Section B - Supplies or Services and Prices

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot

PROJECT JLSS 13-0011, REPAIR FIRE SUPPR

FFP

CONSTRUCTION, TO PROVIDE MATERIAL, LABOR, EQUIPMENT, TRANSPORTATION, AND ALL WORK REQUIRED TO REPAIR FIRE SUPPRESSION SYSTEMS, HANGARS 129, 416, 417. PROJECT JLSS 13-0011. ALL WORK TO BE COMPLETED IN ACCORDANCE WITH CONTRACT DOCUMENTS.

FOB: Destination

PURCHASE REQUEST NUMBER: F5K6CE4317A001

SIGNAL CODE: A

NET AMT

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN
INSPECT AT
INSPECT BY
ACCEPT AT
ACCEPT BY
0001
Destination
Government
Destination
Government

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC
0001
180 dys. ADC
1
911TH AIRLIFT WING/CE - F5K6CE

1100 HERMAN AVENUE

CORAOPOLIS PA 15108-4421

FOB: Destination

F5K6CE

Section G - Contract Administration Data

CLAUSES INCORPORATED BY FULL TEXT

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)

(a) Definitions. As used in this clause--

Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.

Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.

(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall--

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through

WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.

(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:

(1) Document type. The Contractor shall use the following document type(s).

Construction Invoice

(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.

FA6712

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF

Data to be entered in WAWF

Pay Official DoDAAC

F67100 Issue By DoDAAC

FA6712

Admin DoDAAC

FA6712

Inspect By DoDAAC

F5K6CE

Ship To Code

F5K6CE

Ship From Code

Mark For Code

Service Approver (DoDAAC)

F5K6CE

Service Acceptor (DoDAAC)

FA6712

Accept at Other DoDAAC

LPO DoDAAC

DCAA Auditor DoDAAC

Other DoDAAC(s)

(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.

(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.

daniel.ellingsen.1@us.af.mil

(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

peggy.teets@us.af.mil

(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.

(End of clause)

Section H - Special Contract Requirements

CLAUSES INCORPORATED BY FULL TEXT

5352.223-9001 HEALTH AND SAFETY ON GOVERNMENT INSTALLATIONS.

As prescribed in 5323.9001, insert the following clause in solicitations and contracts:

HEALTH AND SAFETY ON GOVERNMENT INSTALLATIONS (JUN 1997)

(a) In performing work under this contract on a Government installation, the contractor shall:

(1) Comply with the specific health and safety requirements established by this contract;

(2) Comply with the health and safety rules of the Government installation that concern related activities not directly addressed in this contract;

(3) Take all reasonable steps and precautions to prevent accidents and preserve the health and safety of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and

(4) Take such additional immediate precautions as the contracting officer may reasonably require for health and safety purposes.

(b) The contracting officer may, by written order, direct Air Force Occupational Safety and Health Standards (AFOSH) and/or health/safety standards as may be required in the performance of this contract and any adjustments resulting from such direction will be in accordance with the Changes clause of this contract.

(c) Any violation of these health and safety rules and requirements, unless promptly corrected as directed by the contracting officer, shall be grounds for termination of this contract in accordance with the Default clause of this contract.

(End of clause)

5352.242-9000 CONTRACTOR ACCESS TO AIR FORCE INSTALLATIONS (Nov 2012)

(a) The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.

(b) The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, and a valid vehicle insurance certificate to obtain a vehicle pass. At least 14 days before their arrival on base, the contractor will verify their employees are U.S. citizens or have permanent residency cards in addition to submitting a valid criminal background check through the Pennsylvania State Police, https://epatch.state.pa.us/. Since background checks are limited to state information, the Registered Offenders List, a national registry should also be searched, http://www.registeredoffenderslist.org.

The contractor shall submit the request for personnel access to the installation on the “Contractor Pre-Entry Form for DBIDS ID Cards” form (for access of more than 60 calendar days), or on a designated local form for access of employees working less than 60 calendar days under the contract. The contractor shall provide the below information, but not limited to the following:

Name, First, Last, Middle Inintial

Social Security No.:

Date and Place of Birth:

Contract Number:

Location of Work Site:

Start and Stop Dates, or Performance Period:

Driver’s license number and state issued:

Pennsylvania criminal background check of employees and subcontractor employees needing access to the base.

(c) During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.

(d) When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with AFI 31-101, Volume 1, The Air Force Installation Security Program and AFI 31-501, Personnel Security Program Management, citing the appropriate paragraphs as applicable.

(e) Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.

(f) Failure to comply with these requirements may result in withholding of final payment.

(End of clause)

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.202-1
Definitions
NOV 2013
52.203-3
Gratuities
APR 1984
52.203-5
Covenant Against Contingent Fees
MAY 2014
52.203-6
Restrictions On Subcontractor Sales To The Government
SEP 2006
52.203-7
Anti-Kickback Procedures
MAY 2014
52.203-8
Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
MAY 2014
52.203-10
Price Or Fee Adjustment For Illegal Or Improper Activity
MAY 2014
52.203-12
Limitation On Payments To Influence Certain Federal Transactions
OCT 2010
52.203-16
Preventing Personal Conflicts of Interest
DEC 2011
52.203-17
Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights
APR 2014
52.204-4
Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-7
System for Award Management
JUL 2013
52.204-9
Personal Identity Verification of Contractor Personnel
JAN 2011
52.204-10
Reporting Executive Compensation and First-Tier Subcontract Awards
JUL 2013
52.209-2
Prohibition on Contracting with Inverted Domestic Corporations--Representation
MAY 2011
52.209-6
Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
AUG 2013
52.209-10
Prohibition on Contracting With Inverted Domestic Corporations
MAY 2012
52.211-12
Liquidated Damages--Construction
SEP 2000
52.211-13
Time Extensions
SEP 2000
52.214-29
Order Of Precedence--Sealed Bidding
JAN 1986
52.215-8
Order of Precedence--Uniform Contract Format
OCT 1997
52.219-8
Utilization of Small Business Concerns
OCT 2014
52.222-1
Notice To The Government Of Labor Disputes
FEB 1997
52.222-3
Convict Labor
JUN 2003
52.222-4
Contract Work Hours and Safety Standards Act - Overtime Compensation
MAY 2014
52.222-6
Construction Wage Rate Requirements
MAY 2014
52.222-7
Withholding of Funds
MAY 2014
52.222-8
Payrolls and Basic Records
MAY 2014
52.222-9
Apprentices and Trainees
JUL 2005
52.222-10
Compliance with Copeland Act Requirements
FEB 1988
52.222-11
Subcontracts (Labor Standards)
MAY 2014
52.222-12
Contract Termination-Debarment
MAY 2014
52.222-13
Compliance With Construction Wage Rate Requirements and Related Regulations
MAY 2014
52.222-14
Disputes Concerning Labor Standards
FEB 1988
52.222-15
Certification of Eligibility
MAY 2014
52.222-21
Prohibition Of Segregated Facilities
FEB 1999
52.222-26
Equal Opportunity
MAR 2007
52.222-27
Affirmative Action Compliance Requirements for Construction
FEB 1999
52.222-33
Notice of Requirement for Project labor Agreement
MAY 2010
52.222-36
Equal Opportunity for Workers with Disabilities
JUL 2014
52.222-37
Employment Reports on Veterans
JUL 2014
52.222-40
Notification of Employee Rights Under the National Labor Relations Act
DEC 2010
52.222-50
Combating Trafficking in Persons
FEB 2009
52.222-54
Employment Eligibility Verification
AUG 2013
52.223-3
Hazardous Material Identification And Material Safety Data
JAN 1997
52.223-5
Pollution Prevention and Right-to-Know Information
MAY 2011
52.223-6
Drug-Free Workplace
MAY 2001
52.223-11
Ozone-Depleting Substances
MAY 2001
52.223-18
Encouraging Contractor Policies To Ban Text Messaging While Driving
AUG 2011
52.225-9
Buy American--Construction Materials
MAY 2014
52.225-10
Notice of Buy American Requirement--Construction Materials
MAY 2014
52.225-13
Restrictions on Certain Foreign Purchases
JUN 2008
52.225-25
Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications.
DEC 2012
52.227-1
Authorization and Consent
DEC 2007
52.227-2
Notice And Assistance Regarding Patent And Copyright Infringement
DEC 2007
52.227-4
Patent Indemnity-Construction Contracts
DEC 2007

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be TWENTY (20%) percent of the bid price or $ N/A, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of provision)

CLAUSES INCORPORATED BY REFERENCE

52.228-2
Additional Bond Security
OCT 1997
52.228-5
Insurance - Work On A Government Installation
JAN 1997
52.228-11
Pledges Of Assets
JAN 2012
52.228-12
Prospective Subcontractor Requests for Bonds
MAY 2014
52.228-14
Irrevocable Letter of Credit
MAY 2014
52.228-15
Performance and Payment Bonds--Construction
OCT 2010
52.229-3
Federal, State And Local Taxes
FEB 2013
52.232-5
Payments under Fixed-Price Construction Contracts
MAY 2014
52.232-17
Interest
MAY 2014
52.232-23
Assignment Of Claims
MAY 2014
52.232-23 Alt I
Assignment of Claims (May 2014) - Alternate I
APR 1984
52.232-25
Prompt Payment
JUL 2013
52.232-27
Prompt Payment for Construction Contracts
MAY 2014
52.232-33
Payment by Electronic Funds Transfer--System for Award Management
JUL 2013
52.232-40
Providing Accelerated Payments to Small Business Subcontractors
DEC 2013
52.233-1
Disputes
MAY 2014
52.233-3
Protest After Award
AUG 1996
52.233-4
Applicable Law for Breach of Contract Claim
OCT 2004
52.236-2
Differing Site Conditions
APR 1984
52.236-3
Site Investigation and Conditions Affecting the Work
APR 1984
52.236-5
Material and Workmanship
APR 1984
52.236-6
Superintendence by the Contractor
APR 1984
52.236-7
Permits and Responsibilities
NOV 1991
52.236-8
Other Contracts
APR 1984
52.236-9
Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10
Operations and Storage Areas
APR 1984
52.236-11
Use and Possession Prior to Completion
APR 1984
52.236-12
Cleaning Up
APR 1984
52.236-13
Accident Prevention
NOV 1991
52.236-14
Availability and Use of Utility Services
APR 1984
52.236-15
Schedules for Construction Contracts
APR 1984
52.236-17
Layout of Work
APR 1984
52.236-21
Specifications and Drawings for Construction
FEB 1997
52.236-26
Preconstruction Conference
FEB 1995
52.242-13
Bankruptcy
JUL 1995
52.242-14
Suspension of Work
APR 1984
52.243-4
Changes
JUN 2007
52.244-6
Subcontracts for Commercial Items
OCT 2014
52.246-12
Inspection of Construction
AUG 1996
52.246-21
Warranty of Construction
MAR 1994
52.248-3
Value Engineering-Construction
OCT 2010
52.249-2
Termination For Convenience Of The Government (Fixed-Price)
APR 2012
52.249-10
Default (Fixed-Price Construction)
APR 1984
52.253-1
Computer Generated Forms
JAN 1991
252.203-7001
Prohibition On Persons Convicted of Fraud or Other Defense-Contract-Related Felonies
DEC 2008
252.204-7004 Alt A
System for Award Management Alternate A
FEB 2014
252.209-7004
Subcontracting With Firms That Are Owned or Controlled By The Government of a Terrorist Country
MAR 2014
252.223-7004
Drug Free Work Force
SEP 1988
252.223-7006
Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials
SEP 2014
252.225-7012
Preference For Certain Domestic Commodities
FEB 2013
252.225-7016
Restriction On Acquisition Of Ball and Roller Bearings
JUN 2011
252.225-7030
Restriction On Acquisition Of Carbon, Alloy, And Armor Steel Plate
DEC 2006
252.225-7031
Secondary Arab Boycott Of Israel
JUN 2005

252.225-7044 BALANCE OF PAYMENTS PROGRAM--CONSTRUCTION MATERIAL (JUN 2012)

(a) Definitions. As used in this clause--

Commercially available off-the-shelf (COTS) item--

(1) Means any item of supply (including construction material) that is--

(i) A commercial item (as defined in paragraph (1) of the definition of ``commercial item'' in section 2.101 of the Federal Acquisition Regulation);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

“Component” means any article, material, or supply incorporated directly into construction material.

“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means--

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the end product (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means--

(1) An unmanufactured construction material mined or produced in the United States; or

(2) A construction material manufactured in the United States, if--

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

``United States'' means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference. This clause implements the Balance of Payments Program by providing a preference for domestic construction material. The Contractor shall use only domestic construction material in performing this contract, except for—

(1) Construction material valued at or below the simplified acquisition threshold in part 2 of the Federal Acquisition Regulation;

(2) Information technology that is a commercial item; or

(3) The construction material or components listed by the Government as follows:

NONE

(End of clause)

CLAUSES INCORPORATED BY REFERENCE

252.232-7003
Electronic Submission of Payment Requests and Receiving Reports
JUN 2012
252.232-7010
Levies on Contract Payments
DEC 2006
252.236-7000
Modification Proposals-Price Breakdown
DEC 1991
252.236-7013
Requirement for Competition Opportunity for American Stell Producers, Fabricators, and Manufacturers
JUN 2013
252.243-7001
Pricing Of Contract Modifications
DEC 1991
252.243-7002
Requests for Equitable Adjustment
DEC 2012

52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (JULY 2013)

(a) The Contractor shall update the information in the Federal Awardee Performance and Integrity Information System (FAPIIS) on a semi-annual basis, throughout the life of the contract, by posting the required information in the System for Award Management database via https://www.acquisition.gov.

(b) As required by section 3010 of the Supplemental Appropriations Act, 2010 (Pub. L. 111-212), all information posted in FAPIIS on or after April 15, 2011, except past performance reviews, will be publicly available. FAPIIS consists of two segments--

(1) The non-public segment, into which Government officials and the Contractor post information, which can only be viewed by--

(i) Government personnel and authorized users performing business on behalf of the Government; or

(ii) The Contractor, when viewing data on itself; and

(2) The publicly-available segment, to which all data in the non-public segment of FAPIIS is automatically transferred after a waiting period of 14 calendar days, except for--

(i) Past performance reviews required by subpart 42.15;

(ii) Information that was entered prior to April 15, 2011; or

(iii) Information that is withdrawn during the 14-calendar-day waiting period by the Government official who posted it in accordance with paragraph (c)(1) of this clause.

(c) The Contractor will receive notification when the Government posts new information to the Contractor's record.

(1) If the Contractor asserts in writing within 7 calendar days, to the Government official who posted the information, that some of the information posted to the non-public segment of FAPIIS is covered by a disclosure exemption under the Freedom of Information Act, the Government official who posted the information must within 7 calendar days remove the posting from FAPIIS and resolve the issue in accordance with agency Freedom of Information procedures, prior to reposting the releasable information. The contractor must cite 52.209-9 and request removal within 7 calendar days of the posting to FAPIIS.

(2) The Contractor will also have an opportunity to post comments regarding information that has been posted by the Government. The comments will be retained as long as the associated information is retained, i.e., for a total period of 6 years. Contractor comments will remain a part of the record unless the Contractor revises them.

(3) As required by section 3010 of Pub. L. 111-212, all information posted in FAPIIS on or after April 15, 2011, except past performance reviews, will be publicly available.

(d) Public requests for system information posted prior to April 15, 2011, will be handled under Freedom of Information Act procedures, including, where appropriate, procedures promulgated under E.O. 12600.

(End of clause)

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within TEN (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 calendar days. The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008)

(a) Definitions. As used in this clause--

Postconsumer material means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”

Recovered material means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.

(b) The Contractor, on completion of this contract, shall--

(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and

(2) Submit this estimate to 911th Airlift Wing, Contracting Office, Pittsburgh IAP ARS, 2375 Defense Ave, Coraopolis, PA 15108-4495.

(End of clause)

52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.

(b) The use in this solicitation or contract of any Defense Federal Acquisition Regulation Supplement (48 CFR 2) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

(End of clause)

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

Title

Drawing No.

Cover Sheet

G-1

HVAC Data Sheet

H-1

HVAC Plans, Hangar 129

H-2

HVAC Plans, Hangar 417

H-4

Electrical Data Sheet

E-1

Electrical Power Floor Plan, Hangar 129 E-2

Electrical Power Floor Plan, Hangar 416 E-3

Electrical Power Floor Plan, Hangar 417 E-4

Sprinkler System Hangar 417

F-1

(End of clause)

5352.201-9101 Ombudsman

As prescribed in 5301.9103, insert the following clause:

OMBUDSMAN (APR 2010)

(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and others for this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman does not affect the authority of the program manager, contracting officer, or source selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of protests or formal contract disputes. The ombudsman may refer the party to another official who can resolve the concern.

(b) Before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution. Consulting an ombudsman does not alter or postpone the timelines for any other processes (e.g., agency level bid protests, GAO bid protests, requests for debriefings, employee-employer actions, contests of OMB Circular A-76 competition performance decisions).

(c) If resolution cannot be made by the contracting officer, concerned parties may contact the Center/MAJCOM ombudsmen, Col Steven Slick, HQ AFRC/A7Z, Phone DSN 497-2472 (Comm 478-327-2472). Concerns, issues, disagreements, and recommendations that cannot be resolved at the MAJCOM/DRU level, may be brought by the concerned party for further consideration to the Air Force ombudsman, Associate Deputy Assistant Secretary (ADAS) (Contracting), SAF/AQC, 1060 Air Force Pentagon, Washington DC 20330-1060, phone number (703) 588-7004, facsimile number (703) 588-1067.

(d) The ombudsman has no authority to render a decision that binds the agency.

(e) Do not contact the ombudsman to request copies of the solicitation, verify offer due date, or clarify technical requirements. Such inquiries shall be directed to the Contracting Officer.

(End of clause)

5352.223-9000 ELIMINATION OF USE OF CLASS I OZONE DEPLETING SUBSTANCES (ODS).

As prescribed in 5323.804, insert the following clause in solicitations and contracts:

ELIMINATION OF USE OF CLASS I OZONE DEPLETING SUBSTANCES (ODS) (MAY 1996)

(a) It is Air Force policy to preserve mission readiness while minimizing dependency on Class I Ozone Depleting Substances (ODS), and their release into the environment, to help protect the Earth's stratospheric ozone layer.

(b) Unless a specific waiver has been approved, Air Force procurements:

(1) May not include any specification, standard, drawing, or other document that requires the use of a Class I ODS in the design, manufacture, test, operation, or maintenance of any system, subsystem, item, component, or process; and

(2) May not include any specification, standard, drawing, or other document that establishes a requirement that can only be met by use of a Class I ODS;

(c) For the purposes of Air Force policy, the following are Class I ODS:

(1) Halons: 1011, 1202, 1211, 1301, and 2402;

(2) Chlorofluorocarbons (CFCs): CFC-11, CFC-12, CFC-13, CFC-111, CFC-112, CFC-113, CFC-114, CFC-115, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, and CFC-217, and the blends R-500, R-501, R-502, and R-503; and

(3) Other Controlled Substances: Carbon Tetrachloride, Methyl Chloroform, and Methyl Bromide.

(d) The Air Force has reviewed the requirements specified in this contract to reflect this policy. Where considered essential, specific approval has been obtained to require use of the following substances:

Substance Application Use Quantity (lbs.)

NONE

(e) To assist the Air Force in implementing this policy, the offeror/contractor is required to notify the contracting officer if any Class I ODS not specifically listed above is required in the performance of this contract.

(End of clause)

Section K - Representations, Certifications and Other Statements of Offerors

CLAUSES INCORPORATED BY REFERENCE

52.204-8
Annual Representations and Certifications
OCT 2014
52.209-7
Information Regarding Responsibility Matters
JUL 2013
252.209-7001
Disclosure of Ownership or Control by the Government of a Terrorist Country
JAN 2009

Section L - Instructions, Conditions and Notices to Bidders

CLAUSES INCORPORATED BY REFERENCE

52.214-3
Amendments To Invitations For Bids
DEC 1989
52.214-4
False Statements In Bids
APR 1984
52.214-5
Submission Of Bids
MAR 1997
52.214-6
Explanation To Prospective Bidders
APR 1984
52.214-7
Late Submissions, Modifications, and Withdrawals of Bids
NOV 1999
52.214-10
Contract Award--Sealed Bidding
JUL 1990
52.214-12
Preparation Of Bids
APR 1984
52.214-18
Preparation of Bids-Construction
APR 1984
52.214-19
Contract Award-Sealed Bidding-Construction
AUG 1996
52.222-23
Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction
FEB 1999

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm Fixed-Price contract resulting from this solicitation.

(End of provision)

52.222-5 Construction Wage Rate Requirements--SECONDARY SITE OF THE WORK (MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of provision)

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from 911th Airlift Wing, Contracting Office, 2375 Defense Avenue, Coraopolis, PA 15108

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for—

16 December 2014, 10:00 A.M local time.

(c) Participants will meet at—

911th Airlift Wing Contracting Office, Bldg 210, Conference Room, 2475 Defense Ave, Coraopolis, PA 15108.

Contact Mr. Daniel Ellingsen, 412-474-8125 no later than 15 December 2014, in order to schedule personnel planning to attend the site visit.

(End of provision)

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http: //farsite.hill.af.mil

(End of provision)

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil

(End of provision)

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

NONE

Section M - Evaluation Factors for Award

CLAUSES INCORPORATED BY REFERENCE

52.225-10
Notice of Buy American Requirement--Construction Materials
MAY 2014