This document is a Request for Information (RFI) for a contract involving 3 snowplows with flexible blades, identified by RFI No. 0002 and Contract No. FA66062500002. The RFI was submitted on 12/26/2025 and focuses on determining whether quick couplers/connects are still a required salient feature for the snowplow equipment. The WARB (Weapon Acquisition Review Board) response indicates that quick connects are no longer required. The RFI form includes a standard note emphasizing that the information request does not authorize additional work and that any changed conditions must be formally communicated to the Contracting Officer's Representative.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION REPORT (RFI)

RFI NO. PAGE NO.

Page 1 of

CONTRACT NO. CONTRACT TITLE PRIME CONTRACTOR

Contractor's Request for Information

REQUESTED BY: DATE REQUESTED Potential Cost Impact

[No] Potential Schedule

Impact [No]SUBCONTRACTOR

RFI

SUBJECT:

DRAWINGS

INFORMATION REQUESTED:

ATTACHMENTS FROM CONTRACTOR: (1 attachment)

Question 01:

NOTE: THE RFI SYSTEM IS INTENDED TO PROVIDE AN EFFICIENT MECHANISM FOR RESPONDING TO CONTRACTOR'S REQUESTS FOR

INFORMATION. IT DOES NOT PROVIDE AUTHORITY TO PROCEED WITH ADDITIONAL WORK. IF THE CONTRACTOR CONSIDERS

THE RFI RESPONSE A CHANGED CONDITION, PROVIDE WRITTEN NOTICE TO THE CONTRACTING OFFICER'S REPRESENTATIVE

IN ACCORDANCE WITH CONTRACT PROVISIONS.

QA REVIEWER'S SIGNATURE DATE

RFI FORM

WARB Response: WARB states that quick connects are required any longer.

1250170374C Inserted Text vvv

RFI NO: 0002
PAGE NO Page 1 of: 1
CONTRACT NO: FA660626Q0002
CONTRACT TITLE: 3 SNOWPLOWS WITH FLEXIBLE BLADES
PRIME CONTRACTOR:
Contractors Request for Information:
REQUESTED BY:
DATE REQUESTED: 12/26/2025
Potential Cost Impact No Potential Schedule:
SUBCONTRACTOR:
RFI:
DRAWINGS:
INFORMATION REQUESTEDRow1:
ATTACHMENTS FROM CONTRACTOR 1 attachment:
Question 01: Are quick couiplers/connects required as a salient feature?
QA REVIEWERS SIGNATURE: