DRAFT SOO WO 38CEIG-2024-00097 Aviano AB B110 Premises Wiring Upgrade v01.docx
DOCX document 930 KB Posted
- Solicitation number
- FA568225PWUpgrade
About this file
This document is a Draft Statement of Objectives (SOO) for a premises wiring upgrade project at Aviano Air Base in Italy. The United States Air Forces in Europe - Air Forces Africa is seeking industry input through a Request for Information (RFI) for engineering, furnishing, installing, and testing (EFI&T) new NIPR Cat-6 cabling on the 2nd floor of Building 110, including new uninterruptible power supply (UPS) and Ethernet switch equipment. Contractors are required to remove existing outdated Cat-3/Cat-5 cabling and associated materials.
Potential offerors are requested to submit seven-page capability statements by Thursday, April 17, 2025, at 1500 PM EST, detailing their ability to perform the installation in Italy, estimated project timeline, required personnel, and any additional insights or clarification needs. Submissions should include a list of existing Government-Wide Acquisition Contracts and Federal Supply Schedule contracts. Questions and capability statements should be sent to specified Air Force contacts, referencing RFI #FA568225PWUpgrade in the subject line.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF OBJECTIVES
For
PREMISES WIRING UPGRADE, BUILDING 110, 2ND FLOOR
At Aviano AB, IT
Prepared By 38 ES/ENIU 4064 Hilltop Road Tinker AFB, OK 73145-2713
10 Feb 2025
TABLE OF CONTENTS
| 1. SCOPE | 1 |
| 2. GENERAL INFORMATION | 1 |
| 2.1 Place of Performance | 1 |
| 2.2 Performance Period | 1 |
| 2.3 Hours of Operation | 1 |
| 2.4 Holidays/Down Days | 1 |
| 3. GENERAL REQUIREMENTS | 1 |
| 3.1 Site Coordination | 1 |
| 3.2 Project Management | 1 |
| 3.3 Contractor Supervision | 1 |
| 3.4 Personnel Training and Certifications | 2 |
| 3.5 Safety | 2 |
| 3.6 Accident/Incident Reporting and Investigation | 2 |
| 3.7 Security Clearances | 2 |
| 3.8 Base Access | 2 |
| 3.9 Identification/Marking | 2 |
| 3.10 Environmental Management | 2 |
| 3.11 Permits | 3 |
| 3.12 Reserved | 3 |
| 3.13 Labor Compliance | 3 |
| 3.14 In-brief and Out-brief | 3 |
| 3.15 Work Area(s) | 3 |
| 3.16 Packaging, Handling, Storage, and Transportation | 3 |
| 3.17 Documentation | 3 |
| 3.18 Implementation | 4 |
| 4. SPECIFIC REQUIREMENTS | 4 |
| 4.1 Sustainment | 4 |
| 4.2 Standards | 4 |
| 4.3 Labelling | 4 |
| 4.4 Rack Cabinet | 4 |
| 4.5 Network Equipment | 4 |
SOO - Premises Wiring Upgrade, Building 110, 2nd Floor at Aviano AB ii
| 4.6 Cable Pathway | 5 |
| 4.7 Bonding and Grounding | 5 |
| 4.8 Structured Cabling Requirements | 5 |
| 4.9 Removal and Disposal | 7 |
| 4.10 Restoration | 7 |
| 4.11 Service Outages | 7 |
| 4.12 Contractor Furnished Materials | 7 |
| 4.13 Warranty | 7 |
| 4.14 Manuals and Practice | 7 |
| 4.15 Quality Assurance | 7 |
| 4.16 Weekly IPT Meeting | 8 |
| 4.17 Weekly Status Reports | 8 |
| 4.18 Project Schedules | 8 |
| 4.19 Cutover Plan | 8 |
| 4.20 Test Plan | 8 |
| 4.21 Testing Requirements | 8 |
| 4.22 Test Report | 8 |
| 4.23 As-Built Drawings | 8 |
| 4.24 Final Acceptance/Project Completion | 9 |
| 4.25 Deliverables | 9 |
| 5. GOVERNMENT-FURNISHED PROPERTY, EQUIPMENT, AND SERVICES | 9 |
| APPENDIX A | APPLICABLE DOCUMENTS AND STANDARDS .....................................A-1 |
| APPENDIX B | LABELING STANDARDS ............................................................................. B-1 |
| ATTACHMENT A | LAYOUT DRAWINGS ...................................................................... ATT-1 |
1. SCOPE. This Statement of Objectives (SOO) defines the requirements for the Contractor to engineer, furnish, install, and test (EFI&T) a premises wiring upgrade to new NIPR Cat-6 cabling for the 2nd floor of Building 110 (B110) at Aviano, IT. The premises wiring upgrade shall include the provision of new uninterruptible power supply (UPS) and Ethernet switch equipment. The Contractor shall remove the existing outdated and abandoned-in-place (AIP) Cat-3/Cat-5 cabling from the building, including any residual materials, upon completion.
2. GENERAL INFORMATION.
2.1 Place of Performance. The place of performance shall be Aviano AB, IT.
2.2 Performance Period. The period of performance for this project shall be determined based on the proposed schedule and the actual contract award date. All work shall be completed within the scheduled timeframe. Any request or justification for changes shall be made to the designated Government Contracting Officer (CO) in writing and must be approved by the Government CO.
2.3 Hours of Operation. The Contractor shall perform routine work during the normal duty hours of the base (normally Monday to Friday, 0730-1630 CET). However, mission requirements may necessitate work outside of normal hours, such as during maintenance windows, nights, and/or weekends, especially if existing services must be interrupted. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated in advance with the Government CO and the designated base Point of Contact (POC) for pre-approval.
2.4 Holidays/Down Days. The Contractor shall not perform work under this contract on federal holidays or site-specific down days unless expressly authorized by the Government CO and coordinated with the base POC.
3. GENERAL REQUIREMENTS. The Contractor shall provide all personnel, transportation, supervision, management, coordination, labor, and other incidentals for the entire premises wiring upgrade project. The Contractor shall coordinate with the base to obtain all necessary supports for successful project completion and to ensure mission continuity during implementation.
3.1 Site Coordination. The Contractor shall coordinate with the base POC a minimum of 10 business days prior to arrival on-site. The Integrated Product Team (IPT) members shall also be identified for this project, including the base POC, Contractor representatives, Government CO, 38 ES program manager, 31 CS/SCXP and SCOI, allied supports, and other base personnel as required.
3.2 Project Management. The Contractor shall identify by name a project manager (PM), who shall be the prime Contractor’s employee, responsible as the single POC from award to final acceptance. The PM shall remain on site as necessary to ensure successful performance. The Contractor shall identify the PM’s range of authority to act for the Contractor relating to daily contract operation.
3.3 Contractor Supervision. The Contractor shall be responsible for supervision of all contract personnel and performance of all Contractor-related functions.
SOO - Premises Wiring Upgrade, Building 110, 2nd Floor at Aviano AB
3.4 Personnel Training and Certifications. All Contractor personnel identified to support this requirement shall be trained and/or certified on the systems involved in this effort. The Contractor shall be able to provide certifications or qualifications upon Government request.
3.5 Safety. The Contractor shall comply with all federal, state, host nation, and base security and safety laws, regulations, policies, and requirements. If at any time it is determined that equipment is unsafe and/or work is being performed in an unsafe manner, all work will be immediately suspended until the Contractor has corrected the problem to the satisfaction of the base. The Contractor shall meet with the base Safety Officer (SO) immediately upon arrival on site for review of the specific safety requirements prior to implementation.
3.6 Accident/Incident Reporting and Investigation. The Contractor shall record and report all available facts relating to each instance of injury to either Contractor or Government personnel to the base SO or POC unless otherwise stated in the SOO. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the base POC. If the Government elects to conduct an investigation of the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.
3.7 Security Clearances. There are no security requirements for performance of this project. It is the Government's responsibility to provide escorts. All Contractor personnel shall comply with established security procedures for entering an installation and its facilities. The Contractor personnel working under this project shall not require a security clearance but, as a minimum, shall have a favorable National Agency Check. However, if the proposed solution requires a need for access to Government system(s) requiring a higher security level, the Contractor shall ensure personnel have the proper security requirements at no additional cost to the Government.
3.8 Base Access. The Contractor shall coordinate with the base POC for base access/entry pass requirements and process a Site Visit Access Request Letter to obtain access to the base. This letter shall identify the name, home address, birth date and place, nationality, physical description, passport number, driver’s license number or government issued identification (ID), social security number, etc. of the personnel who will be performing work on this project. This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual and company name, be clearly and distinctly marked as Contractor, and be in accordance with (IAW) the base regulations.
3.9 Identification/Marking. The Contractor shall clearly mark all Contractor-furnished Property/ Contract-furnished Equipment (CFP/CFE) with their company's name. The Contractor shall place an easily read, very visible sign (minimum 8.5" x 11") on large containers, construction equipment, or un-manned rental vehicles while on the base or Government installation indicating the company name and both the Contractor POCs and local telephone numbers.
3.10 Environmental Management. The Contractor shall comply with most stringent federal, state, host nation, local, and base environmental laws and regulations and Air Force policies, instructions, and plans. The Government is not exempt from compliance with environmental laws and regulations. The Contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on the base. The prime Contractor shall ensure their sub-contractors, if any, comply with these requirements.
3.11 Permits. The Contractor shall complete and process all permits as required to complete the installation. For example:
· Digging permit, AF Form 103 shall be submitted through the base Civil Engineering (CE) 21 calendar days in advance of any digging, trenching, boring, restoration and/or compacting activities.
· Base CE Work Clearance Request, AF Form 332 and Request for Environmental Impact Analysis, AF Form 813 required to complete the installation shall be submitted through the base CE 21 calendar days in advance of any construction activities.
3.12 Reserved.
3.13 Labor Compliance. The Contractor shall be responsible for complying with all federal labor laws and with applicable regulations governing installation access.
3.14 In-brief and Out-brief. The Contractor shall conduct an in-brief with the IPT members prior to the start of implementation, as well as an out-brief after project completion. The in-brief shall cover all of the Contractor’s implementation plans and necessary support requirements. The out- brief shall cover all equipment installations, implementation results, required maintenance, and warranties, at a minimum.
3.15 Work Area(s). At day’s end, the Contractor shall remove all debris and surplus materials from the workplace. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard.
3.16 Packaging, Handling, Storage, and Transportation. The Contractor shall be responsible for the packaging, handling, storage, transportation, staging, and deployment of any equipment and materials provided as part of this project. The Contractor shall coordinate with the base POC to identify any necessary base support, such as laydown and storage areas, and provide a plan for delivering all materials to the work site. The Contractor shall also be responsible for equipment inventory. The Contractor shall return all government-furnished laydown and storage areas to their original condition upon completion of the project. In addition, the Contractor shall be responsible for off-base disposal of residues and removed equipment IAW the base POC’s instructions, Defense Logistics Agency (DLA) and AFB policies, and federal, state, and local environmental laws and regulations.
3.17 Documentation. The Contractor shall verify the accuracy of all government-furnished documents and drawings. The Contractor shall comply with DoD security provisions and shall not divulge any government-furnished documentation or other knowledge that may be gained to anyone who is not authorized to have access to such information. All Contractor deliverables shall be marked IAW DoDM 5200.01, Vol. 3 & Vol. 4, Information Security, and DoDM 5400.07, Freedom of Information Act Program, unless otherwise directed by the Government.
3.18 Implementation. The Contractor shall have ultimate responsibility for the successful completion of the project. Any work deemed non-compliant shall be reworked immediately at the Contractor’s expense. The Contractor shall plan and manage daily operations and activities associated with project performance. The Contractor will employ effective management tools and methods to ensure control of cost, schedule, and performance. The Contractor shall conduct, support, and/or participate in program management and technical reviews, meetings, and conferences, as required, to ensure the effective and efficient execution of this project. The Contractor shall ensure the protection of government property to prevent damage during project performance.
4. SPECIFIC REQUIREMENTS. The Contractor shall provide all equipment, tools, supplies, materials, hardware, licensing, documentation, manuals, and services necessary for the completion of the project. The Contractor shall comply with all current ANSI/TIA telecommunications installation and testing commercial standards, as well as Aviano AB construction standards. All upgrade equipment, supplies, hardware, and materials shall be new and not refurbished.
4.1 Sustainment. It is required that all purchased equipment be maintainable and supportable for at least five (5) years. Government Re-use Equipment (GRE) does not have to meet this requirement.
4.2 Standards. All installations, including rack cabinets, racks, cabling (communications, power, grounding, etc.), equipment, pathways, raceways, cable management, patch panels, and related hardware/components, shall be IAW the Aviano AB standards and the standards referenced in Appendix A, Applicable Documents and Standards. In secure areas, all installations shall comply with AFSSI 7702 “Emission Security Countermeasures” and NSTISSAM Tempest/2-95 “NSTISSAM Red/Black Installation Guidelines.”
4.3 Labelling. All equipment, rack cabinets, racks, cables, faceplates, patch panels, powers, and relevant components shall be labeled appropriately IAW the Aviano AB standards and the standards referenced in Appendix B, Labeling Standards, as well as the current version of TIA-606. All labeling shall be completed using a permanent method; handwritten labeling shall not be authorized.
4.4 Rack Cabinet. The existing rack cabinet in the equipment room on the 2nd floor of B110, as shown in Attachment A, Layout Drawings, shall be reused for the Cat-6 premises wiring upgrade. The Contractor shall coordinate with the base POC and 31 CS/SCXP to identify the correct rack cabinet for reuse. The Contractor shall ensure the existing rack cabinet is properly bonded and grounded to the building ground system.
4.5 Network Equipment. The Contractor shall procure the following new equipment and provide them to the base POC and 31 CS/SCOI for installation and configuration in the existing rack cabinet. These new equipment must be TAA-compliant. The Contractor shall coordinate with the base POC and SCOI to verify prior to procurement.
· One (1) Cisco Catalyst C9300-48P-A 48-port PoE+ Switches, including a Cisco PWR-C1- 715WAC-P/1 715W AC Primary Power Supply
· One (1) Cisco Catalyst C9300-NM-4G 4x1GE Network Module
· One (1) Cisco PWR-C1-715WAC-P/2 715W AC Secondary Power Supply
· Two (2) Cisco GLC-LH-SM 1GE SFP Transceiver Modules, LC connection
· One (1) IEC 3kVA 3kW, rack-mounted UPS (Eaton 9PX3000IRT2U or equivalent)
4.6 Cable Pathway. The Contractor shall install appropriate cable pathway support hardware, such as cable trays, ladders, risers, caddy straps/slings, J-hooks, dropouts, conduits, ducts, sleeves, and other relevant components, for the entire NIPR Cat-6 cable runs, IAW industry and installation standards. The existing solid bottom cable tray, as shown in Attachment A, Layout Drawings, shall be reused as much as possible. The Contractor shall ensure that all cable tray, ladder, and riser sections shall be bonded together and grounded to the building grounding system. The Contractor shall also ensure that the cable pathway supports are properly sized, with the calculated maximum fill ratio and/or non-continuous cable support (J-hooks or caddy straps/slings) intervals IAW UFC 3-580-01.
4.7 Bonding and Grounding. All rack cabinets, including rack bonding busbars, as well as all cable trays, ladders, and risers, shall be bonded and grounded to the building grounding system IAW Mil-Std-188-124B, Mil-Hdbk-419A, Vol. I and II, or the current version of TIA-607. The Technical Order (TO) 31-10-24, “Installation Practices – Communication Systems Grounding, Bonding, and Shielding,” shall also be adhered to. All bonding and grounding conductors shall be continuous and routed in the shortest practical straight-line path. The Contractor shall test and document any new or extended ground at the rack cabinet and at the new bonding and grounding points. The Government reserves the right to perform any of the Contractor-performed tests to ensure compliance.
4.8 Structured Cabling Requirements. The layout for the new NIPR Cat-6 drop outlets/locations on the 2nd floor of B110 is shown in Attachment A, Layout Drawings. There is a total of 11 new cat-6 dual-drop outlets, resulting in a total of 22 drop cables. The drop locations shown in the layout are approximate and not to scale.
4.8.1 The Contractor shall provide all new cables, termination hardware, connections, and other associated components, which must be Cat-6 compliant. All Cat-6 cables shall be unshielded twisted pair (UTP) and made of solid pure copper wire no smaller than 24 AWG. Plenum-rated Cat-6 cables shall be utilized where required by industry and applicable standards.
4.8.2 All Cat-6 cables shall be wired and terminated using the T568A wiring scheme. The Contractor shall coordinate with the base POC and 31 CS/SCXP to verify the wiring scheme. All Cat-6 cable installations shall be tested IAW the current version of TIA-568.2 to meet wiremap, length, and speed performance specifications.
4.8.3 All Cat-6 cable jackets and outlets, including patch cords, shall adhere to the Aviano AB color-coding scheme for identifying classification levels or networks (e.g., green for NIPRNet and red for SIPRNet). The Contractor shall coordinate with the base POC and 31 CS/SCXP to verify the color-coding scheme.
4.8.4 All Cat-6 labeling shall be IAW the Aviano AB standards or the standards referenced in Appendix B, Labeling Standards. The Contractor shall coordinate with the base POC and 31 CS/SCXP to verify the labeling scheme. All labeling must be completed using a permanent method; handwritten labeling is not authorized.
4.8.5 The Contractor shall provide one (1) new UTP 48-port Cat-6 patch panels and install it in the existing rack cabinet. The Contractor shall also install a new horizontal cable manager for the patch panel to keep the cable runs and patch cords organized and routed neatly within the rack cabinet.
4.8.6 Unless otherwise noted, all Cat-6 cables from the new drop locations shall be routed as “homeruns” via the cable pathway support hardware to the new Cat-6 patch panel in the existing rack cabinet. These cables shall be terminated at both the Cat-6 patch panel and the faceplates at the drop locations. All Cat-6 cabling shall adhere to the same wiring and termination standards, and no cable run shall exceed 295 ft (90 m) in length.
4.8.7 All Cat-6 cables shall be routed in a structured and orderly manner and secured within cable pathway support hardware. All Cat-6 cables shall be fanned and formed using Velcro straps to support the cabling.
4.8.8 The Contractor shall provide and install new Cat-6 patch cords for cross-connections within the rack cabinet, from the Cat-6 patch panel to the network Ethernet switch for all drops. These patch cords shall be pre-made in the same length or in a variety of lengths.
4.8.9 If surface-mounted raceway is installed on wall surfaces, the surface-mounted raceway shall be secured with appropriate anchor and screw hardware and be “off-white” in color unless otherwise noted. The surface-mounted raceway installed with adhesive tape is not authorized.
4.8.10 The existing cable routes within the walls shall be reused where possible, provided they are within the general location of user drops.
4.8.11 The Contractor shall fire-stop all cable entrances that are cut, drilled, or core-drilled into walls IAW industry and safety codes.
4.8.12 New drop installations shall be positioned at a mounting height above the finished floor IAW the base building codes and Architectural Barriers Act (ABA) compliance to allow for easy access for user patch cord connections (18 in as general practice).
4.8.13 All Cat-6 cables shall be protected from rough or sharp edges and burrs when routed through cable openings. All penetrations into the rack cabinet must be reamed, filed, and fitted with bushings or grommets. No exposed metal edges shall come into contact with the Cat-6 cabling.
4.8.14 The Contractor shall verify the specific required lengths of Cat-6 patch cords from the drop locations’ faceplates to user network devices (e.g., laptop, desktop, printer) and provide and install new Cat-6 patch cords for these connections. These patch cords shall be pre-made in a variety of lengths. The Contractor shall ensure that the total length of the cable run, cross-connection patch cord, and user-connection patch cord does not exceed 328 ft (100 m).
4.8.15 The Contractor shall remove the existing outdated and AIP Cat-3/Cat-5 cabling, including any residual materials, from the building. If the existing cables are removed from a drop location and either no longer need to be replaced with new Cat-6 cables or cannot be replaced, the drop location shall be covered with a blank faceplate.
4.9 Removal and Disposal. The Contractor shall provide for the removal and disposal of any existing equipment, cabinets, racks, cabling, hardware, and associated termination equipment, including all residues, IAW the base POC’s instructions. All removed and excess Automatic Data Processing Equipment (ADPE) shall remain U.S. government property. The Contractor shall retain such equipment as spares for the Government or dispose of them off/on-base IAW the base POC’s instructions. The Contractor must ensure compliance with DLA and AFB policies, as well as any relevant federal, state, host nation, and local environmental laws and regulations regarding disposal.
4.10 Restoration. The Contractor shall restore all disturbed areas and base property to the “as found” conditions or better after installation. Any wall penetrations shall be restored to meet the NFPA 1, NFPA 70, and/or base standards.
4.11 Service Outages. The Contractor shall be responsible for preventing any unscheduled interruptions of services caused by the Contractor (i.e., cutting or disabling any in-service cables or equipment) that are properly identified. The Contractor shall minimize downtime and interruptions to network services for base customers as much as possible during installation. If the implementation necessitates a disruption of service (e.g., communications, electrical, or other utilities), the Contractor shall coordinate planned outages with the base POC at least 2 calendar days in advance.
4.12 Contractor Furnished Materials. The Contractor shall furnish all new materials for this project, except for equipment and/or hardware currently owned or leased by the Government. The materials and/or equipment specified by the Contractor must interface properly with existing Government equipment identified for reutilization. Unless otherwise specified, the Contractor shall provide copies of commercial-off-the-shelf (COTS) technical or equipment manuals, warranty documentation, and maintenance procedures for the Contractor-furnished end-item system equipment. The Contractor shall transfer warranties to the Government upon project acceptance.
4.13 Warranty. The Contractor shall provide warranty services for workmanship deficiencies and installed equipment for a minimum period of one (1) year, starting from the date of final acceptance. The Contractor shall provide written procedures and required information for warranty services in the final acceptance form or as an attachment to the final acceptance form at or prior to site acceptance. This information shall include, but is not limited to, written confirmation of the warranty period, as well as phone numbers, contact information, and procedures for technical support, troubleshooting assistance, and replacement of faulty equipment.
4.14 Manuals and Practice. The Contractor shall provide the base POC and 31 CS/SCXP with the latest versions of operation, installation, and maintenance manuals and practices as supplied by the OEM for all new equipment installed for this project.
4.15 Quality Assurance. The Contractor shall provide a Quality Control Plan for the duration of the project. The Contractor’s quality assurance evaluator shall assist the Government representative in performing random spot checks and system acceptance tests. The Contractor shall be responsible for identifying system and outside plant deficiencies and/or discrepancies throughout the project. A weekly soft copy report shall be submitted, indicating progress/status and listing any deficiencies and/or discrepancies found, along with actions taken to correct them (CDRL A003). The Government reserves the right to perform inspections of the Contractor’s work during any and all phases of the installation.
4.16 Weekly IPT Meeting. The Contractor shall chair a weekly IPT meeting. The Contractor shall provide an agenda and a worldwide "Meet Me" teleconference capability for the duration of the project. The purpose of the IPT meeting is to discuss project progress, any issues encountered, any support needed, and other information essential to ensure the success and timely completion of contract requirements. The Contractor shall record meeting minutes and distribute them IAW CDRL A004.
4.17 Weekly Status Reports. The Contractor shall prepare a weekly status report and distribute it IAW CDRL A003. The purpose of the report is to inform IPT members of project progress, problems encountered, and other topics necessary to ensure the success and timely completion of contract requirements. The Status Report and meeting agenda may be combined, provided that the resulting report contains all required elements and sufficient detail to serve as a project record.
4.18 Project Schedules. The Contractor shall provide a complete milestone schedule that outlines project activities, including time-phased start and completion dates for the project and its associated sub-projects relating to the installation (CDRL A002). The Contractor shall establish a preliminary project schedule/plan and submit it with the technical proposal.
4.19 Cutover Plan. The Contractor shall provide a cutover plan clearly detailing how the transition will be implemented, how the upgraded premises wiring will connect to the base system or infrastructure, and how it will be placed into full service (CDRL A005). The Contractor shall coordinate and obtain approval for all planned cutovers with base POC.
4.20 Test Plan. The Contractor shall provide a test plan clearly detailing how the premises wiring upgrade will be pre-tested, in-progress tested, and post-tested (CDRL A005). The Contractor shall test the premises wiring upgrade to demonstrate to the Government that it is correctly installed, properly functioning, fully compliant with standards, and meet or exceed all performance parameters and specified requirements. These tests shall be completed prior to cutover and placement into service.
4.21 Testing Requirements. The Contractor shall provide all test equipment and personnel required to conduct testing and ensure compliance with the Aviano AB standards and the standards referenced in Appendix A, Applicable Documents and Standards. During any testing phase, the Government reserves the right to perform any of the inspections and tests conducted by the Contractor to ensure that solutions conform to the prescribed requirements. The Contractor shall provide on-site support during acceptance testing.
4.22 Test Report. The Contractor shall document and provide a test report of all results from the testing completed under the test plan to the base POC and 31 CS/SCXP (CDRL A006).
4.23 As-Built Drawings. The Contractor shall provide clear drawings showing the “as-built” condition in Visio and PDF formats (CDRL A001). The drawings shall depict the details of the entire premises wiring upgrade, including, but not limited to, equipment room locations, rack cabinets, drop locations, drop outlet numbers, rack elevation, pathways, labeling, cabling, wiring, cross-connections, patch panels, grounding, and other relevant details.
4.24 Final Acceptance/Project Completion. The final acceptance shall conclude upon the successful completion and receipt of all deliverables. The Contractor shall schedule a final project walkthrough with the base POC, Government CO, and 31 CS/SCXP at least five (5) calendar days prior to acceptance. The Government reserves the right to refuse final acceptance until all discrepancies and problems have been resolved to its satisfaction.
4.25 Deliverables. All deliverables are subject to Government acceptance and approval. They shall meet the professional standards and requirements set forth in this SOO. All deliverables shall be produced using software tools and versions recommended and accepted by the Government. The Contractor shall submit the following deliverables:
Table 1. Contract Data Requirement List (CDRL)
| CDRL | Data Item Title |
| Data Item Title |
| A001 |
| As Built |
| DI-DRPR-80151A/T |
| A002 |
| Work Schedule |
| DI-MISC-81382/T |
| A003 |
| Status Report |
| DI-MGMT-80368A |
| A004 |
| Meeting Minutes |
| DI-ADMIN-81505/T |
| A005 |
| Cutover and Test Plan |
| DI-NDTI-80566A/T |
| A006 |
| Test Report |
| DI-QCIC-80512 |
5. GOVERNMENT-FURNISHED PROPERTY, EQUIPMENT, AND SERVICES. The Contractor shall coordinate with the base POC to identify and ensure that all necessary support is provided by the Government prior to implementation. The Government shall support and provide the following for the premises wiring upgrade, including, but not limited to:
· Provide the B110, 2nd floor, floor plan layout
APPENDIX A. APPLICABLE DOCUMENTS AND STANDARDS
The Contractor shall comply with all military and commercial standards where applicable. Other commercial standards may apply to individual projects and will be specified in the respective task orders. In the event of a conflict between a commercial document and a Federal or Military Standard, the Federal or Military Standard shall take precedence. It is the Contractor's responsibility to identify and obtain the applicable standards proposed for the project in the SOO.
The following tables are not all-inclusive lists of standards. The Contractor shall obtain and comply with any other applicable manuals not identified in these tables that are required to meet industry standards.
Table A-1. Federal Government Standards
| NUMBER |
| TITLE |
| WEBSITE OR LOCATION |
| OSHA |
| Occupational Safety and Health Administration (OSHA) |
| http://www.osha.gov |
| OSHA CFR 29 Part 1910-268 - (1988) |
| Telecommunications |
| EPA |
| Environmental Protection Agency (EPA) |
| http://www.epa.gov/ |
| EPA |
| EPA Rules, Regulations, and Legislation |
| ABA/ADA |
| Architectural Barriers/Americans with Disabilities Acts |
| DODD 5220.22 |
| DOD Industrial Security Program Directive |
| DOD JTA ver. 4 |
| Department of Defense Joint Technical Architecture |
| AFI 31-101 |
| The Air Force Installation Security Plan |
Table A-2. Military Standards
| NUMBER |
| TITLE |
| MIL-STD-188-154A |
| Subsystem, Equipment, and Interface Standards for Common Long Haul and Tactical Telecommunications Control Facilities |
| MIL-STD-188-124B |
| Grounding, Bonding and Shielding for Common Long Haul/Tactical Communications Systems |
MIL-HDBK 419A,
Vol. I and II Grounding, Bonding, and Shielding for Electronic Equipment and Facilities
| MIL-HDBK-232A |
| Red/Black Engineering Installation Guidelines |
| MIL-HDBK-411B |
| Power and the Environment for Sensitive DoD Electronic Equipment |
| AFI 32-1065 |
| Grounding Bonding and Shielding for Electronic Equipment and Facilities |
| AFI 91-203 |
| Air Force Consolidated Occupational Safety Instruction |
| MIL-HDBK-1857 |
| Grounding, Bonding and Shielding Design Practices |
| MIL-HDBK-454B |
| General Guidelines for Electronics Equipment |
| UFC 3-580-01 |
| Telecommunications Interior Infrastructure Planning and Design |
| Local Standards |
| Aviano AB Construction Standards |
(Copies of the above documents may be obtained from the Naval Publications and Forms Center (NPFC 105), 5801 Tabor Ave, Philadelphia PA 19120.)
SOO - Premises Wiring Upgrade, Building 110, 2nd Floor at Aviano AB A-1
Table A-3. Commercial Standards and Manuals
| NUMBER |
| TITLE |
| WEBSITE OR LOCATION |
BICSI TDM
Manual
| Building Industry Consulting Service International, Inc. (BICSI) Telecommunications Distribution Methods (TDM) Manual |
| http://www.bicsi.org/ |
| NFPA 70 |
| National Fire Protection Association (NFPA) |
National Electric Code (NEC) http://www.nfpa.org/
| NFPA 72 |
| National Fire Alarm Code |
| EIA/ECA-310-E |
| Racks, Panels and Associated Equipment |
| http://www.eia.org/ http://www.tiaonline.org/ |
| TIA-526-7 |
| Measurement of Optical Power Loss of Installed |
Single-mode Fiber Cable Plant
| TIA-526-14-B |
| Optical Power Loss Measurement of Installed Multimode Fiber Cable Plant |
| ANSI/TIA 568.0-D |
| Generic Telecommunications Cabling for Customer Premises |
| ANSI/TIA-568.1-D |
| Commercial Building Telecommunications Cabling Standard |
| ANSI/TIA-568.2-D |
| Balanced Twisted-Pair Telecommunications Cabling and Components Standard |
| ANSI/TIA-568.3-D |
| Optical Fiber Cabling Components Standard |
| ANSI/TIA 569-E |
| Telecommunications Pathways and Spaces Standard |
| TIA-570-C |
| Residential Telecommunications Infrastructure Standard |
| TIA-598-C |
| Optical Fiber Cable Color Coding |
| ANSI/TIA-606-C |
| Administration/Labelling Standards for the Telecommunications Infrastructure of Commercial |
| TIA/EIA-607-D |
| Generic Telecommunications Grounding and |
Bonding (Earthing) for Customer Premises
| TIA-758-A |
| Customer-owned Outside Plant Telecommunications Infrastructure |
| ANSI/TIA-862-C |
| Structured Cabling Infrastructure Standard for Intelligent Building System |
| ANSI/TIA-942-B |
| Telecommunications Infrastructure Standard for |
Data Centers
ANSI/NECA/BICSI
-002 Data Center Design and Implementation Best Practices
| RUS Bulletin 1751F-801 |
| Electrical Protection Fundamentals |
RUS Bulletin
1753F-201 (PC-4)
RUS Standard for Acceptance Tests and Measurements of Telecommunications Plant
| RUS Bulletin 1753F-207 (PE- |
| REA Specification for Terminating Cables |
| TIA-604 Series |
| Fiber Optic Connector Intermateability Standard |
(FOCIS)
APPENDIX B. LABELING STANDARDS
B.1 LAN Faceplate Labeling.
B.1.1 Two Position UTP Wall Plate.
ROOM Actual room number from the facility drawings at time of design.
TELECOM ROOM (TR) Actual TR or Equipment Room where the end of the wall plate cables terminate. In existing facilities with no TR numbers, the TR room identifier shall be floor number, room number where room number starts with the letter A with additional TR labeled B, C etc.
| RACK # | Actual Rack number that contains the patch panel where the cable terminates. PATCH PANEL # | Actual patch panel number. |
| PORT #’s | Actual port numbers in the patch panel. |
The bottom position of the UTP wall plate shall be marked with the Room Number that the wall plate is installed. This information is reflected in the site cable plan.
Top Position Example:
110-1-1-1, 2
TR 110
Rack # 1 Patch Panel # 1 Port #’s 1, 2 (On the patch panel)
Bottom Position Example:
32 = Room Number (Actual room # from the cable plan and facility drawings at time of design)
Top Position Example: (no comm. room identifier) 1A-1-1-1, 2 = TR 1A, Rack # 1, Patch Panel # 1, Port #’s 1, 2 (On the patch panel)
B-1
Figure B-1. Two-Position Wall Plate Numbering Scheme
B.2 Patch Panel Labeling Patch panel shall be labeled using the following format. Room number (actual room where user wall plate is located), face plate number, jack designator, 110-1 A B C D.
Figure B-2. Patch Panel Numbering Scheme
B.3 Fiber Marking.
B.3.1 Fiber Optic Distribution Panel (FODP)/Fiber Optic Patch Panel (FOPP) Marker.
All new FODPs or FOPPs shall be marked to identify those that terminate fibers, using the following formats:
Inter-building fiber backbone:
FOPP [Building #] (or FODP [Building #]) FO [Route: Source Building# - Destination Building#], [Strand Count] [Fiber Type] Intra-building fiber backbone:
TIE FOPP [Room #] TIE FO [Route: Source Room# - Destination Room#], [Strand Count] [Fiber Type] Example:
FOPP B395
FO B395 - B1203, 1-12 SM TIE FOPP R100
TIE FO R100 – R122, 1-12 SM
B.3.2 Fiber Cable Marker Tag.
All fiber cables shall be tagged and marked to identify their size, type, cable number, and strand count, using the following format:
Example:
12L8.3F
FO B395 – B1203, 1-12 SM
First line: “12” stands for Fiber Count. “L” stands for Loose Tube Buffer or (“T”) for Tight Tube Buffer. “8.3” stands for Single Mode. “F” stands for Filled Core (otherwise leave blank).
ATTACHMENT A. LAYOUT DRAWINGS
Figure ATT-1. B110, 2nd Floor Premises Wiring Upgrade with Drop Location Layout
ATT-1
Figure ATT-2. Existing Rack Cabinet to Be Reused in B110, 2nd Floor Equipment Room
ATT-2
Figure ATT-3. Proposed Equipment Locations in Existing Rack Cabinet image76.png image77.png image78.png image79.png image80.png image81.png image82.png image83.png image84.png image85.png image86.png image87.png image88.png image89.png image90.png image91.png image92.png image93.png image94.png image95.png image96.png image97.png image98.jpeg image99.jpeg image100.png image1.png image2.png image3.png image4.png image5.png image6.png image7.png image8.png image9.png image10.png image11.png image12.png image13.png image14.png image15.png image16.png image17.png image18.png image19.png image20.png image21.png image22.png image23.png image24.png image25.png image26.png image27.png image28.png image29.png image30.png image31.png image32.png image33.png image34.png image35.png image36.png image37.png image38.png image39.png image40.png image41.png image42.png image43.png image44.png image45.png image46.png image47.png image48.png image49.png image50.png image51.png image52.png image53.png image54.png image55.png image56.png image57.png image58.png image59.png image60.png image61.png image62.png image63.png image64.png image65.png image66.png image67.png image68.png image69.png image70.png image71.png image72.png image73.png image74.png image75.png