Attachment 1

STATEMENT OF WORK

Niagara Falls Air Reserve Station

Building #317:

• Clean and sanitize two (2) existing HVAC systems that serve the above referenced facility to include the following:

1. Two (2) Air Handling Units to include supply/return air fans, coils, unit housings and walls, and access panels.

2. +/- 85 feet of galvanized bare return air ductwork (including horizontals and risers).

3. +/- 740 feet of galvanized bare supply air ductwork (including horizontals and risers).

4. All associated flexible supply air ductwork.

5. Thirty eight (38) supply air diffusers.

6. Twenty (20) return air grilles.

7. Eleven (11) VAV boxes.

8. All inline devices including turning vanes and volume dampers.

• Clean and coat

1. All fiberglass lined unit interiors.

2. +/- 30 feet of fiberglass lined supply air ductwork (including horizontals and risers).

3. +/- 40 feet of fiberglass lined return air ductwork (including horizontals and risers).

• Furnish and install all access doors needed for cleaning.

Building #821:

ITEM #1: HVAC System Cleaning

• Clean: one (1) HVAC system and various exhaust systems Firehouse to include the following:

1. One (1) Air Handling Unit (AHU #1) and one (1) Return Air Fan.

2. All associated rooftop exhaust air fans.

3. All associated supply air ductwork.

4. All associated return air ductwork.

5. All associated exhaust air ductwork.

6. All associated supply diffusers.

7. All associated return/exhaust grilles.

8. All associated VAV boxes and Reheat Coils.

• Furnish and install any access panels needed for cleaning.

• Apply microbial reduction agent to all associated supply & return ductwork.

• Provide Post Remediation Report including photo documentation.

Notes:

• Utilize personnel trained for Confined Space Entry.

Clean and coat
ITEM #1: HVAC System Cleaning
Clean: one (1) HVAC system and various exhaust systems Firehouse to include the following:
1. One (1) Air Handling Unit (AHU #1) and one (1) Return Air Fan.
2. All associated rooftop exhaust air fans.
3. All associated supply air ductwork.
4. All associated return air ductwork.
5. All associated exhaust air ductwork.
6. All associated supply diffusers.
7. All associated return/exhaust grilles.
8. All associated VAV boxes and Reheat Coils.
Furnish and install any access panels needed for cleaning.
Apply microbial reduction agent to all associated supply & return ductwork.
Provide Post Remediation Report including photo documentation.
Notes:
Utilize personnel trained for Confined Space Entry.