Questions_Answers.doc

DOC document 29 KB Posted

Attached to
Wetland Deliniation Federal contract opportunity
Solicitation number
FA6606-11-T-0001
Issued by
Department of the Air Force Reserve Command

View the file

Other files for this federal contract opportunity

Other files attached to Wetland Deliniation, newest first.
File Type Posted
More Qs and As re YTPM 11 7026 Wetland Delineation.doc DOC document
GuidanceVegMgmtAirports.pdf PDF
FA6606-11-T-0001.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers FA6606-11-T-0001

Q: Delineation worksheets (scope item 2): will both federal (Army

Corps) and state worksheets (for Bordering Vegetated Wetlands) be required or just one of these?

A: Both. USACE to show all 3 criteria are met for wetlands meeting its requirements.

Per Ludlow Conservation commission regulations:

In order for the Commission to approve a wetland delineation, an Appendix G form (from the manual Delineating Bordering Vegetated Wetlands Under the

Massachusetts Wetlands Protection Act) shall be required. Appendix G must be provided and signed by the individual who performed the delineation.

Q: If just one, which - federal or state?

A: Not applicable.

Q: Should we assume the permit application per scope item 3 is Notice of Intent (not an Abbreviated Notice of Resource Delineation)?

A: Yes, NOI for VMP Q: Is there an existing vegetation management plan, which is typical requirement for airstrip maintenance?

A: Yes, it will be updated slightly.

Q: If so can the vegetation management plan be made available to the successful respondent?

A: Yes.

Q: If there is not an existing vegetation management plan should respondents assume one will have to be developed as part of the scope (per scope item 3)?

A: Not applicable.

Q: Has access to properties not owned by the AFB been obtained?

A: Yes

Q: Will shapefiles of existing wetland boundaries be available?

A: Yes

Q: What data sheets should be used to document wetland boundaries (ACOE and/or MA)?

A: Both

Q: Will the contractor be required to determine ILSF with volume calcs?

A: Yes, as applicable.

Q: Will it be possible to get temporary security passes issued?

A: Yes, if the person applying for the pass is not deemed to be a security risk/have outstanding warrants, etc.