Text version
FOUO
RAF Molesworth, UK 1
STATEMENT OF OBJECTIVES
For
GIANT VOICE (GV) EXPANSION
At
RAF Molesworth, United Kingdom
30 June 2021
RAF Molesworth, UK 2
1.0 SCOPE. This Statement of Objectives (SOO) defines the requirements for the Contractor to Engineer, Design, Furnish, Install, and Test (EDFI&T) a turn-key Giant Voice System expansion required at Royal Air Force (RAF) Molesworth, Uni ted Kingdom (UK).
The current Giant Voice (GV) system has one (1) existing SiRcom Omni-direction speaker and it does not provide sufficient intelligible voice coverage for the entire base populace. The current SiRcom GV system utilizes a fiber network communication infrastructure. The contractor will be required to install an additional Bi-Directional speaker arrays to expand the current GV system audible sound coverage. This project covers the following technical requirements.
1.0.1 The Contractor shall use the existing Giant Voice equipment, related controllers, fiber switches, and media converters and established stand-alone IP network enclave for the GV system expansion.
1.0.2 The Contractor shall install one (1) new galvanized steel poles, 18 meters height, and a direct bury through a concrete slab.
1.0.3 The Contractor shall install one (1) square concrete slab (6ft L x 6ft W x 4ft D). The top of slab shall be a smooth finish, not standing water, and 6 inch above ground level.
1.0.4 The Contractor shall install a Bi-Directional Speaker Arrays; 6 horns (900watt) point toward Firing Range (B611) and 4 horns (600watt) point toward the baseball field. The Contractor shall test and adjust the volume to ensure minimal noise bleed to a surrounding community.
1.0.5 The current SiRcom central control station is located at the Base Defense Operating Center (BDOC) Bldg. 318. The Contractor shall use the existing IP-based central control stations equipment to communicate over fiber network infrastructure reprogram two-way communications software, to include the following: a new siren pole, PC-based computer with GUI interface to all outdoor systems which shall have the pole IP addresses that can be easily selected from a map view or zoning system, monitoring the control, activation and display of siren speaker’s and complete system health status.
1.0.6 The existing AtHoc Network Alerting System is integrated with the current GV system. The Contractor shall program and test the GV expansion system with the existing Government AtHoc IP integration Module (IIM64) to include the new siren SCU/speakers for the proper broadcasting alert messages.
1.0.7 The GV expansion system is a combination of methods using pre-recorded and live voice messages, and electronic communication. RAF Molesworth must have a GV expansion system with the capability to disseminate rapidly and effectively the emergency information to warn all personnel immediately, but no longer than 10 minutes, before, during and after incident notification and verification.
1.0.8 RAF Molesworth’s GV expansion system must be capable of operating and ensuring all personnel can immediately hear or see status changes and take action. For example, RAF Molesworth, UK 3 voice warnings must be audible to personnel outside facilities and over background noise such as air-conditioning units.
1.0.9 The GV expansion system shall provide announcement for terrorist attack, weather warnings, Force Protection, chemical spills, active shooter, exercises, local accidents affecting base operations and/or general announcements.
1.0.10 The Contractor shall utilize pre- and post- proposal walk through information to analyze project requirements, sound propagation analysis, perform engineering design tasks, and develop the data deliverables. The sound propagation mapping software shall be used to determine the sound travel, environmental attributes of the land, buildings and the effect on sound travel. This software shall also be used to determine the best hardware to utilize and the preferred optimal speakers and locations for pole. See Table 1 and Figure 1
1.0.11 The GV expansion system will be monitored and accessible 24/7 by the BDOC. The GV system access will be both secured and password protected.
2.0 REQUIREMENTS
2.1 GENERAL REQUIREMENTS. The Contractor shall provide equipment, licenses, software, speakers, wiring, conduits, electrical power, tools, lift, materials, supplies, transportation, labor, supervision, management, concrete pads and other incidentals necessary to EDFI&T (this should be spelled out) the requirements as stated in this SOO. The Contractor shall expand the current GV system, and all required support for this fiber network communication infrastructure, central control equipment and software. All equipment, materials and software shall be new and not refurbished.
2.1.1 Safety Requirements. The Contractor shall meet with the base safety officer immediately, upon arrival on site, for review of the specific safety requirements prior to installation.
2.1.2 Confined Space. The Contractors and Sub Contractors entering spaces on RAF Molesworth, UK are responsible for the safety of their personnel and for their own permit space program as outlined in OSHA 1910.146. All confined space operations must be coordinated with the Wing Safety office, 423 ARW/SE, prior to start of work. The primary Contractor is responsible for all sub-Contractor confined space operations.
2.1.3 Accident/Incident Reporting and Investigation. The Contractor shall record and report all available facts relating to each instance of injury to either Contractor or Government personnel to the Wing Safety Office unless otherwise stated in the SOO. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority, through the 423 CS/SCOI/SCXP. If the Government elects to conduct an investigation of the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.
2.2 Security Requirements
RAF Molesworth, UK 4
2.2.1 Secure Areas. Some of this work will take place in secure areas where Contractor employees must be employees escorted at all times. The Contractor must coordinate access to secure areas at least ten (10) business days ahead of time. It is the Government's responsibility to provide escorts. The Contractor shall not require Security Clearances.
2.3 Environmental Management. The Contractor shall comply with the most stringent environmental RAF Molesworth, UK local laws and regulations; and Air Force policies, instructions, plans and environmental archaeological requirements. The Contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on RAF Molesworth, UK. The Prime Contractor shall ensure their sub-Contractors comply with these specifications.
2.4 Permits. The 423 CS/SCOI/SCXP will coordinate with Base Civil Engineers (CE) and BT FEDERAL and successful awardee on completion of AF Form 103 Digging Permits before any digging, power, fiber, trenching, boring, and one (1) concrete pad, restoration, and compacting are accomplished. The Contractor shall complete the Defense Infrastructure Organization (DIO) Form 29 to work on base.
2.5 Integrated Product Team (IPT). The Contractor shall chair a weekly IPT meeting that includes Contractor representatives, the Contracting Officer (CO), the 38 ES/ENPO, representatives from the 423 CS/SCOI/SCXP and all other required base personnel from RAF Molesworth, UK. The Contractor shall provide a worldwide “Meet Me” Teleconference capability for the duration of the project. The purpose of this meeting is to discuss project progress, problems encountered, corrective action items, and other discussions necessary/ beneficial to timely completion of the Task Order and ensure success. The Contractor shall be responsible for keeping records of the meeting minutes. A copy of the meeting minutes shall be provided to each attendee, and disseminated via e-mail addresses (CDRL A004).
2.6 Quality. The Contractor shall provide a Quality Control Program for the entire life-cycle of the project. The Contractor’s quality assurance evaluator shall assist the Government representative in performing random spot checks and system acceptance tests. The Contractor shall be responsible for identifying system and outside plant deficiencies and/or discrepancies throughout the life of the project. A weekly report (soft copy) shall be submitted indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them
(CDRL A003).
2.7 Contractor Personnel
2.7.1 Project Management. The Contractor shall designate a Project Manager (PM) and alternate(s) Project Manager to be responsible for contract performance and continuity. The Contractor shall identify the scope of authority of the Project Manager and Alternate(s) to act on behalf of the Contractor for matters relating to daily contract operation.
RAF Molesworth, UK 5
2.7.2 Site Point of Contact (POC). The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for individual projects in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours until project completion.
The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancies related to performance matters.
2.7.3 Enterprise-Wide Contractor Manpower Reporting Application (BetaSAM.gov) The Contractor shall report ALL Contractor labor hours (including sub-Contractor labor hours) required for performance of services provided under this contract for upgrading the 844 CG/SCX Giant Voice system via a secure data collection site. The Contractor is required to register in the system for award management and fill out all required data fields using the following web address at: https://beta.sam.gov/ Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each business year.
Contractors may direct questions to the beta.sam.gov customer service. THIS DOES NOT
MAKE SENSE
2.8 Warranty. The Contractor shall provide guarantees that the products of its manufacturer are free from defective material and workmanship. Break-fix support for hardware, software, speakers, wiring, and any and all speakers, unspecified components of this system related to the GV expansion system shall be provided for one year after the GV system acceptance date, to include all field trips, telephone support, and shipping costs. The Contractor shall not be responsible for the installing of the British Telecom Federal (BT FEDERAL) Fiber Optic Cable (FOC) Outside Plant (OSP) and the electrical power. The Contractor shall be responsible and warranty electrical and outdoor rated FOC connections.
2.9 Out-brief. The Contractor shall conduct an out-briefing with the 423 CS/SCOI POC or designated representative at the conclusion of the implementation. The implementation out-brief shall inform the customer of implementation results and necessary maintenance issues (including warranties).
2.9.1 Manuals and Practices. The Contractor shall provide the latest version of operation, installation, and maintenance manuals and practices/users guide for each system installed as provided by the original manufacturer with all new or upgrade equipment.
3.0 SPECIFIC REQUIREMENTS
Outside Plant Requirements. The Contractor shall EDFI&T and coordinate with 423 CS/SCOI, 423 CS/SCXP RAF Molesworth to ensure the Fiber Optic Cable (FOC) is run properly to new pole site, SCU, and buildings/ITNs for the GV expansion system. The outdoor blown fiber optic cables are funded by a local sole-sourced O&M contract with British Telecom Federal (BT FEDERAL). The electrical power will be supported by the base Civil Engineer, and the Contractor shall provide as-built drawings upon project completion (CDRL A001).
https://beta.sam.gov/
RAF Molesworth, UK 6
3.0.1 Molesworth GV system currently has the existing SiRcom pole mounted Omni Directional loud siren speakers. See attached Figure 1 below.
3.0.2 The GV expansion system shall be interconnected via existing Government Furnished Equipment (GFE) fiber infrastructure and distribution system. The Contractor shall use the existing outdoor GFE fiber optic cables for connection to siren controller units (SCUs). The Contractor shall install 4 strands Single Mode (SM) from the fiber patch panel and connect to the media converters, Cisco 24 port Gigabit fiber switches, and also connect CAT 6 cables to the IP-based interface modules which are located inside the SCU. The LC connectors, media converter and CAT6 cable shall be used to interface with the equipment. See Table 1 below.
3.0.3 All fiber shall tie back to Core Node buildings (B400 critical node and B318/ITN) for media conversion and central broadcasting from the central fiber switches using fiber network infrastructure. All fiber links must be connected together the above Core Node buildings with existing fiber switches as the only means of the new GV system fiber reliable and redundant communications connectivity and transport.
Table 1. The Proposed New GV Pole Locations, Fiber Optic Cables and Power Requirements
Pole Name Coordinates Siren Controller Unit (SCU) Equipment
Location
Manhold/LAN Rack # OF
SM/MM
Fiber Optic Cable
Strands Requirement
AC Power Requirements
New Galvanized Steel GV# 2 (B420, AFRICOM)
Long:
0.421765, Latitude:
52.383677
(New Bi-directional speakers, 900watt each, Volume Output adjustable)
New SCU shall be installed on the steel pole.
New Harsh
Weather Media
Converter, CAT 6 Cable.
Fiber patch panel at B318, Reserve 4 SM FOC ports. Reserve 4 SM fiber cables run from B318 to Manhole #29.
Blow 4 strands SM FOC from
MH#29 to the SCU cabinet.
Pull power from Existing B420 Outside Power
Box. Estimate 100 meter direct bury run to the pole. Trench under Manhole duct.
240VAC, B16 Amp circuit breaker, 1 phase, 50Hz.
RAF Molesworth, UK 7
Existing Galvanized Steel GV#1
Long:
0.417494, Latitude:
52.383677
(Existing Omni-directional speakers)
Existing SCU was installed on the pole.
Existing Fiber Patch and Rack
Existing 4 strands SM
Existing Power Panel
Figure 1. The Molesworth GV Expansion Audible Sound Coverage
3.0.4 The Contractor shall install the proper weatherproof head and liquid tight devices and sealant to prevent moisture, water and insects from entering the outdoor siren controller units.
The Contractor shall install the 2 inch electrical tubing conduits, couplings, straps, tape and cable tie for securing the fiber optic cables, power cables, and siren speaker wires
3.0.5 The Contractor shall coordinate with the Base CE to ensure the appropriate voltage and current are provided to the new siren tower location electrical load and the communication. The Contractor shall need to be a skilled person qualified by DIO to test the voltage, current, wire size, distance, transformer size, fuses, breakers, voltage, current limiting devices, and other variables to ensure they are correctly utilized to drive the new load for the upgrade GV system.
The Contractor must possess the critical electrical qualifications, skills and ability to proficiently perform the tasks, operations, and functions.
3.0.6 The Contractor shall coordinate with 423 CS/SCOI/SCXP and 423 CES before energizing all new power loads.
3.0.7 The Contractor shall comply with all applicable documents including standards in paragraph 5.1.
3.0.8 Upon project completion the Contractor shall provide configuration management, the as-built drawings and documentation of the installed system, including the predicted and tested audible coverage areas. The Contractor shall deliver the As-Built drawings CD in Microsoft Visio format and a courtesy copy in PDF IAW CDRL A001.
3.0.9 Each siren tower shall utilize proper 12VDC batteries system for the siren speakers and proper back-up batteries for the GV expansion system.
3.0.10 The Contractor shall provide the proper grounding rod, bonding, wiring, and lighting arrestor protection for all siren speakers, pole and the SCU.
RAF Molesworth, UK 8
3.0.11 The Contractor shall mount a new SCUs on the new galvanized steel pole. The bottom of the cabinet unit shall be mounted 4ft above the ground level.
3.0.12 BT FEDERAL shall ensure the availability of the existing main ducts PVC, tubes, microducts, and fiber cables, and power cables to the new pole’s SCU. BT FEDERAL shall install, blow fiber cables and coil the sufficient fiber cables inside the steel pole. Base CE will trench and install the two 2 in PVC paths for fiber cables and power cables inside the steel pole.
The Contractor shall connect the fiber cables and power cables to the outdoor SCU. The fiber and power cables shall not be spliced to the SCU.
3.0.13 The Contractor shall ensure and install the rated fiber cables from the fiber patch panels to the existing Cisco Gigabit fiber switch and to the new SCU.
3.0.14 The Contractor shall install the new harsh environment media converters inside the new outdoor SCU.
3.1 Installation Requirements.
3.1.1 Restoration. Any wall penetrations shall be restored to meet National Fire Protection Association (NFPA) 1, NFPA 70 and NFPA 72 standards.
3.1.2 Grounding. The Contractor shall properly ground new SCU to the Telecommunication Main Ground Bus-Bar (TMGB), near the terminal in all communication rooms. Ground all fiber transmission lines to the building and upon entering the building, all fiber transmission lines shall route through a fiber Transient Voltage Surge Suppression (or Surge Protection Device).
Technical Order (TO) 31-10-24 “Installation Practices – Communication Systems Grounding, Bonding, and Shielding” must also be adhered to. The GV Contractor shall properly ground the GV equipment and electrical power installs IAW base, host nation, local, state and federal codes, laws and National Electric Code’s most recent edition and in paragraph 5.1.
3.1.3 Bonding. Shield bonding connectors, bond bars, braids, ribbons, clamps, etc., shall be provided to maintain cable shield continuity at splices and at ground connections. Bonding connectors shall be provided IAW the Rural Utilities Service (RUS) Bulletin 1753F-803 (PE- 33). Shields shall be grounded and continuous throughout the cable distribution system.
3.1.4 Power Source. The Base CE will install new 240VAC, C 16 amp circuit, 1 phase, electrical power for the new pole, conduits, and dedicated power. Base CE will pull power from Existing B420 outside Power Box to the new SCU mounted on the new galvanized steel pole.
The SCU shall operate on the primary electrical power 240VAC, 50Hz, C16 amp, and 1 phase.
The Contractor shall coordinate with 423 CS/SCOI and CE on all electrical work performed.
3.1.5 Galvanized Steel Poles. The Contractor shall install the new galvanized steel pole, 18 meters height from the ground to the top. The new steel poles shall withstand a wind load up to 100 miles per hour sustained and 140 mph 3 second gust. The new steel pole and siren speakers shall not exceed 60ft and meet the height restrictions as specified by RAF Molesworth base CE.
RAF Molesworth, UK 9
The new shall support the full weight of the siren speakers and the windload. The locations of the new and existing poles are identified in Figure 1 above and Table 1 above. The Contractor shall install the proper 2 inch PVCs, conduits, ducts, liquid tight, connectors, weatherproof sealants for speaker cables and power cables, proper ground rods, cables and clamps for the lightning protection.
3.1.6 The Contractor shall install a new square concrete pad with an 8”Hx 4ftLx4ftW. The new galvanized pole shall be secured and direct bury through the concrete pad. The Contractor shall install two conduits/ducts paths for the fiber cables and the power cables utilizing stub-outs from concrete pads. BT FEDERAL install the new PVC ducts, tubes external blown fiber micro-ducts for the fiber optic cables, and electrical cables. The Contractor shall coordinate with 423 CS/SCOI/SCXP, BT FEDERAL, and Base CE. See Figure 1 and Table 1 above.
3.1.7 The SCU must be rated National Electrical Manufacturer Association (NEMA-4), two-way fiber link communications and provide real-time feedback status to the central control stations.
3.1.8 The GV expansion system shall provide pre-recorded voice alert messages, informational messages, action to be taken, playing of taps, retreat, reveille, and active shooter announcement messages to all personnel in the event of an emergency, terrorist threats, Force Protection contingencies, and exercises. The pre-recorded messages will be provided upon contract award.
3.1.9 Features and Capabilities. The GV expansion system shall provide the following features and capabilities:
3.1.9.1 The siren speakers shall deliver alert, warning and informational messages of what to do before, during and after an emergency, exercises or disaster by the operators at the BDOC B318.
3.1.9.2 The BDOC B318 Central Control Stations shall transmit emergency announcements as live voice messages to alert and warn base personnel through remote siren speakers via microphone to any individual zone or all zone speakers.
3.1.9.3 Activation and control subsystems. The Contractor shall utilize the fiber optic cable communications infrastructure for the GV expansion communications architecture. The Contractor shall provide the central control activation and communication system with stand-alone IP network and not connect to the base network.
3.1.9.4 The system shall allow operators to activate SCU independently and an entire system.
The system shall be equipped with a silent test diagnostic that allows it to test all major system components without producing an audible signal.
3.1.9.5 The SCU shall allow for multiple activation sequences to be programmed from the central control stations or locally at the site.
3.1.9.6 The SCU shall utilize a separate battery cabinet that isolates the batteries from the electronic circuitry. The system shall be equipped with a silent test diagnostic that allows it to
RAF Molesworth, UK 10 test all major system components without producing an audible signal.
3.1.9.7 The SCU shall use extremely efficient hot swappable pulse width modulated amplifiers or single board amplifiers to provide the highest reliability and efficiency in a small modular weatherproof enclosure. Controller units shall be powered from standard 12VDC batteries, and the sirens shall operate continuously for at least 30 minutes in tone and voice.
3.1.9.8 The amplifier shall be a modular component, which is hot swappable or single board amplifier, allowing easier maintenance and increased redundancy.
3.1.9.9 The GV expansion system shall be programmed to perform automatic testing of all speakers in the system, weekly and/or monthly routine report, quiet testing, growl testing, or a full system test.
3.1.9.10 The GV expansion system shall provide secure digital communications methods via 256 bit encryption to prevent malicious, unauthorized access or accidental operation of the system.
3.1.9.11 A detailed sound propagation analysis shall be performed to determine the exact siren speaker’s and horn size and intelligible voice coverage IAW CDRL A006. The Contractor shall use Figures 1 and Table 1 above to design and install the siren speakers for the required intelligible voice and tone coverage requirements
3.1.9.12 The Contractor shall provide a bucket/line truck and a licensed driver to operate the truck.
3.1.10 System Interface. The GV System shall provide the following features:
3.1.10.1 Application Programming Interface (API) to remotely activate audible alerts.
3.1.10.2 Standard TCP/IP network protocols, RS 232, RS-485, and audio-in input. The equipment should be on the AF APL.
3.1.10.3 The API shall conduct all interactions using XML messages conforming to the OASIS (Organization for the Advancement of Structured Information Standard) Common Alerting Protocols (CAP) Standard.
3.1.10.4 The API shall allow an external system to initiate specified pre-recorded audio alerts in the GV expansion system.
3.1.10.5 Target activation of specific sirens or speakers.
3.1.10.6 Request reports on the status of delivery and activation of an alert already in progress; specifically, if the alert was delivered to all targeted speakers and these speakers are sounding the alert.
RAF Molesworth, UK 11
3.1.10.7 Terminate an alert already in progress.
3.1.10.8 Request reports on system health status, replying with a detailed response.
3.1.10.9 The GV expansion system central control consoles shall configure and program to allow the control and activation of target GV siren or speaker via dry contacts and audio-in input.
3.1.11 Pre-programming. The GV expansion system shall be pre-programmed with the following existing messages:
NOTE: This is intended as a general list and the exact message list will be supplied by the base at the Walk-Through.
3.1.11.1 Example Broadcasting Messages:
• Westminster Chime
• Attack Warning
• Disaster Warning
• FPCON Alpha
• FPCON Bravo
• FPCON Charlie
• FPCON Delta
• Lightning Announcement
• All Clear
• Hazardous Material
• Severe Weather
• Recall Message
• Active Shooter Announcement
• Heat Advisory Start/End
• Weather Warning
• To The Colors
• Retreat, Bugle
• Reveille
• Bugle Taps
• The National Anthems (England and American)
• Retreat/Anthem
• Lock down
• End Message Indicator
3.1.11.2 Broadcasting Tones:
• Alt Steady
• Alt Wail
• Pulse Steady
• Pulse Wail
3.1.11.3 Broadcasting Voice:
RAF Molesworth, UK 12
• Public Address
• Audio level (line-level) input
3.1.11.4 Control System will perform the following functions:
• Reset - used to reset all poles
• Cancel - used to cancel a message in mid-stream
• Test Message
• Silent Test
3.1.12 Zone Selectable. The GV expansion system shall provide a speaker zone selective capability. All zones are linked to provide simultaneous activations and selective zone ability to activate each individual zone or all zones of the siren speakers. The GV expansion system shall allow for the pre-configuration of two (2) zones, which can be selected by the operator to promptly issue an announcement to the selected area.
3.2.14 Central Control Stations. The GV expansion system shall have two-way IP fiber optic communications alarm software with graphics screen for control and status monitoring. The system shall be capable of being activated, monitored, and controlled and receive real-time remote status monitoring of all system activities from BDOC, B318. The Contractor shall use the existing GPS time server, GPS antenna, cables and mounting brackets for maintaining the accurate timing and synchronization of the central control PC console clock and activation.
3.2.15 BDOC, Building 318. The Contractor shall use the existing Desktop PC with Windows 10 Operating System (OS), 22 inch monitor and ink jet printer, encoder, desk mount noise canceling microphone, Smart UPS (240VAC) and software packaged.
3.2.16 Backup Power for Control Stations. The Contractor shall provide central control station with its own backup power (UPS) to maintain operations during emergencies that could result from temporary loss of normal base utilities. Backup Power Capacity for fire alarm systems is defined in the National Fire Alarm Code, NFPA 72, and section 4.4.1. As stated in Annex E of NFPA 72, mass notification systems should have the same backup power capacity as fire alarms. NFPA 72 states that the secondary supply for the control station shall be capable of supporting alarm operation for a minimum of 4 hours.
3.2.17 Wiring and Infrastructure. The Fiber Optic Cables shall be done by the BTFED. The GV Contractor shall furnish and install all signaling wiring to include fiber and SC connector to provide control of the GV expansion system.
3.2.18 Electrical Power. The Base CE will install the new electrical power sources to provide power to the GV expansion system. The current GV system will be operational during the installation of the new system. The Contractor shall coordinate with Civil Engineering Electrical Shop on power removal, modification, and/or installation of dedicated 230VAC power for new and established poles and power to facility. The Contractor shall coordinate with 423 CS/SCOI/SCXP and BT FEDERAL and base CE on all electrical work performed.
Installations must comply with NFPA 70 (National Electric Code), host nation rules and standards and UFC 3-520-01 low voltage
RAF Molesworth, UK 13 requirements.
3.2.19 Coordination. All allied support infrastructures shall be coordinated and approved by the 423 CS/SCOI/SCXP, BT FEDERAL and 423 CES.
3.2.20 Audible and Visual Signal. When broadcasting tone alerts for different warnings and when used as a vocal GV system for command and control instructions, the speaker system shall produce an audible signal and intelligible voice messages to any personnel located in the populated areas.
3.2.21 Music and Voice. The GV system shall be capable of broadcasting standard military music selections and recorded voice.
3.2.22 Legacy System Removal/Site Restoration/Debris Removal. The Contractor shall remive GV equipment and infrastructure (electronics, cabling, and power) which is not used in the project, to include all spares and excess soil. Coordinate with Civil Engineering Electrical Shop on power removal, modification, and/or installation feeds at each site. Installations must comply with NFPA 70 (National Electric Code) and UFC 3-520-01 low voltage requirements.
All GV equipment/ residuals from this project including conduits and cabling shall be turned over to the 423CS/SCIO/SCXP for disposal through the Defense Realization and Marketing Office (DRMO) at RAF Molesworth, UK as directed by the Contracting Officer (CO). Prior to project completion, the Contractor shall remove all debris and surplus materials from the work place. Equipment and materials required to complete the work effort may remain on site during the project as long as they are organized/stored in a manner that does not cause a safety or security hazard. The Contractor shall accomplish the necessary ground clearing and install required for the new poles. The Contractor shall return all disturbed areas to their original condition upon completion of the installation.
3.2.23 Service Outages. The Contractor shall prevent any unscheduled (i.e. cutting or disabling any in-service cables or equipment.) interruptions of communications capabilities. The Contractor shall coordinate planned outages with 423 CS/SCOI in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).
3.2.24 Identification/Marking. The Contractor shall clearly mark all Contractor-Furnished Property and Equipment (CFP/CFE) with their company's name. The Contractor shall place an easily read, very visible, sign (minimum 8.5" x 11") on large containers, pole #, construction equipment, or unmanned rental vehicles while on the Government installation indicating the company name and both the Contractor and Site POC's names and local telephone numbers. The Contractor shall label all equipment, pole #, and cables they install IAW ANSI/TIA/EIA-606-A- 2002.
3.2.25 Installation Schedules. The Contractor shall provide a complete milestone schedule that denotes project activities to include time-phased start and completion dates for the project and sub- projects associated with the installation of the components and system IAW CDRL
RAF Molesworth, UK 14
A002.
3.2.26 Weekly Status Reports. The Contractor shall prepare a Weekly Status Report and distribute IAW CDRL A003. The purpose of the report is to inform IPT members of project progress, and any problems being encountered, and other topics necessary/beneficial to ensure success and timely completion of the contract requirements.
3.2.27 Red-Line and As-Built Drawings. The Contractor shall submit drawing(s) showing the “as built” configuration in Visio format. The As Built Drawings shall include the locations of all existing and the upgraded tower locations; the Global Positioning Satellite (GPS) coordinates of each tower location, the logical diagram of the GV system, the facility location of the GV equipment, a floor plan of the room location, power source facilities and connections, a rack elevation plan of the GV equipment, and tested coverage areas for RAF Molesworth, UK. The coverage area drawings shall be shown on a satellite image of the coverage areas with the street names, facility locations and other geo-references shown IAW CDRL A001.
3.2.28 Test Plan. The Contractor shall submit a written test plan that details how they will test the GV expansion system, all station encoders, and all siren speakers’ arrays and ensure compliance with Unified Facilities Criteria (UFC) 4-021-01. In addition, the Contractor shall submit written instructions to system operators for conducting periodic system tests. The test plan shall include the Cutover Plan. The GV expansion system shall be tested and demonstrate to the Government that the system is fully operational, and meets or exceeds the specified requirements and that the system is fully ready to be placed into service. The detailed test plan and cut over plan shall be provided in the technical proposal. The test plan and cutover plan will be reviewed and approved by the government before installation and testing. These tests shall be accomplished prior to the system being placed into service IAW CDRL A005.
3.2.29 Acceptance/Installation Test Report. The Contractor shall provide an installation test report of the results of the testing accomplished under the installation test plan IAW CDRL A006
3.2.30 Cutover Plan. The Contractor shall provide a detailed cutover plan and schedule to delineate how the transition shall be implemented to minimize or avoid the existing GV system operations down time. This plan shall outline how the system shall be placed into service and clearly specify how the newly installed systems shall connect to the existing base systems IAW
CDRL A005.
3.2.31 Testing Requirements. The Contractor shall furnish all test equipment and qualified personnel required to conduct all required testing. The Contractor shall document all test results in a “Test Report(s)” and submit to local 423 CS/SCOI/SCXP, 38 ES/ENPO within five (5) business days of completion of each test. During any testing phase, the Government reserves the right to perform any of the Contractor performed inspections and tests to assure solutions conform to prescribed requirements. The Contractor shall provide on-site support during the acceptance testing IAW CDRL A006.
3.2.32 Fiber Optic Tests. BT FEDERAL shall test the outdoor fiber optic cables for
RAF Molesworth, UK 15 continuity, opens, decibel loss, faults and transposed pairs. The Contractor, BT FEDERAL and 423 CS/SCOI/SCXP shall jointly test the fiber transmit and receive communications signals from the Central Control Stations to the SCU. Test (or TESTS) shall be accomplished to ensure the GV expansion system with BT FEDERAL FOC have good fiber link communications signals. The Contractor shall include the FOC test results from BT FEDERAL in the test report.
3.2.33 Optical Attenuation. BT FEDERAL shall conduct the end to end attenuation tests on all fiber optic cable strands. Test (or TESTS) shall be accomplished to ensure the installed cable is within the specified parameters. The bi-directional optical power meter method or Optical Time-Domain Reflectometer (OTDR) or equivalent shall be used to perform this test.
3.2.34 Final Acceptance. The Contractor shall schedule a final project walk-through and complete a system test of all work completed prior to close out with the Government representative from 423 CS/SCOI/SCXP and the CO. This should be scheduled at least five (5) business days prior to the acceptance. The Contractor shall perform testing and inspections of the GV expansion systems IAW the approved test plan and cutover plan. When any system, subsystem, component or requirement test fails to meet the requirements of the test, Government acceptance will be withheld until such time as the cause of the failure is corrected to the Government’s satisfaction. After appropriate corrective action has been taken, all tests including those previously completed related to the failed test and the corrective action shall be repeated and successfully completed prior to Government acceptance IAW CDRL A005 and
CDRL A006.
4.1 GENERAL INFORMATION
4.2 Period of Performance. The period of performance for this project will be determined by the successful Contractor bid, but should not exceed 180 days after date of contract. All work including installation, training, testing, and acceptance must be completed with this timeframe.
4.3 Place of Performance. The place of performance is RAF Molesworth, UK.
4.4 Hours of Operation. The Contractor shall perform the work required under this contract during normal duty hours of the facility where work is being performed. At RAF Molesworth, UK. Normal duty hours are: 0730 – 1630 UTC. Any other work schedule outside of normal duty hours requires 423 CS/SCOI/SCXP and CO approval. If an escort is required, the start time will be 0700 at main gate as the escort section only works are 0730 – 1630. The Contractor shall not perform work under this contract on US or UK Federal/bank holidays or site-unique down-days unless expressly authorized by the CO.
Part or all of the facility may be occupied during this effort. The Contractor shall accomplish the installation with minimum disruption of daily office activities. If performance of work outside normal duty hours will be required to meet the scheduled dates stated above, include desired working hours in the proposal.
4.5 Base Support. Laydown and dry storage areas will be provided upon request. The
RAF Molesworth, UK 16
Contractor shall request the amount of storage in their proposal and secure this area if needed. If the base cannot provide the request area, the Contractor will be required to find another area.
5.0 GOVERNMENT FURNISHED EQUIPMENT/STANDARDS/ DELIVERABLES
5.1 Government Applicable Documents and Standards. The Contractor shall comply with these documents during the performance of this contract. The Contractor and BT FEDERAL shall obtain and comply with any other applicable manuals not identified in this SOO that would be required to meet industry standards.
UFC 4-021-01; 9 Apr 2008, change 1, Jan 2010 - Design and O &M: Mass Notification Systems. UFC 4-010-01/02 - Minimum Antiterrorism Standard for Buildings.
AFI 10-2501 - AF Emergency Management Program Planning and Operations. Executive Order 13407, 28 Jun 2006 - National Public Alert and Warning System.
Secretary of Defense Memorandum: Final Recommendations of the Ft Hood Follow-On Review, 18 Aug 2010.
DoDI 6055-17, 13 Jan 2009 - DoD Installation Emergency Management (IEM) program Incorporating change 1, Feb 13, 2017.
Secretary of Defense Memorandum: Force Protection Recommendations Following the Chattanooga Shooting, 29 Jul 2015.
Air Force Emergency Mass Notification System (EMNS) Concept of Operations (CONOPS).
AFI 10-206, Operational Reporting Chapter 8 Emergency Mass Notification System (EMNS), dated21 July 2016.
AFI 17-210_AFGM2018-01 Attachment 1, paragraph 1.4.3. AF Guidance Memorandum to AFI 17- 210, Radio Management.
OSHA CFR 29 Part 1910-268 - (2013) Telecommunications.
REA TE&CM 701/PC-5A - Rural Electrification Administration (REA). REA TE&CM 643 Form 515C - Rural Electrification Administration (REA).
NEMA TC 2-2013 - Electrical Polyvinyl Chloride (PVC) Tubing and Conduit.
ANSI/TIA/EIA-568-D - (2001) Commercial Building Telecommunications (568B-1, 568B-2, 568B- 3) Cabling Standard.
ANSI/TIA/EIA-569-D - (1998) Commercial Building Standard for Telecommunications Pathways and Spaces.
ANSI/TIA/EIA-606-B - (2011) Administration Standard for the Telecommunications Infrastructure of Commercial Buildings.
ANSI/TIA/EIA-607-B - (1994) Commercial Building Grounding and Bonding Regulation for Telecommunications.
ANSI/EIA-310-D - Cabinets, Racks, Panels, and Associated Equipment.
BICSI TDM Manual - (1998) Building Industries Consulting Services International Telecommunications Distribution Methods (TDM) Manual.
RUS Bulletin 1751F-640 - Design of Buried Plant-Physical Consideration. RUS Bulletin 1751F- 641 - Construction of Buried Plant.
RUS Bulletin 1751F-643 - Underground Plant Design.
RUS Bulletin 1751F-644 - Underground Plant Construction Telecommunications Engineering Shield.
RAF Molesworth, UK 17
Continuity and Construction Manual (TE&CM) 451.2 RUS Bulletin 345-65 (PE-33) - RUS Specification for Shield Bonding Connectors RUS Bulletin 345-54 (PE-52) - RUS Specification for Telephone Cable Splicing Connectors RUS Bulletin 345-72 (PE-74) - RUS Specification for Filled Splice Closures RUS Bulletin 345-150 (515a) - Specifications and Drawings for Construction of Direct Buried Plant RUS Bulletin 345-152 (515d) - Specifications and Drawings for Underground Cable Installation Electronics Industry Alliance EIA-310-D - Cabinets, Racks, Panels, and Associated Equipment ANSI/TIA/EIA-758B - Outside Plant Telecommunication Cabling Regulation.
ANSI/TIA/EIA-606B - Administration Regulation for Commercial Telecommunication Regulation Standard (PVC) Tubing and Conduit.
NFPA 70 - (2017) National Electric Code. NFPA 72 - (2016) National Fire Alarm Code. AFI 33-203 - Emission Security.
AFI 91-203, Chapter 23 - Air Force Consolidated Occupational Safety Instruction.
Unified Facilities Code (UFC) 3-520-01 (2015), Interior Electrical Systems; Engineering Technical Letter.
(ETL) 11-29 (2011), Use of Light-Emitting Diode (LED) Fixtures in Airfield. Lighting Systems on Air Force Installations and Enduring/Contingency Location UFC 3-560-01 (2006), Electrical Safety, O&M; UFC 3-535-01 (2005).
Visual Air Navigation Facilities.
NFPA 70E, Standard for Electrical Safety in the Work Place. Molesworth, UK Electrical Standards. UFC 3-520-01 Low Voltage Requirements.
UFC 3-580-01 Telecommunications Interior Infrastructure Planning and Design 1 Jun 2016, change 1, 1 Jun 2016.
Molesworth, UK Instruction 32-2001 - Fire Emergency Services Program International Building Codes (IBC) of 2012.
Molesworth JSP375 Safety Rules and Procedures.
5.2 List of Deliverables. All deliverables are subject to Government acceptance and approval.
They shall meet professional standards and the requirements set forth in this SOO. All deliverables shall be produced using recommended software tools/versions as accepted by the Government. The Contractor shall submit the following deliverables:
CDRL Data Item Data Item Title A001 As-Built DI-DRPR-80151A/T
A002 Work Schedule DI-MISC-81382/T
A003 Status Reports DI-MGMT-80368A
A004 Meeting Minutes DI-ADMIN-81505/T
RAF Molesworth, UK 18
A005 Test Plan & Cutover DI-NDTI-80566A/T
A006 Acceptance/Test Report DI-QCIC-80512
ATTACHMENTS: Required Forms that the Contractor shall need to complete in order to work on base.
5.1.1 Skilled Person Electrical Application
5.1.2 Example DIO Form 29
5.1.3 Example DIO Form 2597
D I O
20150909 - Original DIO Form 2597.doc
Skilled Person Electrical Application.p
| 2.0 REQUIREMENTS |
| 2.2 Security Requirements |
| 2.2.1 Secure Areas. Some of this work will take place in secure areas where |
| Contractor employees must be employees escorted at all times. The Contractor must coordinate access to secure areas at least ten (10) business days ahead of time. It is the Government's responsibility to provide escorts. The Con... |
| 2.7 Contractor Personnel |
| 2.7.1 Project Management. The Contractor shall designate a Project Manager (PM) and alternate(s) Project Manager to be responsible for contract performance and continuity. The Contractor shall identify the scope of authority of the Project... |
| 2.7.3 Enterprise-Wide Contractor Manpower Reporting Application (BetaSAM.gov) |
| 3.0 SPECIFIC REQUIREMENTS |
| Table 1. The Proposed New GV Pole Locations, Fiber Optic Cables and Power Requirements |
| 3.1 Installation Requirements. |
| 4.1 GENERAL INFORMATION |
| 5.0 GOVERNMENT FURNISHED EQUIPMENT/STANDARDS/ DELIVERABLES |