify Contracting Officer (7) seven calendar days in advance of dates and times when mockups will be constructed.
3. Demonstrate the proposed range of aesthetic effects and workmanship.
4. Obtain Contracting Officer’s approval of mockups before starting work, fabrication, or construction.
5. Maintain mockups during construction in an undisturbed condition as a standard for judging the completed Work.
6. Demolish and remove mockups when directed, unless otherwise indicated.
F. Preconstruction Testing: Testing agency shall perform, preconstruction testing for compliance with specified requirements for performance and test methods.
1. Contractor responsibilities include the following:
JLSS 17-0011 01 40 00 - 4
a. Provide test specimens and assemblies representative of proposed materials and construction. Provide sizes and configurations of assemblies to adequately demonstrate capability of product to comply with performance requirements.
b. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying the Work.
c. Fabricate and install test assemblies using installers who will perform the same tasks for Project.
d. When testing is complete, remove assemblies; do not reuse materials on Project.
2. Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and similar quality-assurance service to Contracting Officer, with copy to Contractor.
Interpret tests and inspections and state in, each report whether tested and inspected work complies with or deviates from the Contract Documents.
3. TEST SECTIONS: Before proceeding with the work, the Contractor shall demonstrate the processes and materials to be used a minimum of 24 hours prior to proceeding with the work to allow for resolution of any questions or clarifications. Test sections shall include the following:
a. Joint Cleaning and Sealing. Include a minimum 50 ft length. All preparations and processes to be followed for the contract work must be demonstrated in the completion of the test section.
4. Positive Drainage: A horizontal surface included in this scope of work will be placed such that the surface will achieve positive drainage and water will, in accordance with existing drainage patterns, both freely flow onto the surface and will freely flow off and away from the surface to existing rain drainage systems. No water shall be allowed to “pond” or collect on that surface due to its profile, edging or joint filling treatments. Contractor shall completely remove and replace any work which does not conform to positive drainage requirements.
QUALITY CONTROL
A. Contractor Responsibilities: Unless otherwise indicated, provide quality-control services specified and required by Contracting Officer.
1. Engage a qualified testing agency to perform these quality-control services.
2. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed.
3. Where quality-control services are indicated as Contractor’s responsibility, submit a certified written report, in duplicate, of each quality-control service.
4. Testing and inspecting requested by Contractor and not required by the Contract Documents are Contractor’s responsibility.
5. Submit additional copies of each written report directly to Contracting Officer, when they so direct.
JLSS 17-0011 01 40 00 - 5
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct special tests and inspections required by Contracting Officer.
1. Testing agency will notify Contracting Officer promptly of irregularities and deficiencies observed in the Work during performance of its services.
2. Testing agency will submit a certified written report of each test, inspection, and similar quality-control service to Contracting Officer.
3. Testing agency will submit a final report of special tests and inspections at Substantial
Completion, which includes a list of unresolved deficiencies.
4. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
5. Testing agency will retest and reinspect corrected work.
C. Retesting and Reinspecting: Regardless of whether original tests or inspections were Contractor’s responsibility, provide quality-control services, including retesting and reinspecting, for construction that revised or replaced Work that failed to comply with requirements established by the Contract Documents.
D. Testing Agency Responsibilities: Cooperate with Contracting Officer and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.
1. Notify Contracting Officer and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.
2. Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.
3. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor.
4. Do not release, revoke, alter, or increase requirements of the Contract Documents or approve or accept any portion of the Work.
5. Do not perform any duties of Contractor.
E. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:
1. Access to the Work.
2. Incidental labor and facilities necessary to facilitate tests and inspections.
3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples.
4. Facilities for storage and field-curing of test samples.
JLSS 17-0011 01 40 00 - 6
5. Delete first subparagraph below if not required or common practice in Project vicinity.
6. Delivery of samples to testing agencies.
7. Preliminary design mix proposed for use for material mixes that require control by testing agency.
8. Security and protection for samples and for testing and inspecting equipment at Project site.
F. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and quality-control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.
1. Schedule times for tests, inspections, obtaining samples, and similar activities.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
REPAIR AND PROTECTION
A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.
1. Comply with the Contract Document requirements for Section 01 73 89 "Cutting and
Patching."
B. Protect construction exposed by or for quality-control service activities.
C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.
911th Airlift Wing, Renovate/Add for AGE Shop/Offices, B129 Environmental Protection
JLSS 17-0011 01 41 00-1
SECTION 01 41 00
ENVIRONMENTAL PROTECTION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SCOPE OF WORK
A. The Contractor shall comply with all federal, state and local environmental rules and regulations, including all Air Force and 911th Airlift Wing (AW) programs and policies. Failure to comply shall result in the Contractor reimbursing the 911th AW for any fines, fees, or additional costs incurred by the 911th AW as a result of Contractor non-compliance.
B. The Contractor shall participate in the base Hazardous Materials (HAZMAT) program whereby all
HAZMAT shall be approved by the Government prior to use and all HAZMAT use tracked.
C. The Contractor shall adhere to the Air Force requirement to use licensed pesticide applicators as per
Para. E4.1.5.2.3 of DODI 4150.7: “Contractor employees performing pest management work on a
DoD installation shall be certified prior to the beginning of the contract under a State plan accepted in the State in which the work is performed.” All pesticides must be approved by the base Pest
Manager prior to bringing material on base or applying. This includes pesticides that can be purchased over the counter by consumers. Pesticides include any substance or mixture of substances intended for preventing, destroying, repelling, or mitigating any pest including but not limited to insecticides, herbicides, fungicides, and various other substances to control pests. Any pesticide usage and reporting must be in accordance with the Pittsburgh IAP ARS Integrated Pest Management
Plan.
1.3 SUBMITTALS
A. The following shall be submitted in accordance with Section 01 34 00 “Submittals”.
1. Environmental Protection Program:
a. Within 10 calendar days after Notice to Proceed and prior to commencement of the work at the site, the Contractor shall submit in writing his detailed proposal for implementing requirements for environmental controls specified herein.
B. Preconstruction Survey:
1. Prior to start of any onsite construction activities, the Contractor and the Contracting Officer shall make a joint condition survey, after which the Contractor shall prepare a brief report indicating on a layout plan the condition of the areas immediately adjacent to the site of the work and adjacent to his assigned storage area and access routes(s) as applicable.
2. Both the Contracting Officer and Contractor will sign this report upon mutual agreement as to its accuracy and completeness.
JLSS 17-0011 01 41 00-2
C. Waste Disposal Scheme:
1. The Contractor shall submit a description of his scheme for disposing of waste materials resulting from the work under this contract.
2. If any waste material is dumped in unauthorized areas, the Contractor shall remove the material and restore the area to the condition of the adjacent undisturbed areas.
3. Where directed, contaminated ground shall be excavated, disposed of properly, and replaced with suitable clean fill material at the expense of the Contractor.
D. Safety Data Sheets (SDS) & HAZMAT Usage:
1. Prior to bringing any HAZMAT on base, submit for the Contracting Officer’s review and approval three (3) copies of the most current SDS for each HAZMAT to be used for performance of work under the contract. The Contractor shall note the contract number, project number, and project title on each SDS.
2. In addition, provide the container size for each item (in units of weight / volume) and the quantities used for all HAZMAT. Provide the information on the attached HAZMAT Usage
Log. This information is required for the base HAZMAT program. Submit the HAZMAT
Usage Log, at completion of all project work, or at a frequency (i.e. monthly or quarterly) determined by the Contracting Officer.
E. Location of Contractor’s HAZMAT Storage:
1. Submit a drawing/sketch showing the location(s) designated for storage of HAZMAT for approval by the Contracting Officer.
2. The location of the Contractor’s HAZMAT storage shall be in area(s) designated by the
Contracting Officer.
3. Storage areas for HAZMAT shall comply with Paragraph 3.13, Hazardous Materials.
F. Pesticides (Including Herbicides)
1. Submit the Pesticide Application Business License to the Contracting Officer.
2. Submit the Certified Commercial Pesticide Applicator license for all pesticide applicators to the
3. Submit proposed pesticide SDS, copy of the label, intended quantity, and location of application for project to the Contracting Officer. The base Pesticide Manager will review and provide recommendation for approval or disapproval to the Contracting Officer. Material must be approved before being brought on base or applied.
4. Submit the following information of pesticide used as soon as application is complete:
a. Names of all certified applicators.
b. Contractor business name.
c. Date of application.
d. Duration of each task in hours.
e. Building, facility, or location treated.
JLSS 17-0011 01 41 00-3
f. Room number or specific location.
g. Target pest (pest to be controlled).
h. Pesticide applied and EPA Registration Number.
i. Quantity applied (undiluted).
j. SDS and product labels for each material used.
k. Reason for application.
l. Total units treated (i.e. acres, cubic feet, each, linear feet, or square feet).
m. Describe if pesticide was applied indoors or outdoors.
n. Business and applicator(s) certification numbers and expiration dates.
G. Solid Waste:
1. Weight Receipts: As proof of proper disposal, the Contractor shall provide weight receipts for every load of recycled or disposed materials. Weights can be obtained through use of the installation truck scales located near Building 320, certified weighing devices located at recycling and disposal facilities, or by using a commercial weigh station. The Contractor shall submit receipts to the Contracting Officer within ten (10) days of the transaction date. The weight receipts shall be completely legible and include the date of the transaction, type of material, and weight of the material in pounds/tons.
2. Construction and Demolition Debris Waste Management Report: The Contractor shall submit a
Construction and Demolition Debris Waste Management Report (sample enclosed at end of
Section). The report shall be submitted to the Contracting Officer on a quarterly basis in hard-copy or electronic format. The Contractor shall use weight receipts to generate the report.
1.4 PLAN FORMAT
A. All plans required to be provided by the Contractor for approval by the Contracting Officer shall be simple, legible documents detailing the activities and operations the Contractor intends to perform under this contract, including drawings / sketches where applicable.