RFQ Solicitation FA663326QA009_Yamry Construction Inc.pdf

PDF 645 KB Posted

Attached to
Remove & Replace Bullet Proof Glass Bldg. 906
Solicitation number
FA663326C0008
Issued by

About this file

Summary

This is a Request for Quote (RFQ) from the 934th Airlift Wing, Minneapolis–St. Paul Air Reserve Station for removal and replacement of bullet-proof glass in Building 906. Yamry Construction, Inc., a Service-Disabled Veteran-Owned Small Business based in Saint Joseph, Minnesota, submitted this technical and price proposal on July 29, 2026, for Solicitation Number FA663326QA009 (Project QJKL 26-0020). The contractor proposes a firm-fixed-price of $84,900.00 on an FOB Destination basis, with work completion within 120 calendar days after Notice to Proceed. The proposal specifies installation of a custom three-station ballistic barrier system using Armortex 1-1/4-inch SP1250 Lexgard polycarbonate rated UL 752 Level 3 and compliant with applicable NIJ Type IIIA requirements, approximately 19 feet 2 inches wide by 4 feet high with an 18-inch drop at the ADA station.

The technical approach includes preconstruction field verification, submittal of manufacturer shop drawings and technical documentation for Government approval before fabrication, careful removal of existing glazing systems with finish restoration, installation with quality control oversight, and comprehensive closeout including as-built drawings and warranties. Matthew C. Lindstrom, President/CEO with 25 years of construction management experience in ballistic-resistant systems for federal buildings and U.S. Embassies, will serve as onsite superintendent. The proposal assumes normal Monday–Friday working hours (7:00 a.m.–3:30 p.m.) with off-hours coordination, incorporates prevailing wage requirements, and includes payment bond or letter of credit furnished after award. The offer is valid for 60 calendar days from submission, and the contractor commits to compliance with all contract terms, conditions, and special Section H requirements identified in the solicitation.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

YAMRY CONSTRUCTION, INC.

UEI: TK29EE387AG8

REQUEST FOR QUOTE (RFQ) REMOVE & REPLACE BULLET-PROOF GLASS BUILDING 906

Solicitation Number FA663326QA009

Caleb C. Anderson Contracting Specialist | 934th Contracting Office

934th Airlift Wing, Minneapolis–St. Paul Air Reserve Station 860 Military Hwy Room 229

Minneapolis, Minnesota

July 29, 2026

545 8th Avenue NE, St. Joseph, MN 56374

Matthew Lindstrom, President & CEO

(320) 291-2637 | matt@yamryconstruction.com mailto:matt@yamryconstruction.com 1137525662C Inserted Text cole@alphaonesource

YAMRY CONSTRUCTION, INC. | FA663326QA009

YAMRY CONSTRUCTION, INC.

TECHNICAL & PRICE

PROPOSAL

Removal & Replacement of Bullet-Proof Glass – Building 906

Minneapolis–St. Paul Air Reserve Station

BUILT FOR RESPONSIVE DELIVERY

• Established in 1998

• Service-Disabled Veteran-Owned Small Business

• Minnesota-based commercial general contractor

• Federal, state, municipal, military, educational, and commercial experience

• Experienced ballistic window, doors, glazing contractor.

SOLICITATION FA663326QA009

PROJECT QJKL 26-0020 – Sustain Bullet-Proof Glass, B906

SUBMITTED TO 934th Airlift Wing, Minneapolis–St. Paul Air Reserve Station

SUBMISSION DATE July 29, 2026

TOTAL PROPOSED PRICE $84,900.00

Yamry Construction, Inc.

545 8th Avenue NE Saint Joseph, MN 56374 www.yamryconstruction.com

Matthew C. Lindstrom, President/CEO 320-291-2637 Matt@yamryconstruction.com

SAM UEI: TK29EE387AG8

1 Offer & Executive Summary

Yamry Construction, Inc. respectfully submits this firm-fixed-price quotation to provide all supervision, labor, materials, equipment, transportation, quality control, safety management, removal, installation, testing support, cleanup, and closeout services required to replace the existing bullet-resistant glazing system at Building 906.

Yamry has reviewed the Statement of Work, technical specifications, drawings, submittal register, wage determination, provisions and clauses, and Section H special contract requirements. Yamry proposes a complete installation meeting the specified UL 752 Level 3 ballistic rating and applicable NIJ Type IIIA requirements, subject to Government approval of manufacturer shop drawings, product data, certificates, and installation details. All work will be completed within 120 calendar days after Notice to Proceed.

ONSITE LEADERSHIP

Matthew C. Lindstrom, President/CEO, will serve as onsite superintendent throughout installation. Mr. Lindstrom has more than 25 years of construction management experience, including directing and inspecting forced-entry and ballistic-resistant doors, windows, and glazing systems for federal buildings, military installations, and U.S. Embassies.

Local and Responsive Execution Yamry is located within convenient driving distance of the Minneapolis–St. Paul Air Reserve Station. This regional presence supports prompt field verification, efficient mobilization and delivery coordination, direct involvement by company leadership, and timely punch-list or warranty response without dependence on long-distance travel.

OFFER COMMITMENTS

Firm-fixed-price offer: $84,900.00

FOB Destination: Building 906, Minneapolis–St. Paul Air Reserve Station

Offer validity: 60 calendar days

Contract completion: within 120 calendar days after NTP

2 Technical Approach

2.1 Preconstruction & Field Verification

• Participate in the preconstruction conference and coordinate base access, security, working hours, staging, deliveries, and protection requirements.

• Field-verify openings, counters, soffits, deal trays, ADA station geometry, cable pass-throughs, and adjoining finishes before fabrication.

• Submit the baseline schedule, submittal register, Accident Prevention Plan, Activity Hazard Analysis, contact list, product data, ballistic certificates, and manufacturer shop drawings.

2.2 Proposed Ballistic Glazing System

The proposed basis-of-design is an Armortex custom three-station ballistic barrier system approximately 19 feet 2 inches wide by 4 feet high, with an additional 18-inch drop at the ADA station. Yamry has obtained Armortex Quote QT066689 for a custom-fabricated system using 1-1/4-inch SP1250 Lexgard polycarbonate rated UL 752 Level 3.

The proposed assembly includes compatible clear or dark-bronze anodized aluminum U-channel at the counter and vertical joints, aluminum F-channel at the head, transaction-area components, dowel assembly hardware, fasteners, and manufacturer-prepared shop drawings.

PROPOSED SYSTEM SUPPLIER

UL 752 Level 3 ISO 9001 Certified

Custom shop drawings

Armortex will fabricate the system following Yamry’s verified field measurements and Government approval of the technical submittal. Final frame construction, deal-tray configuration, anchorage, finish selection, and interface details will conform to the approved shop drawings and contract requirements.

2.3 Removal & Installation

• Protect counters, adjacent finishes, equipment, circulation paths, and non-work areas from dust, debris, and damage.

• Carefully remove the existing polycarbonate barrier and framing without damaging work designated to remain.

• Remove demolition debris from the installation and dispose of it off site in accordance with contract requirements.

• Install the approved ballistic glazing and framing plumb, level, rigid, aligned, sealed, and anchored in accordance with manufacturer instructions.

• Maintain ADA station geometry, transaction-counter functions, cable pass-throughs, and required clearances.

2 Technical Approach – Continued

Pre-Staging & Finish Restoration Yamry will receive the ballistic glazing system at its St. Joseph facility, inspect the shipment for damage and completeness, and pre-stage the assembly before mobilization. Verified field dimensions will be reconciled with the fabricated components using a measure-twice, cut-once approach to minimize onsite adjustments, noise, dust, and disruption within the ID office.

Where the thicker glazing assembly requires selective wall modification, Yamry will perform controlled cutting, required backing or framing adjustments, and complete patching and finish restoration. Disturbed masonry, gypsum board, casework, counters, wall base, and adjacent finishes will be restored to a condition equal to or better than the preconstruction condition.

2.4 Quality, Safety & Closeout

• Provide qualified superintendent, quality-control, and site-safety oversight during onsite activities.

• Perform preparatory, initial, and follow-up inspections; maintain required daily records and progress photographs.

• Conduct pre-final and final inspections, complete punch-list corrections, and deliver as-built drawings, material records, warranty documentation, and construction/debris reporting.

• Provide the specified five-year glazing-material warranty and one-year overall construction warranty.

EXECUTION PRIORITY

The visitor control center is a sensitive operational environment. Yamry’s approach emphasizes controlled demolition, clean work practices, short onsite duration, direct supervision, and complete daily restoration of the work area.

Primary Deliverables

PRECONSTRUCTION TECHNICAL CLOSEOUT

Schedule • APP/AHA • Submittal register Shop drawings • Product data • Certifications As-builts • Warranties • Final records

3 Compliance Summary

REQUIREMENT STATUS YAMRY RESPONSE

Period of performance COMPLIES Complete within 120 calendar days after NTP.

Ballistic protection COMPLIES UL 752 Level 3 / applicable NIJ Type IIIA documentation submitted for approval.

FOB requirement COMPLIES FOB Destination, Building 906, Minneapolis–St. Paul ARS.

Working hours COMPLIES Normal hours Monday–Friday, 7:00 a.m.–3:30 p.m.; off-hours work coordinated in advance.

Prevailing wages COMPLIES Applicable wage determination and labor requirements included in pricing.

Submittals COMPLIES Schedule, APP/AHA, shop drawings, product data, certificates, and closeout records.

Payment protection COMPLIES Payment bond or irrevocable letter of credit furnished after award as directed.

Offer validity COMPLIES Price remains firm for 60 calendar days after the quotation due date.

TECHNICAL ACCEPTANCE

Yamry will not release the custom ballistic system for fabrication until field dimensions are confirmed and the Government-approved submittal establishes the final assembly configuration.

4 Preliminary Performance Schedule

CALENDAR

DAYS PHASE PLANNED ACTIVITIES

1–10 Preconstruction Kickoff, access coordination, field verification, schedule, APP/AHA, and submittal register.

1–24 Submittal Review Shop drawings, product data, certifications, installation details, and Government review.

25–94 Fabrication Release approved system; anticipated manufacturer lead time of 8–10 weeks.

85–100 Delivery Planning Confirm delivery, staging, access, protection, crew, and installation sequence.

101–107 Onsite Construction Protection, removal, installation, sealing, restoration, and cleanup.

108–115 Inspection / Closeout Pre-final/final inspection, punch list, as-builts, warranties, and final records.

By Day 120 Contract Completion All work and required closeout deliverables complete.

YAMRY SCHEDULE APPROACH

Yamry approaches each project collaboratively, engaging the Government, suppliers, subcontractors, and field personnel in planning and scheduling from the earliest practical point. Frequent communication keeps current status, constraints, work handoffs, and upcoming milestones visible to all parties. Yamry utilizes Pull Planning, based on Last Planner System principles, to coordinate activities backward from required milestones.

To minimize disruption and protect the privacy of personnel visiting the ID section during normal business hours, Yamry recommends performing the primary removal and installation over one weekend, with approximately (2) two days of onsite construction. This approach is subject to Government approval and advance coordination of base access, security, and off-hours work requirements.

5 Price Proposal

CLIN 0001 – PRICE COMPONENT AMOUNT

Project management, mobilization, field verification, submittals, and safety planning $11,750.00 Ballistic glazing system, components, shop drawings, freight, and use-tax allowance $34,834.00 Protection, temporary storage, demolition, debris handling, and off-site disposal $3,200.00 Installation labor, supervision, equipment rental, quality control, and safety oversight $17,100.00 Anchors, compatible sealants, miscellaneous materials, handling, and equipment $3,600.00 Finish restoration, inspections, as-builts, warranties, and closeout $3,500.00 Insurance/bond, overhead, and profit $10,916.00

TOTAL FIRM-FIXED-PRICE $84,900.00

Pricing includes FOB Destination delivery to Building 906 and all work necessary for a complete installation consistent with the solicitation documents. No prompt-payment discount is offered. Payment terms are those established by the contract.

Assumptions & Clarifications

• Final dimensions will be field verified before fabrication; Government approval of manufacturer shop drawings and technical submittals is required before material release.

• Existing transaction counters and adjoining casework remain unless limited modification is necessary for the approved installation.

• The proposal assumes no hazardous-material abatement, concealed structural reconstruction, utility relocation, or electrical-system modification.

• Government utilities and restroom facilities will be available as stated in the SOW.

• Work outside normal duty hours will be performed only with advance Government approval.

• If a conflict exists between this proposal and the solicitation, the solicitation and resulting contract govern.

6 Offeror Representations & Acceptance

Yamry Construction, Inc. agrees with all terms, conditions, provisions, attachments, and applicable amendments included in Solicitation FA663326QA009. Yamry is registered in the System for Award Management and will maintain all required insurance and post-award payment protection. This quotation is valid for 60 calendar days from July 29, 2026.

AUTHORIZED REPRESENTATIVE

Name: Matthew C. Lindstrom Title: President/CEO Company: Yamry Construction, Inc.

SAM UEI: TK29EE387AG8

ACCEPTANCE

Signature

Date

SUBMISSION CONTACT

Matthew C. Lindstrom, President/CEO | 320-291-2637 | Matt@yamryconstruction.com

Yamry Construction, Inc. | 545 8th Avenue NE, Saint Joseph, MN 56374

July 29, 2026

Yamry_Preconstruction_Cover Page_Revision_3
Yamry_Proposal_FA663326QA009_Modern_Rebuild
Local and Responsive Execution
2.1 Preconstruction & Field Verification
2.2 Proposed Ballistic Glazing System
2.3 Removal & Installation
Pre-Staging & Finish Restoration
2.4 Quality, Safety & Closeout
Primary Deliverables
Assumptions & Clarifications