SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0001
ADDENDUM 01 FOR SOLICITATION FA6712-09-B-0001
PROJECT JLSS 09-0003
13 Mar 09
1. The solicitation for this project requests a single lump sum bid. All contractor costs are to be included in the lump sum price. Disregard any notes in the drawings specifying separate line items in the bid, including Drawing EL-1, Note O, and Drawing ES-4D, Coded Note 2.
2. Change Drawing E7-1 (Sheet 28), Details 2 through 6 to the following –
Eliminate requirement for rebar in the concrete envelope around the duct bank.
Delete note that reads “#3 Rebar 8’-0” O.C.”
Delete note that reads “#4 Rebar Continuous (5 Places).”
3. Add a requirement to provide the following:
All pad-mounted switchgear and transformers shall be secured using padlocks supplied by the contractor. Padlocks shall be number 21B722 with M keyway and BB-2 keying by Best Lock Corp. These can be purchased from Best Access System, POC Sue at (724) 733-2378, X42502, email Ljones@stanleyworks.com. The contractor should confirm the keying information with the Contracting Representative prior to purchasing.