F1F3A28206A001 ASHP 18-1102

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

-change the period of project performance, -incorporate addendum #1 to the technical specif ications and -extend the closing date for receipt of offers, as indicated in the below Summary of Changes.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 06-Sep-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA568218R0052

X 9B. DATED (SEE ITEM 11)

22-Aug-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Sep-2018

CODE

31 CONS LGC - FA5682

VIA PORDENONE 89/B, AREA "E" EDIF. 600

BASE AEREA DI AVIANO

AVIANO (PN) 33081

FA5682 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

FA568218R0052

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 06-Sep-2018 04:00 PM to 10-Sep-2018 04:00 PM.

The offeror acceptance period has decreased by 4 from 24 to 20.

The contractor period of performance end date has increased by 15 days from 45 days to 60 days.

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0001

The CLIN extended description has changed from:

THE CONTRACTOR SHALL FURNISH ALL LABOR, EQUIPMENT, MATERIALS, TRANSPORTATION,

SUPERVISION AND ANY OTHER NECESSARY WORK TO ACCOMPLISH THE PROJECT HEREIN

LISTED AT THE PRICE STATED BELOW AND STRICTLY IN ACCORDANCE WITH THE TERMS AND

CONDITIONS OF THIS CONTRACT INCLUDING THE FOLLOWING ATTACHED DOCUMENTS LISTED

IN SECTION J HEREIN: TECHNICAL SPECIFICATIONS FOR PROJECT ASHE 18-1102 SUSTAIN

ASPHALT PAVEMENT AREA G, AVIANO AB, ITALY, DATED JUL 2018- 38 WRITTEN PAGES

INCLUDING COVER PAGE AND ATTACHMENTSC. ADDITIONAL REQUIREMENTS DATED AUG 2018 -

3 WRITTEN PAGES

To:

THE CONTRACTOR SHALL FURNISH ALL LABOR, EQUIPMENT, MATERIALS, TRANSPORTATION,

SUPERVISION AND ANY OTHER NECESSARY WORK TO ACCOMPLISH THE PROJECT HEREIN

LISTED AT THE PRICE STATED BELOW AND STRICTLY IN ACCORDANCE WITH THE TERMS AND

CONDITIONS OF THIS CONTRACT INCLUDING THE FOLLOWING ATTACHED DOCUMENTS LISTED

IN SECTION J HEREIN: TECHNICAL SPECIFICATIONS FOR PROJECT ASHE 18-1102 SUSTAIN

ASPHALT PAVEMENT AREA G, AVIANO AB, ITALY, DATED JUL 2018 AND ADDENDUM #1 DATED

AUG 2018-41 WRITTEN PAGES INCLUDING COVER PAGE,ATTACHMENTS AND ADDENDUM #1C.

ADDITIONAL REQUIREMENTS DATED AUG 2018 - 3 WRITTEN PAGES

SECTION F - DELIVERIES OR PERFORMANCE

The following Delivery Schedule item for CLIN 0001 has been changed from:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

45 dys. ANP 1 31 CES ENGINEER - F1F3A2

UNIT 6110

APO AE 09601-6110

FOB: Destination

F1F3A2

To:

FA568218R0052

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

60 dys. ANP 1 31 CES ENGINEER - F1F3A2

UNIT 6110

APO AE 09601-6110

FOB: Destination

F1F3A2

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 30 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause)

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The following have been modified:

LIST OF ATTACHMENTS – CONSTRUCTION CONTRACTS

The following documents are attachments to this document and are an integral part hereof:

a. Attachment 1:

Technical Specifications ASHP 18-1102 Sustain Asphalt Pavements Area G, Aviano AB, Italy dated Jul 2018

- 41 pages including cover page, Attachments and Addendum #1 dated Aug 2018

b. Attachment 2:

Additional Requirements, dated May 2018, 3 pages

(End of Summary of Changes)