ASHE 19-1048
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| SUSTAIN HVAC WATER FILTER MULTI | ||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| ASHE 19-1048 | AVIANO AIR BASE, ITALY | |||||||||
| MATERIAL COSTS | LABOR COSTS | |||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) |
| A. | SUSTAIN WORKS / Lavori di Manutenzione Evolutiva | ||||||||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni | |||||||||||
| Id Mechanical Demolitions - Id Demolizioni Meccaniche | 0.00 | 0.00 | 0.00 | ||||||||
| 1 | CUTTING AND REMOVAL PARTIALLY EXISTING CHILLED AND HOT WATER LINEAS AND CHEMICAL POT FEEDERS. | ||||||||||
| Taglio e rimozione parziale di tubazioni esistenti e dei dosatori esistenti. | IT. No. Art. n. | 1 | EA/NO | 55.00 | 0.00 | 0.00 | 0.00 | 0.00 | |||
| Total Mechanical Demolitions - Totale Demolizioni Meccaniche | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
TOTAL PART I / Totale Parte I 0.00 0.00 0.00 0.00
| PART III - MECHANICAL WORK / Parte III - Lavori Meccanici | |||||||
| IIIa HVAC - IIIa HVAC | |||||||
| 2 | SUPPLY AND INSTALLATION OF CB-THERMOCYCLON 25-N | ||||||
| Fornitura ed installazione di CB-THERMOCYCLON 25-N | IT. No. Art. n. | 1 | EA/NO | 27.00 | 0.00 | 0.00 | 0.00 |
| 3 | SUPPLY AND INSTALLATION OF CB-THERMOCYCLON 50-N | ||||||
| Fornitura ed installazione di CB-THERMOCYCLON 50-N | IT. No. Art. n. | 2 | EA/NO | 28.00 | 0.00 | 0.00 | 0.00 |
| 4 | SUPPLY AND INSTALLATION OF CILLIT-MAXITHERMOCYCLON | ||||||
| Fornitura ed installazione di CILLIT-MAXITHERMOCYCLON | IT. No. Art. n. | 3 | EA/NO | 7.00 | 0.00 | 0.00 | 0.00 |
| Total HVAC - Totale HVAC |
TOTAL PART III / Totale Parte III
| PART IV - ELECTRICAL WORK / Parte IV - Lavori Elettrici | ||||||
| 5 | SUPPLY AND INSTALLATION OF NEW ELECTRICAL FEEDING LINE. | |||||
| Fornitura e posa in opera di nuovi collegamenti elettrici. | IT. No. Art. n. | 1 | EA/NO | 35.00 | 0.00 | 0.00 |
| Total electrical - Totale Elettrico |
TOTAL PART IV / Totale Parte IV
| SUSTAIN WORKS SUMMARY / Riepilogo Lavori di Manutenzione Evolutiva |
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS |
| PART III - MECHANICAL WORK |
| PART IV - ELECTRICAL WORK |
| TOTAL PRICE / Costo Totale |
OR US DOLLARS (RATE 1$ = 0,8582€)
| Total Summary / Riepilogo Complessivo | |
| A. | SUSTAIN WORKS / Lavori di Manutenzione Evolutiva |
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS | |
| PART III - MECHANICAL WORK | |
| PART IV - ELECTRICAL WORK | |
| SUB TOTAL A / Subtotale A |
TOTAL PRICE / Costo Totale