Attachment 2 - PWS RPL WWTP Fine Screen WO18121 - 9 July 2018
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_3_-_ROT_RPL_Filtro_de_Finos_en_Depuradora.pdf | ||
| Attachment_1_-_Price_Schedule_-_WWTP_Fine_Screen.xls | XLS spreadsheet | |
| FA5575-18-Q-MD05_-_WWTP_Fine_Screen.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
(PWS)
FOR
RPL WWTP FINE SCREEN
WO#18121
CIVIL ENGINEERING 496 ABS/CEORM
(9 July 2018)
PERFORMANCE WORK STATEMENT (PWS)
TABLE OF CONTENTS
SECTION PAGE
1. DESCRIPTION OF SERVICES 5-6
2. SERVICES SUMMARY 6
3. GOVERNMENT FURNISHED PROPERTY AND SERVICES 6
4. GENERAL INFORMATION 6/8
5. APPENDICES 9-16
6. DRAWINGS 01
DESCRIPTION OF SERVICES. The contractor shall provide all the management, tools, supplies, equipment and labor needed to replace fine filtration system and install a system for compacting and transporting solids in the WWTP, building 1215 at Morón Base.
1.1. Description of Work.
The work will consist of:
1.1.1. Supply and installation of filtering sieve of the characteristics indicated in appendix A.
1.1.2. Supply and installation of conveyor/compactor of the characteristics indicated in appendix A.
1.1.3. Isometric drawings of the installation of all the elements accompanied by lists of materials.
1.1.4. Plant operation and maintenance manual, describing the operating procedures, maintenance, spare parts and electrical operation, with description of the panelboard and PLC.
1.2. Brand Names.
Names indicated for materials are for the purpose of establishing a standard selection only. Other manufacturers' materials are acceptable provided they conform to all specified requirements.
Names indicated for the quality of model, give the quality standard to be achieved. Other manufacturer's materials are acceptable if it is equal to the quality and function of the suggested model. All selected material is subject to the approval of Contracting Officer.
1.3. Special Requirements.
The contractor will accomplish preliminary topographic survey of the drainage and stone rip-rap channels, maintaining existing initial and final invert elevations, leveling existing surfaces to check in situ interferences between the new channels with service lines and existing manholes. The contractor will submit workshop plans for approval. Once approved by the contracting officer this layout the contractor will be authorized to grade and build the natural berm and channels in their final location.
1.4. Final Cleaning.
Final cleaning of installations affected by this contract
1.5. Period of Performance.
The period of performance for this contract is two hundred and ten (210) days of field work.
The contractor will provide its deadline with its proposal.
The items mentioned and the list of main tasks do not limit in any way the responsibility of the contractor to perform all work required by the contract to provide a complete and operational installation.
1. SERVICES SUMMARY.
Performance Objective SOW Performance Threshold Activities. Par 1.1 100%
2. GOVERNMENT FURNISHED PROPERTY AND SERVICES.
3.1. Use of Base Utilities: Base utilities are available to the Contactor at no additional expense to the Contractor. The following utilities shall be available from the existing Base utility connections in reasonable quantities:
a. Electricity 120/208 volts, 60 Hz.
b. Water.
All of the equipment, materials and labor required to accomplish the aforementioned items stipulated shall be supplied by the Contractor, as part of this contract.
3. GENERAL INFORMATION.
3.1. Security Requirements. The contractor will request installation access through 496
ABS/CE.
3.2. Physical Security. The contractor shall be responsible for safeguarding all government property provided for contractor use. At the close of each work period, government facilities, property, and materials shall be secured.
3.3. Hours of Operation.
3.3.1. Normal Hours of Operation. The contractor shall perform the services required under this contract during the following hours: Monday to Friday, 08:00-17:00. The contractor may work, with prior approval of the Contracting Officer, extended hours to ensure timely completion of work at no additional cost to the Government.
3.3.2. Recognized Holidays. The contractor is not required to provide service on the following days: New Year’s Day, Martin Luther King Day, Presidents Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Days, Thanksgiving Day and Christmas Day. If the holiday falls on Saturday, it is observed on Friday. If the holiday falls on a Sunday, it is observed on Monday.
3.4. Conservation of Utilities. The contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions which prevent the waste of utilities which include the following:
3.4.1. Lights shall be used only in areas where and when work is actually being performed.
3.4.2. Mechanical equipment controls for heating, ventilation, and air conditioning systems shall not be adjusted by the contractor or by contractor employees unless authorized.
3.4.3. Water faucets or valves shall be turned off after the required use has been accomplished.
3.4.4. Government telephones shall be used only for official government business.
3.5. Records. The contractor shall be responsible for creating, maintaining, and disposing of only those government required records that are specifically cited in this PWS.
3.6. Environmental Controls:
3.6.1. Compliance with Laws and Regulations. The contractor shall be knowledgeable of and comply with all applicable Interstate, Federal, State, and Local laws, regulations, and requirements regarding environmental protection. In the event environmental laws/regulations change during the term of this contract, the contractor is required to comply as such laws come into effect. If there is an increase or decrease in cost as a result of the change, the contractor shall inform the Contracting Officer pursuant to notice requirements and negotiate a modification to the contract.
3.6.2. Notification of Environmental Spills. If the contractor spills or releases any substance contained in 40 CFR 302 into the environment, the contractor or its agent shall immediately report the incident to Moron AB Fire Dept at 117. The liability for the spill or release of such substances rests solely with the contractor and its agent.
3.6.3. Material Storage and Use. The contractor shall follow manufacturer’s guidelines and professional recommendations for control of humidity, temperature, cleanliness, and materials handling. This includes hazardous materials.
3.7. Government Observations. Government personnel, other than contracting officers (COs) and quality assurance personnel (QAPs), may from time-to-time, with CO coordination, observe contractor operations. However, these personnel may not interfere with contractor performance or make any changes to the contract.
3.8. Safety Requirements. In performing work under this contract, the contractor shall:
3.8.1. Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.
3.8.2. Take such additional immediate precautions as the contracting officer may reasonably require for safety and mishap prevention purposes.
3.8.3. Develop and provide at the start of the orientation period or the start of the first operational performance period (if there is no orientation period) a safety plan for the protection of government facilities and property and to provide a safe work environment for contractor personnel.
3.8.4. Provide protection to government property to prevent damage during the period of time the property is under the control or in possession of the contractor.
3.8.5. Include a clause in all subcontracts to require subcontractors to comply with the safety provisions of this contract as applicable.
3.8.6. Record and report promptly (within one hour) to the contracting officer or designated government representative (GR), all available facts relating to each instance of damage to government property or injury to either contractor or government personnel.
3.8.7. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the contracting officer.
3.8.8. If the government elects to conduct an investigation of the accident/mishap, the contractor shall cooperate fully and assist government personnel in the conduct of investigation until the investigation is completed.
3.8.9. Include a clause in each applicable subcontract requiring the subcontractor's cooperation and assistance in accident reporting and investigation.
3.9. Special Qualifications. The Contractor shall submit any commercial certifications and a reference of past performance on similar works performance to the existing as a means to verify experience in this field of work.
3.10. Continuation of Essential DOD Contractor Services During Crisis IAW DoDI 3020.37.
IAW AFI 63-124, para 2.7.1, and DODI 3020.37 this requirement is not considered mission essential.
3.11. Contract Restriction: In accordance with the Agreement of Defense and Cooperation between the Kingdom of Spain and the United States of America, any contract resulting from this notice/solicitation can only be entered into with companies authorized to carry out these activities in Spain under Spanish law. Companies must meet the requirements established by Spanish legislation for execution of Government works. In addition, in accordance with the Office of Defense Cooperation Policy Directive 400- 5 "(4) Spanish material, labor, and equipment must be used if permitted by the requirements of the contract specifications."
APPENDIX A
NICAL SPECIFICATION
APPENDIX A
SPECS
INDEX
1. DESCRPTIVE MEMORY
2. DESIGN DATA
3. WASTE MANAGEMENT ESTIMATES
4. EQUIPMENTS
1. DESCRPTIVE MEMORY: At the present time, there are two filter systems in the channel, one after the other:
The first sieve, coarse roughing, works correctly and no action is required, the second sieve does not work properly, in addition the solid compaction and transport system is inefficient and does not transport the solids removed to the desired location, which would be in the outer road close to the existing curb:
2. DESIGN DATA: The channel width is 680 mm and the depth is 1,000 mm. The passing light of the new equipment must be 3 mm. The design flow used, according to the data provided by the treatment plant, is 134 m³/h.
CONTAINER
LOCATION
3. WASTE MANAGEMENT ESTIMATES: The estimated waste management calculations are as follows:
3.1. Waste production:
Waste production indices
- Coarse roughing (L/1,000 heq/d) 25,0
- Fine roughing (L/1,000heq/d) 40,0 Daily volume
- Waste roughing coarse (L/d) 78,1
- Waste fine grinding (L/d) 125,0
3.2. Transport of coarse waste
Type: Conveyor/compactor screw
- Volume reduction (%): 66,7
- Volume pressed (L/d): 26,0
- Nº units in operation 1
- Operating time (h/d): 4,0 Capacity
- Minimum (L/h): 6,5
- Adopted (L/h): 750,0
3.3. Transport of fine waste
Type: Conveyor/compactor screw
- Volume reduction (%) 66,7
- Volume pressed (L/d) 41,7
- Nº units in operation 1
- Operating time (h/d) 4,0 Capacity
- Minimum (L/h): 10,4
- Adopted (L/h): 500,0
3.4. Storage of coarse waste
Type: Metallic container
- Nº de units 1
- Unit capacity (m³): 1,1
- Storage capacity (d): 42,2
3.5. Storage of fine waste
Type: Metallic container
- Nº de units 1
- Unit capacity (m³) 1,1
- Storage capacity (d) 26,4
4. EQUIPMENT: The equipment will be the following:
4.1. Filter sieve. With the following characteristics:
a. Flow rate of treatment: 134 m³/h
b. Water sheet and admissible flow rate considering passing speed: 1 m/sec.
c. Channel width: 680 mm
d. High channel: 1,000 mm
e. Water sheet height: 152 mm
f. High discharge (From support floor): 2,000 mm
g. Inclination equipment: 75º
h. Step light: 3 mm Type of mobile grid
i. Structure type: Monoblock
j. Flow rate of washing water: 36 liters/minute
k. Washing water pressure: 3 Kg/cm²
l. Conductor sprockets Two in upper head
m. Water inlet piping: 1”
n. Cleaning brush filter grid: Yes (motorized)
o. Separating washers: Derlin 7.5
p. Possibility of inversion direction of rotation: Yes
q. Lift speed filtering grid: 3.4 m/min.
4.1.1. Construction materials:
- Construction frame: Inox. Aisi - 316/1,4401 - EN10088
- Filtering grid construction: Inox. Aisi - 316/1,4401 - EN10088
- Side construction filtering chain: Inox. Aisi - 316/1, 4401 - EN10088.
- Construction skates chain: Inox. Aisi - 316/1,4401 - EN10088
- Construction brush cleaner: RILSAN
- Construction of separating rods: Inox. Aisi - 316/1, 4401 - EN10088.
- Construction of tension plates: Inox. Aisi - 316/1, 4401 - EN10088.
- Construction of protective covers according to CEE standard: Inox. Aisi - 316/1, 4401 - EN10088.
- Fixing elements: Inox. Aisi - 316/1, 4401 - EN10088
- Separating washers: Nylon anti wear
- Drive shaft construction: Inox. Aisi - 316/1, 4401 - EN10088
- Cleaning brush shaft construction: Inox. Aisi - 316/1, 4401 - EN10088
- Construction Conductor pinions Carbon steel A42-b / S275JR - EN10025
- Piping cleaning filter grid: Inox. Aisi- 316/1, 4401 - EN10088
- Screws in submerged areas. Inox. Aisi- 316/A-4
- Screws in exposed areas. Inox. Aisi- 316/A-4
4.1.2. Motor drive (Main):
- Electro Adda electric motor or similar Power: 0.55 KW
- Input speed: 1420 Rpm
- Voltage and frequency: 120V 60 Hz
- Protection and insulation: IP-55 class F
- Single direction of rotation: Yes
4.1.3. Reducing drive: (Main)
- Mechanical reducer: Hidromec or similar Output speed: 3,1 rpm
- Service factor over consumed power:1,8
- Operation: Hollow shaft.
4.1.4. Motor drive: (Brush)
- Electro Adda electric motor or similar Power: 0,37 KW
- Input speed: 1420 rpm
- Voltage and frequency: 120V 60 Hz
- Protection and isolation: IP-55 class F
4.1.5. Reducer drive: (Brush)
- Mechanical reducer: Hidromec or similar Output speed: 30 rpm
- Service factor over consumed power:1,8
- Operation: Hollow shaft
- Finishes: Stainless Steel parts. Exposed and submerged (avesta welding pickling) and subsequent pressurized hot water jet enamel Bi-component silver metallic.
4.2. Worm screw conveyor/compactor. With the following characteristics:
a. Transport capacity: Between 0.75 and 1.50 m³/h.
b. Working position: Horizontal
c. Pushing Function
d. Diameter helical thread: 160 mm Length: 2,700 mm
e. Compaction zone length: 500 mm
f. Total length without counting motor reducer: 3,200 mm
g. Distance from loading hopper to ground: 500 mm
h. Transport channel: Thickness 1.50 mm
i. Polyethylene transport bed: Thickness 6.00 mm
j. Protective caps according to CEE standard Thickness 1.50 mm
k. Support legs: Thickness 3.00 mm
l. Reinforcements body: U-shaped thickness 2.00 mm
m. Loading nozzles 1
n. Loading mouth width: 500 mm
o. Load port length: 680 mm
p. Cleaning brush location: In mouth/s load
q. Type of structure: Monoblock.
r. Compaction head: Perforated 3.00 mm.
s. Liquid outlet pipe in 1 ½”compaction head male thread
t. Liquid outlet pipe in load port 1 ½” male thread.
4.2.1. Construction materials:
- Construction of “U” compactor channel Inox. Aisi - 316/1, 4401 - EN10088
- Support legs construction Inox. Aisi - 316/1, 4401 - EN10088
- Helical thread construction (Hollow shaft) Swedish cemented steel F-1515
- Drive shaft construction Carbon steel F-5 Reinforcement of the Inox compactor channel. Aisi - 316/1, 4401 - EN10088
- Construction plate support motor reducer Inox. Aisi - 316/1, 4401 - EN10088.
- Stainless steel loading hopper construction. Aisi - 316/1, 4401 - EN10088
- Transport bed: HD-1000 polyethylene
- Cleaning brush: Nylon anti wear
- Construction of protective covers according to CEE norm: Plastic Polyethylene
- Handle for cover type: 1157 code 1157, 14, 200
- Material construction mouth discharge: Inox. Aisi - 316/1, 4401 - EN10088
- Screws in submerged areas Stainless steel. Aisi - 316/A-4.
- Screws in stainless steel areas. Aisi - 316/A-4
- Liquid outlet pipe (L = 80 mm) Stainless steel Aisi - 316/1, 4401 - EN10088
4.2.2. Reducer drive:
- Reducer mechanical: Hydromec or similar Type Visinfin crown
- Output speed: 15 rpm
- Service factor over consumed power: 1.8
- Operation: Hollow shaft
- Electric motor: Electro Adda or similar Power:0.55 KW
- Input speed:1420 rpm
- Voltage and frequency:120V 60 Hz
- Protection and insulation: IP-55 class F Assembly B-5
4.2.3. Finishes:
- Exposed and submerged stainless steel parts (pickling Avesta welding) and subsequent pressurized hot water jet metallic silver bi-component enamel-helical thread finish, epoxy resin prime coat (20 microns) and HEMPEL finish coat, two blue components RAL 5003 (50 microns)
A
D
E
I
TAMIZ FILTRANTE AUTOLIMPIANTE
SINF[N TRANSPORTADOR COMPACTADOR
BORDILLO
L __ _J
ISOMETRICO DE LA INSTALACION
S/E
I
I
L_
I
I
L
I l
N
CX) co
0 co
J
ALZADO DE LA INSTALACION
J
PLANTA DE LA INSTALACION
t-----------------r----------------"""T'"---------------....... --------------,.-----...... ------------------------l f
ESCALA:
\{ECTRUS
f./11! 11 , llf.l"I I '.
SUSTITUCioN TAMIZ
TDRNILLD + TDRNILLD
CDMPACTADDR
2 3
NOMBRE DE LA OBRA:
�OMERO DE PLANO:
1-..DE_1
NOMBRE DEL PLANO:
REFERENaA DE LA OFERTA:
N' REVISION: FICHERO INFORMATICO
S/E REV 0
FECHA: VERIFICADO POR: CHA APROBACION: DIBUJADO POR:
6 7