B 838 HVAC Repair Questions_1.pdf
PDF 83 KB Posted
- Attached to
- Repair HVAC Building 838 Bay 1
- Solicitation number
- FA670325B0004
About this file
This document is a set of Questions and Answers (Q&A) for a B 838 HVAC Repair project. The Q&A covers key technical and operational details including valve replacement requirements, reuse of existing controls for AHU-6, personnel qualifications, project phasing, and performance period. Highlights include guidance to replace heat valves in kind with GPM requirements, reuse of existing AHU-6 controls, flexibility for having one person fulfill superintendent, SSHO, and QC manager roles, and a requirement to provide a schedule minimizing user impact.
Additional important details include confirmation of no known asbestos or lead issues, tax exemption status, and surface restoration limited to only impacted areas. The government will provide building controls contractor and fire alarm company contact information after award. The project involves specific site access considerations referenced in section 3.3, and while a site visit was offered, no photos of existing conditions were available. The document indicates phasing requirements exist and that the contractor must develop a schedule to minimize disruption to building occupants, though the number of occupants remains unknown.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B 838 HVAC Repair Questions
1. During the walkthrough today (9-8-25), I noticed several of the air handler units had 2-way heat valves and other had 3-way heat valves. Is the government good with replacing the valves as they are or do they want all 3-way valves?
Replace the valves in kind with gpm requirement on the plans.
2. AHU-6 Controls were replaced a couple of years ago. Should the new controllers and zone temperature/humidity/Co2 sensors be re-used and just replace devices on new Air Handler or does the government desire the new controllers and zone temperature/humidity/Co2 sensors?
AHU-6 controls should be reused.
3. Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?
We can have one person fulfill this as long as they are qualified to do all parts and they are on site during construction.
4. Are there any phasing requirements?
Yes, See 1.1.3 and 3.2.1. The contractor is responsible to providing a schedule that will minimize the impact to the user.
5. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?
The Gov’t cannot guarantee extension of the period of performance.
6. Are there any temporary heating/cooling requirements?
No
7. If the building remains occupied, how many people will be in the building?
Unknown
8. Please confirm whether asbestos or lead is present on this project, and if so, provide the relevant documentation.
There are no known asbestos or lead issues in the scope of this project.
9. Please provide the contact information for the building controls contractor.
Provided after award.
10. Please provide the contact information for the building fire alarm company.
Provided after award.
11. Please provide the site visit attendee sign-in sheet.
Attached
12. Please provide photos of the job site and existing conditions.
No Photos are available
13. Is this project tax exempt?
Yes
14. Are there gate hours, escort requirements, or delivery blackout periods that impact mobilization and large equipment deliveries?
Please, see section 3.3
15. Please provide additional details on the ceiling removal and replacement scope. Please provide existing ceiling types by location as well as height AFF.
Site visit was offered.
16. What level of surface restoration is required? Corner to corner or only in impacted areas.
Only impacted areas.