Solicitation_Q&A.docx
DOCX document 13 KB Posted
- Attached to
- Power Converters Federal contract opportunity
- Solicitation number
- FA568218Q5058
About this file
Solicitation Q&A
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA568218Q5058-_Power_Converters.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Can you clarifiy the input requirement? Ex. 208V, 230V, 460V A: The building is 208v 50Hz.
2. Do you need any output cables?
A: Units should be wired into the building (2 via underground, 1 through building) and have sockets installed.
3. Are these base Mounted or do you need them to be mobile?
A: Two will need to be placed on a cement pad away from the building and the 3rd will go into a maintenance room in the building.
4. Do you require a technician to perform on site start up and training as part of the requirement?
A: This is preferred.
5. What is th required input Frequency in Hz?
A: 50Hz
6. Output voltage: 115 Line to line or Line to neutral?
A: Neutral