Project # ASJJ 15-1058 Addendum#1

DATE: 21 JUL 2016

31CES/CENM 1

ADDENDUM #1

ASJJ 15-1058-Sustain Electrical Substation Fac. 420

AREA C, AVIANO AB, AVIANO (PN) ITALY

A1.1. Change item 4.2.4 to read “Furnish and install new hot galvanized factory painted steel downspout, thickness 8/10 mm, diameter as existing color chosen by CO, the item includes:

A1.1.1 Modification of one downspout from inside the wall to outside with insert of two curves including the hole closure;

A1.1.2 Furnishing and installation of downspout end diffusers (piede d’anatra) on each downspout;

A1.1.3 the furnishing and the installation of cast iron ends 1.00 m high on each downspout end A1.1.4 all the loose parts, consuming materials, wall supports, load, transportation and disposal of any wasted material in an appropriated dump and any other burden to provide a job performed in work-man-like manner.

LM 25

A1.2. Change item 4.2.14 to read: “Window for restroom. The item consists of supply and installation of anodized aluminum half height single leaf turn and tilt and half height fixed (not operable), color to be determined by Contracting Officer fixed, thickness 60 mm with thermal cut, glass 6+12+6 frosted “isolvetro” on the external side, camera with argon and PLANIBEL ENERGY© laminated and on the internal side; the item includes the zinc coated frame, all necessary gaskets and the hardware to be fixed with expandable gaskets and not with foam on the wall

SM 1.70

A1.3. Change item 4.2.15 to read: “Office window. The item consists of supply and installation of anodized aluminum, color to be determined by Contracting Officer half height double leaf opening turn and tilt (anta e ribalta), half height fixed, thickness 60 mm with thermal cut, glass 6+12+6 “isolvetro” on the external side, camera with argon and PLANIBEL ENERGY© laminated on the internal side; the item includes the zinc coated frame, all necessary gaskets and the hardware to be fixed with expandable gaskets and not with foam on the wall.

SM 2.10

A1.4. Change item 4.2.18 to read: “Heat pump split unit air conditioner. The item consists of furnishing and installing an air conditioner 9000 BTU heat pump, class A++, split with external unit, remote control, Italy official three years warranty EUROVENT class “A” certification, the item includes all necessary masonry work to install it including coring, drills to install the supports and the necessary supports and necessary restorations; furthermore the item includes electrical connections and all the as built drawings, manuals, required training for use and maintenance, transport and disposal of proven materials, cleaning of the areas and any other burden to have a job performed in work-man-like manner.

LS

A1.5. Change item 4.2.23 to read: “Furnishing and installation of temporary backup generators for both Area C and Area D:

Project # ASJJ 15-1058 Addendum#1

DATE: 21 JUL 2016

31CES/CENM 2

A1.5.1 Rental of 240kW backup generator together with 4900 lt fuel tank, at least 21 days of fuel consistent with the daily consumption of the equipment to support area C;

A1.5.2 Rental of 16kW backup generator together with 920 lt fuel tank, at least 21 days of fuel consistent with the daily consumption of the equipment to support Area D, to be installed in area D;

A1.5.3 Fuel tank and portable backup generator shall be provided with a spill containment function;

A1.5.4 Contractor will coordinate with ENEL the electricity interruption and re-connection of the ENEL feeding ;

A1.5.5 Contractor shall follow required procedure for power outage (with CE support) 45days;

A1.5.6 Temporary connection of the portable backup generators to MDP of Area C and Area D;

A1.5.7 24/7 assistance fast response assistance for any trouble it may occur on the temporary backup connection and equipment;

A1.5.8 Restore of the existing connection of the MDP at Area C and Area D.

LS

cristina.Moro Typewritten Text cristina.Moro Typewritten Text