new cnstr.

COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
ASHE 13-1022 RPR PASs ELEC SYS AT ZULU LOOP, B. 7930, 7970, 7990, 8030
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
ASHE 13-1022B. 7930, 7970, 7990, 8030, AREA F, AVIANO AIR BASE, ITALY
MATERIAL COSTSLABOR COSTS
LINE NO.ITEMUNIT OF MEASUREQUANTITYUNITTOTALMANHOURS MANDAYSAVERAGE RATETOTALOTHER DIRECT COSTSLINE TOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
A.NEW CONSTRUCTION / Nuova Costruzione
PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni
Ia Architectural Work - Ia Lavori Architettonici
NOT APPLICABLE Non Applicabile
Total Architectural Work - Totale Lavori Architettonici0.000.000.000.00
Ib Structural Work - Ib Lavori Strutturali0.000.000.00
NOT APPLICABLE Non Applicabile
Total Structural Work - Totale Lavori Strutturali0.000.000.00
0.000.000.00
Ic Civil Work - Ic Lavori Civili0.000.000.00
NOT APPLICABLE Non Applicabile
Total Civil Work - Totale Lavori Civili0.000.000.00
Id Mechanical Work - Ic Lavori Meccanici
NOT APPLICABLE Non Applicabile
Total Mechanical Work - Totale Lavori Meccanici0.000.000.00
Ie Electrical Work - Ic Lavori Elettrici
NOT APPLICABLE Non Applicabile
Total Mechanical Work - Totale Lavori Meccanici0.000.000.00
TOTAL PART I - Totale Parte I0.000.000.000.000.00
PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili
NOT APPLICABLE Non Applicabile
0.000.000.00
Total Architectural Work - Totale Lavori Architettonici0.000.000.000.00
IIb Structural Work - IIb Lavori Strutturali0.000.000.00
NOT APPLICABLE Non Applicabile
Total Structural Work - Totale Lavori Strutturali0.000.000.000.00
IIc Civil Work - IIc Lavori Civili0.000.000.00
NOT APPLICABLE Non Applicabile
Total Civil Work - Totale Lavori Civili0.000.000.000.00
TOTAL PART II / Totale Parte II0.000.000.000.00
PART III - MECHANICAL WORK / Parte III - Lavori Meccanici
IIIa HVAC System - IIIa Impianto di Condizionamento
NOT APPLICABLE Non Applicabile
Total HVAC Systems - Totale Impianti HVAC0.000.000.000.00
PART IIIb - COMPRESSED AIR AND SPRINKLER SYSTEMS / PARTE IIIa - Impiant di aria compressa e sprinkler
NOT APPLICABLE Non Applicabile
Total Compressed air and sprinkler Systems - Totale Impianti di aria compressa e sprinkler0.000.000.000.00
TOTAL PART III / Totale Parte III0.000.000.000.00
PART IV- ELECTRICAL WORK / Parte IV - Lavori Elettrici0.000.00
NOT APPLICABLE Non Applicabile
TOTAL PART IV / Totale Parte IV0.000.000.000.00
PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS€ 0.00€ 0.00€ 0.00€ 0.00
PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK€ 0.00€ 0.00€ 0.00€ 0.00
PART III - MECHANICAL WORK€ 0.00€ 0.00€ 0.00€ 0.00
PART IV - ELECTRICAL WORK€ 0.00€ 0.00€ 0.00€ 0.00
TOTAL PRICE / Costo Totale€ 0.00€ 0.00€ 0.00€ 0.00
$0.00$0.00$0.00$0.00

&RSheet &P of &N repair

COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
ASHE 13-1022 RPR PASs ELEC SYS AT ZULU LOOP, B. 7930, 7970, 7990, 8030
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
ASHE 13-1022B. 7930, 7970, 7990, 8030, AREA F, AVIANO AIR BASE, ITALY
MATERIAL COSTSLABOR COSTS
LINE NO.ITEMUNIT OF MEASUREQUANTITYUNITTOTALMANHOURS MANDAYSAVERAGE RATETOTALOTHER DIRECT COSTSLINE TOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
B.REPAIR WORK / Lavori di Ristrutturazione
PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni
Ia Architectural Work - Ia Lavori Architettonici
1ASBESTOS REMOVAL. COMPLETE OF DUMP FEE

BLDG 7930, 7970, 7990, 8030

Rimozione amianto. Competo di oneri discarica.

Edifici 7930, 7970, 7990, 8030IT. No. Art. n.1LS/AC1.00
Total Architectural Work - Totale Lavori Architettonici
Ib Structural Work - Ib Lavori Strutturali
2PERFORATION METAL AND CONCRETE WALLS

BLDG 7930, 7970, 7990, 8030

Esecuzione di carrotaggi su pareti in metallo e calcestruzzo

Edifici 7930, 7970, 7990, 8030IT. No. Art. n.1LS/AC1.00
Total Structural Work - Totale Lavori Strutturali
Ic Civil Work - Ic Lavori Civili
3Not Applicable

Non applicabile

Total Civil Work - Totale Lavori Civili
Id Mechanical Work- Id Lavori Meccanici
4Not Applicable

Non applicabile

Total Mechanical Work - Totale Lavori Meccanici
Ie Electrical Work - Ie Lavori Elettrici
5REMOVAL OF EXISTING ELECTRICAL AND COMMUNICATION SYSTEM. COMPLETE OF PUBBLIC DUMP FEE.

BLDG 7930, 7970, 7990, 8030

Rimozione dell'impianto elettrico e dati esistente. Completo di oneri pubblica discarica.

Edifici 7930, 7970, 7990, 8030IT. No. Art. n.1LS/AC1.00
Total Electrical Work - Totale Lavori Elettrici
TOTAL PART I / Totale Parte I
PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili
IIa Architectural Work - IIa Lavori Architettonici
6Not Applicable

Non applicabile

Total Architectural Work - Totale Lavori Architettonici
IIb Structural Work - IIb Lavori Strutturali
7Not Applicable

Non applicabile

Total StructuralL Work - Totale Lavori Strutturali
IIc Civil Work - IIc Lavori Civili
8INSTALL DOOR SEALS

BLDG 7930, 7970, 7990, 8030

Installare nuove guarnizioni porta

Edifici 7930, 7970, 7990, 8030IT. No. Art. n.1LS/AC1.00
9SAND FLOOR SURFACE AND VACUUM
Pulizia meccanica delle superfici da trattare con resinaIT. No. Art. n.2am21,852.00
10PRIMER
Fornitura e posa di primerIT. No. Art. n.2bm21,852.00
11THREE-COMPONENT "CONTRO SPINTA"
Fornitura e posa di strato resina epossidica tri-componenteIT. No. Art. n.2cm21,852.00
12FIRST COAT OF RESIN AND ANTI-SKID CORUNDUM
Fornitura e posa di primo strato di trattamento della resinaIT. No. Art. n.2dm21,852.00
13SECOND COAT OF EPOXY RESIN
Fornitura e posa di secondo strato di trattamento della resinaIT. No. Art. n.2em21,852.00
14ANTI-SCRATCH OPAQUE FINISHING WITH CORUNDUM
Fornitura e posa di strato finale di trattamente della resinaIT. No. Art. n.2fm21,852.00
15ELASTIC JOINT SEAL
Fornitura e posa di giunto elestico di tenutaIT. No. Art. n.2gm640.00
16COLORED STRIPING AND MARKING

BLDG 7930, 7970, 7990, 8030

Colorazione e marcatura delle superfici

Edifici 7930, 7970, 7990, 8030IT. No. Art. n.2hLS/AC1.00
Total Civil Work - Totale Lavori Civili
TOTAL PART II / Totale Parte II
PART III - MECHANICAL WORK / Parte III - Lavori Meccanici
PART IIIa - HVAC SYSTEMS / Parte IIIa - Impianti HVAC
17GALVANIZED SHEET METAL DUCT D.630mm, COMPLETE BY SUCTION GRIDS, DUCT SUPPORTS AND ACCESSORIES
Canali in lamiera zincata D.630mm, completo di bocchette, staffaggi ed accessoriIT. No. Art. n.1am80.00
18EXHAUST AIR MOTOR - EXPLOSION PROOF
Aspiratore antideflagrante - CE ATEX Zona 1IT. No. Art. n.2EA/NO4.00
19EXPULSION GRID
Griglia di espulsione ariaIT. No. Art. n.3aEA/NO4.00
20FINAL TEST MECHANICAL SYSTEM. SUBMITTAL MECHANICAL WORK CERTIFICATIONS.

BLDG 7930, 7970, 7990, 8030

Verifica impianto meccanico. Sottomissione delle dichiarazioni di conformità DM 37/08.

Edifici 7930, 7970, 7990, 8030IT. No. Art. n.4LS/AC1.00
Total HVAC Systems - Totale Impianti HVAC
PART IIIb - PLUMBING - COMPRESSED AIR - SPRINKLER SYSTEMS / PARTE IIIa - Impianti Idrico-sanitario - aria compressa - sprinkler
21Not Applicable

Non applicabile

Total Plumbing - Compressed air - Sprinkler Systems - Totale Impianti Idrico-Sanitario - Aria compressa - Sprinkler
TOTAL PART III / Totale Parte III
PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici
22NEW MAIN BREAKER 4x160A IN THE EXISTING SUBSTATION BLDG #78030
Installazione nuovo int. 4x160A all'interno della cabina elettrica esistente n.78030IT. No. Art. n.1aEA/NO3.00
23EXTENSION ELECTRICAL PANEL QBT INSEDE BUILDING # 78030. NEW PORTION STRUCTURE.
Ampliamento quadro elettrico esistente QBT all'interno dell'edificio n.78030. Nuova anta quadro.IT. No. Art. n.1bLS/AC1.00
24EXISTING "MDP " ELECTRICAL PANEL - (ELECTRICAL CHANGE AND ADJUST)- BUILDINGS #7930
Quadro elettrico esistente "MDP" (modifiche elettriche ed adeguamento) - EDIFICIO N.7930IT. No. Art. n.2LS/AC1.00
25"MDP" ELECTRICAL PANEL - EXPLOSION PROOF -BUILDING #7970, 7990, 8030
Quadro elettrico "MDP" tipo ATEX - EDIFICIO N.7970, 7990, 8030IT. No. Art. n.3aEA/NO3.00
26"GEN" ELECTRICAL PANEL
Quadro elettrico "GEN"IT. No. Art. n.3bEA/NO4.00
27MAIN PANEL FEEDER LINE FG7R-3x185+185N+185PENmmq
Linea di alimentazione generale FG7R-3x185+185N+185PEN mmqIT. No.4m780.00
28ELECTRICAL CABLE FG7R 1x50mmq
Cavo elettrico FG7R 1x50mmqIT. No. Art. n.5am500.00
29ELECTRICAL CABLE FG7OR 3G2,5mmq
Cavo elettrico FG7OR 3G2,5mmqIT. No. Art. n.5bm660.00
30ELECTRICAL CABLE FG7OR 3G4mmq
Cavo elettrico FG7OR 3G4mmqIT. No. Art. n.5cm1,900.00
31ELECTRICAL CABLE FG7OR 3G6mmq
Cavo elettrico FG7OR 3G6mmqIT. No. Art. n.5dm80.00
32ELECTRICAL CABLE FG7OR 3G10mmq
Cavo elettrico FG7OR 3G10mmqIT. No. Art. n.5em180.00
33ELECTRICAL CABLE FG7OR 5G6mmq
Cavo elettrico FG7OR 5G6mmqIT. No. Art. n.5fm280.00
34ELECTRICAL CABLE FG7OR 4G10mmq
Cavo elettrico FG7OR 4G10mmqIT. No. Art. n.5gm360.00
35ELECTRICAL CABLE FG7OR 7G1,5mmq
Cavo elettrico FG7OR 7G1,5mmqIT. No. Art. n.5hm20.00
36ELECTRICAL CABLE FG7OR 10G1,5mmq
Cavo elettrico FG7OR 10G1,5mmqIT. No. Art. n.5im80.00
37ELECTRICAL CABLE FG7R 1x150mmq
Cavo elettrico FG7R 1x150mmqIT. No. Art. n.5lm40.00
38EXCAVATION FOR NEW CONDUITS
Scavo per nuove tubazioni interrateIT. No. Art. n.6m3340.00
39EXCAVATION BY PIPE PERCUSSION
Scavo per nuove tubazioni interrateIT. No. Art. n.7m100.00
40SUPPLY AND INSTALLATION AT SIGHT, OR DIGGING WITHIN WELLS, CONDUITS OF HIGH-DENSITY POLYETHYLENE "HDPE DIAM. 160
Fornitura e posa in opera a vista, entro cavedi o scavo, di cavidotti in polietilene alta densità "PEHD DIAM. 160IT. No.8m1,900.00
41PRECAST REINFORCED CONCRETE MANHOLES WITH MANHOLE DRIVEWAY VIBRATED BY 100X100X150x10cm.
Pozzetti prefabbricati in CLS armato vibrato con chiusino carrabile da 100x100x150x10cm (dimensioni interne)IT. No.9aEA/NO11.00
42PRECAST REINFORCED CONCRETE MANHOLES WITH MANHOLE DRIVEWAY VIBRATED BY 40X40X40X5cm, COMPLETE BY COPPER EARTH ROD 1,5m AND INFORMATION GROUNDING SYSTEM.
Pozzetti prefabbricati in CLS armato vibrato con chiusino carrabile da 40x40x40x5cm, completo di picchetto in rame 1,5m e cartello di terra.IT. No.9bEA/NO28.00
43BURRIED GROUND CABLE - 95mmq COPPER
Corda di rame nuda 95mmq interrataIT. No. Art. n.10m600.00
44HOT GALVANISED STEEL STRIP - 40x4mm
Barra di terra in acciaio zincato - 40x4mmIT. No. Art. n.11m360.00
45GALVANIZED STEEL ROUND WIRE - D.8mm
Tondino in acciaio zinacato - D.8mmIT. No. Art. n.12m200.00
46GROUND DISCONNECT
Sezionatore di terraIT. No. Art. n.13EA/NO32.00
47PICKING-UP ROD H=2,5m
Asta di captazione H=2,5mIT. No. Art. n.14EA/NO16.00
48C16/20 LEAN CONCRETE
Calcestruzzo C16/20IT. No. Art. n.15m3130.00
49SAND
SabbiaIT. No. Art. n.16m355.00
50FURNISH AND INSTALL OF GALVANIZED STEEL PIPE (UNI 7683) - 1/2 INCH DIAMETER
Fornitura e posa in opera di tubo in acciaio zinacato (UNI 7683) - diametro 1/2 polliceIT. No.17am200.00
51FURNISH AND INSTALL OF GALVANIZED STEEL PIPE (UNI 7683) - 3/4 INCH DIAMETER
Fornitura e posa in opera di tubo in acciaio zinacato (UNI 7683) - diametro 3/4 polliceIT. No.17bm1,850.00
52FURNISH AND INSTALL OF GALVANIZED STEEL PIPE (UNI 7683) - 1 INCH DIAMETER
Fornitura e posa in opera di tubo in acciaio zinacato (UNI 7683) - diametro 1 polliceIT. No.17cm900.00
53FURNISH AND INSTALL OF GALVANIZED STEEL PIPE (UNI 7683) - 2 INCH DIAMETER
Fornitura e posa in opera di tubo in acciaio zinacato (UNI 7683) - diametro 2 pollicIIT. No.17dm100.00
54FURNISH AND INSTALL OF GALVANIZED STEEL PIPE (UNI 7683) - 4 INCH DIAMETER
Fornitura e posa in opera di tubo in acciaio zinacato (UNI 7683) - diametro 4 pollicIIT. No.17em15.00
55180W IP66 LIGHTING FIXTURE LED TYPE - EXPLOSION PROOF II2GD Ex de IIC T5
Corpo illuminante LED IP66 180W - CE ATEX II2GD Ex de IIC T5IT. No.18aEA/NO72.00
561x36W IP65 LIGHTING FIXTURE FLUORESCENT TUBE TYPE - EXPLOSION PROOF II2GD Ex de IIC T5/T6 - EMERGENCY ONLY
Corpo illuminante 1x36W fluorescente IP65 - CE ATEX II2GD Ex de IIC T5/T6 - Solo emergenzaIT. No.18bEA/NO16.00
57EXTERNAL FLOOD LIGHT, LED TYPE - 92W - IP66
Proiettore asimmetrico industriale da esterno a LED - 92W - IP66IT. No.18cEA/NO12.00
582x31W LIGHTING FIXTURE LED TYPE - EXPLOSION PROOF II 2GD Ex d IIC T6
Corpo illuminante 1x36W fluorescente IP65 - CE ATEX II2GD Ex d IIC T6IT. No.18dEA/NO40.00
59PHOTOCELL SWITCH
Sensore crepuscolareIT. No.19EA/NO4.00
60INTERLOCKED OUTLET 2P+G 16A 230V - EXPLOSION PROOF II2GD Ex de IIC T5
Presa interbloccata 2P+G 16A 230V - CE ATEX II2GD Ex de IIC T5IT. No.20aEA/NO8.00
61INTERLOCKED OUTLET 3P+G 16A 400V - EXPLOSION PROOF II2GD Ex de IIC T5
Presa interbloccata 3P+G 16A 400V - CE ATEX II2GD Ex de IIC T5IT. No.20bEA/NO4.00
62INTERLOCKED OUTLET IP55 3P+N+G 125A 400V WITH CIRCUIT BREAKER - GENERATOR
Presa interbloccata IP55 3P+N+G 125A 400V con interruttore magnetotermico ed interblocco - GeneratoreIT. No.20cEA/NO4.00
63JUNCTION BOX FOR INSTALLATION OF FIRE ALARM EQUIPMENTS. EQUIPPED WITH CIRCUIT BREAKER - INSIDE DIMENSIONS 890x590x340mm - EXPLOSION PROOF II2GD Ex d IIB T5/T6
Custodia per apparati impianto rilevazione incendi, completo di interrruttori - dimmensioni interne 890x590x340mm - CE ATEX II2GD Ex d IIB T5/T6IT. No.21aEA/NO8.00
64JUNCTION BOX FOR INSTALLATION OF COMMUNICATION EQUIPMENTS. EQUIPPED WITH CIRCUIT BREAKER 16A (ON FRONT), TEMPERATURE PROBE AND DISPLAY (ON FRONT) TRAILING SOCKETS, N.3 CABLE GLANDS (ELECTRICAL SET UP), GROUND BAR - INSIDE DIMENSIONS 890x590x340mm - EXPLOSION PROOF II2GD Ex d IIB T5/T6
Custodia per apparati impianto dati. Completa di int. magnetotermico 16A su fronte custodia, sonda temperatura e display (quest'ultima su fronte custodia), ciabatta multipresa interna, 3 pressavavi per futuri punti di ingresso, barra di terra. - dimmensioni interne 890x590x340mm - CE ATEX II2GD Ex d IIB T5/T6IT. No.21bEA/NO12.00
65CONTROL STATION FOR CONTROL - DOUBLE UNIT: 4+4 PUSH BUTTON - EXPLOSION PROOF II2GD Ex d IIC T5/T6
Pulsantiera doppio corpo - 4+4 pulsanti - CE ATEX II2GD Ex d IIC T5/T6IT. No.22aEA/NO8.00
66CONTROL STATION FOR SIGNALING - SINGLE UNIT: 1 RED PILOT LIGHT - EXPLOSION PROOF II2GD Ex d IIC T5/T6
Spia di segnalazione - 1 spia colore rosso - CE ATEX II2GD Ex d IIC T5/T6IT. No.22bEA/NO4.00
67SEALING THE HOLES

BLDG 7930, 7970, 7990, 8030

Sigillare i fori o gli attraversamenti

Edifici 7930, 7970, 7990, 8030IT. No. Art. n.23LS/AC1.00
68VERIFY , RESTORE AND ADJUST THE EXISTING EQUIPOTENTIAL CONNECTIONS

BLDG 7930, 7970, 7990, 8030

Verificare, ripristinare e adeguare i collegamenti equipotenziali esistenti

Edifici 7930, 7970, 7990, 8030IT. No. Art. n.24LS/AC1.00
69REALIZE NEW EQUIPOTENZIAL CONNECTIONS

BLDG 7930, 7970, 7990, 8030

Realizzare nuovi collegamenti equipotenziali

Edifici 7930, 7970, 7990, 8030IT. No. Art. n.25LS/AC1.00
70RECONNECT EXISTING SYSTEMS OR DEVICES

BLDG 7930, 7970, 7990, 8030

Ricollegare gli impianti o le apparecchiature esistenti non rimosse

Edifici 7930, 7970, 7990, 8030IT. No. Art. n.26LS/AC1.00
71FINAL TEST ELECTRICAL SYSTEM. SUBMITTAL ELECTRICAL WORK CERTIFICATIONS.

BLDG 7930, 7970, 7990, 8030

Verifica impianto elettrico. Sottomissione delle dichiarazioni di conformità DM 37/08.

Edifici 7930, 7970, 7990, 8030IT. No. Art. n.27LS/AC1.00
72FURNISH AND INSTALL LOOP CABLE FOR FIRE ALARM SYSTEM - STANDARD EN 50200 - SECTION 2X1 SQ.MM.
Fornitura e posa in opera di cavo loop per allarme incendio EN 50200 - sezione 2x1 mmq.IT. No.28am1,000.00
73FURNISH AND INSTALL LOOP CABLE FOR FIRE ALARM SYSTEM - STANDARD EN 50200 - SECTION 2X1,5 SQ.MM.
Fornitura e posa in opera di cavo loop per allarme incendio EN 50200 - sezione 2x1,5 mmq.IT. No.28bm325.00
74FURNISH AND INSTALL OUTPUT MODULE
Fornitura e posa in opera di modulo ad 1 uscitaIT. No.29aEA/NO12.00
75FURNISH AND INSTALL INPUT MODULE
Fornitura e posa in opera di modulo ad 1 ingressoIT. No.29bEA/NO80.00
76FURNISH AND INSTALL CONVENTIONAL MANUAL CALL POINT - PUSH BUTTON - EXPLOSION PROOF II2GD Ex d IIB T6
Fornitura e posa in opera di pulsante antincendio completo di cartello monitore - CE ATEX II2GD Ex d IIB T6IT. No.29cEA/NO8.00
77FURNISH AND INSTALL RED FLASHING LIGHT - EXPLOSION PROOF II 2GD Ex d IIC T6
Fornitura e posa in opera lampeggiatore luminoso rosso - CE ATEX II 2GD Ex d IIC T6IT. No.29dEA/NO4.00
78FURNISH AND INSTALL SOUNDER - EXPLOSION PROOF II 2GD Ex d IIC T6
Fornitura e posa in opera avvisatore acustico - CE ATEX II 2GD Ex d IIC T6IT. No.29eEA/NO4.00
79FURNISH AND INSTALL TRIPLE IR FLAME DETECTOR - EXPLOSION PROOF Ex II 2GD
Fornitura e posa in opera di rivelatore di fiamma - CE ATEX Ex II 2GDIT. No.29fEA/NO8.00
80FURNISH AND INSTALL ADRESSABLE FIRE ALARM CONTROL PANEL. EQUIPPED WITH 2X12V / 17-18AH BATTERIES AND ACCESSORIES.
Fornitura e posa in opera di centrale allarme incendio. Equipaggaita con batterie 2x12V / 17-18Ah ed accessori.IT. No.29gEA/NO4.00
81SUPPLY AND INSTALLATION OF TRANSMITTER MONACO. COMPLETE WITH ANTENNA, cable, SPD, ECC.
Fornitura e posa in opera di trasmettitore MONACO. Completo di antenna, cavo, SPD, ecc.IT. No.29hEA/NO4.00
82FURNISH AND INSTALL JP8 FUEL GAS DETECTOR - EXPLOSION PROOF Ex-d IIC 2GD T6
Fornitura e posa in opera di rivelatore di gas JP8 - CE ATEX Ex-d IIC 2GD T6IT. No.29iEA/NO16.00
83TEST AND CERTIFICATION OF THE NEW FIRE ALARM SYSTEM.

BLDG 7930, 7970, 7990, 8030

Collaudo e certificazione del nuovo impianto allarme incendio.

Edifici 7930, 7970, 7990, 8030IT. No.30LS/AC1.00
844 COMMUNICATION OUTLET GROUP RJ45 - EXPLOSION PROOF II 3G Ex-nA II T6X - IP68
Gruppo 4 prese per telecomunicazioni RJ45 - CE ATEX II 3G Ex-nA II T6X - IP68IT. No.31EA/NO4.00
85COMMUNICATION CABLE CAT.6 UTP
cavo UTP cat.6, non schermatoIT. No.32am200.00
86TEST AND CERTIFICATION OF COMMUNICATION SYSTEM.

BLDG 7930, 7970, 7990, 8030

Collaudo e certificazione dell'impianto dati.

Edifici 7930, 7970, 7990, 8030IT. No.33LS/AC1.00
87RECONNECT EXISTING COMMUNICATION SYSTEMS OR DEVICES

BLDG 7930, 7970, 7990, 8030

Ricollegare l'impianto o le apparecchiature dati esistenti.

Edifici 7930, 7970, 7990, 8030IT. No. Art. n.34LS/AC1.00
TOTAL PART IV / Totale Parte IV
REPAIR WORK SUMMARY / Riepilogo Lavori di Ristrutturazione
PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS
PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK
PART III - MECHANICAL WORK
PART IV - ELECTRICAL WORK
TOTAL PRICE / Costo Totale

&RSheet &P of &N

Summary

COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
ASHE 13-1022 RPR PASs ELEC SYS AT ZULU LOOP, B. 7930, 7970, 7990, 8030
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
ASHE 13-1022B. 7930, 7970, 7990, 8030,

AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTSLABOR COSTS
LINE NO.ITEMUNIT OF MEASUREQUANTITYUNITTOTALMANHOURS MANDAYSAVERAGE RATETOTALOTHER DIRECT COSTSLINE TOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
A.NEW CONSTRUCTION / Nuova Costruzione
PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS
PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK
PART III - MECHANICAL WORK
PART IV - ELECTRICAL WORK
SUB TOTAL A.
B.REPAIR / Ristutturazione
PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS
PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK
PART III - MECHANICAL WORK
PART IV - ELECTRICAL WORK
SUB TOTAL B.
TOTAL PRICE / Costo Totale

&RSheet &P of &N

Grand Total

ASHE 13-1022 RPR PASs ELEC SYS AT ZULU LOOP, B. 7930, 7970, 7990, 8030
INSTRUCTIONS FOR COMPLETING AF FORM 3052
A. NEW CNSTRB. REPAIRTOTAL A+B (€)
TOTAL MATERIAL COSTS€0.00€0.00€0.00
TOTAL LABOR COSTS€0.00€0.00€0.00
TOTAL OTHER DIRECT COSTS€0.00€0.00€0.00
TOTAL DIRECT COSTS€0.00€0.000.00€0.00
OVERHEAD%€0.00€0.00€0.00
SUBTOTAL€0.00€0.00€0.00
PROFIT%€0.00€0.00€0.00
TOTAL PRICE€0.00€0.00€0.00
DATEFIRM NAME
TITLEMANAGING DIRECTORBY
INSTRUCTIONS TO OFFERORS

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). Item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). Item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs.