This document is a set of questions and answers related to a Request for Information (RFI) for a federal contract opportunity to construct living facilities on Chabelley Airfield in Djibouti. The RFI provides clarification on various aspects of the Statement of Work (SOW), including requirements for seismic design, HVAC systems, electrical and communications infrastructure, and construction materials. Key details include:
The solicitation is for the construction of multiple living facilities, divided into a main body of work and a bid option. Offerors must submit a separate section addressing the bid option, which may or may not be included in the final award. The magnitude of the project is between $1,000,000 and $5,000,000. Proposals are due on the date listed in the solicitation, with questions due by 05 September 2024. A site visit will be held on 31 August 2024. Offerors performing work in the AFRICOM AOR must be registered in the Joint Contingency Contracting System (JCCS) and have an Acceptable status.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA542224R0013 – Construct LSA Living Facilities RFIs
1. Please confirm no payment or performance bonds are required. Box 12 of SF 1442 is checked Not Required, but Box 18 states " "The offeror agrees to furnish any required performance and payment bonds."
Answer: Correct, no payment or performance bonds are required.
2. On page 26 of the RFP under the Clause "(2) PART II - PAST PERFORMANCE", there is a conflict for projects to be submitted whether they must have been completed within 5 or 3 years from the date of the RFP. Can you please clarify. See RFP clauses below.
i. Definitions:
2. RECENT: To be recent, the effort must be on going or must have been performed during the past __5__years from the date of issuance of this solicitation
b. The offeror should complete a separate FACTS Sheet, using roughly the format provided below for a maximum of four (4) active or completed contract (with at least one year of performance history) in the past three (3) years from the issuance date of the RFP, that the offeror considers relevant in demonstrating its ability to perform the proposed effort.
Answer: Apologies on the conflict, past performance must have been completed within 5 years from the date of the RFP to be considered recent.
3. Reference to Attachment 3 - CADJ Drawing GROUND FLOOR PLAN, states that “The bathroom will be removed for construction in Djibouti and the comm, janitorial and electrical rooms will be moved to the space occupied by room 7”.We noticed that the Statement of Work does not include any Plumbing requirements for this project.
Please confirm if the billeting facilities will be exclusively for bedrooms with no consideration for toilet and bath spaces, or if we should allocate a partitioned space for a potential toilet and bath to be constructed by others?
Answer: The spaces are exclusively for billeting. There are still requirements for communications, janitorial, and electrical rooms.
4. Reference to Attachment 3 - CADJ Drawing GROUND FLOOR PLAN, states that “The building will be narrowed at room 7 to accommodate only the required width of the room for the addition of the comm, electrical, and janitorial spaces. Room 15, which will also be narrowed in this process will be converted into a hallway with a door leading to the outside, creating a third entrance facility”.
Since the two opposite rooms will be narrowed, could you please confirm if the width of each bedroom can be adjusted equally to distribute the remaining space?
Answer: The width of the facility shall be reduced to eliminate the extra space. Each dorm room shall be constructed per the provided designs. In other words, the facility should be slightly shorter than 45620 mm wide.
5. Reference to Attachment 3 - CADJ Drawing SECTION DETAILS, the drawing indicate that the roof should have a sandwich panel with a minimum thickness of 100+26mm and an R-value of at least R30, while the exterior walls should have a 50mm sandwich panel.
Please advise the required type, thickness and R-value of the insulation for the roof and wall panels.
Answer: R-30 for roof. Per sheet A10, R25 for external walls.
6. Reference to Statement of Work, item 4.3.2.1.3 Seismic: Based on seismic conditions for Djibouti, as specified in ASCE Seismic Design Criteria and UFC 1-200-01.
We have conducted research on the Seismic conditions for Djibouti in accordance with ASCE Seismic Design Criteria and UFC 1-200-01 and found the following criteria.
Seismic Design Consideration:
Ss =102.0%, S1 = 41.0%, Site Class = D, Seismic Importance Factor = 1.0 Building Risk/Occupancy Category: II (Standard Occupancy Structure) Please confirm if the seismic design criteria above are correct.
Answer: Part of the contract is for the contractor to be responsible for appropriately designing the structural design of the facility to weather seismic activity as dictated by building codes.
7. Are there gypsum ceiling throughout rooms and corridors? SOW mentions selection of ACT tile?
Answer: Per the SOW, the contractor shall submit ceiling tiles for approval in the bid submission. Reference sheet A11 for ceiling finishes.
8. What are the floor finishes throughout?
Answer: Reference sheet A11 for floor finishes.
9. SOW defines USA voltages to be used 120v/208v 60hz, drawings show split units to be 230v – please clarify.
Answer: This project is based off of another construction project in a location using 230v power. Chabelley uses 120v/208v 60 Hz power, so this is still the requirement for this project.
10. Sow mentions comms in corridors, what are the comms requirements for the rooms?
Answer: See Sheet E10 in the attached designs.
11. What are the electrical outlet requirements for each living quarter? Quantity and spacing?
Answer: See sheet E03 and E01 in the attached designs.
12. Fire alarm system – please advise if is required to be mass notification or fire only Answer: Only fire alarm, however the speakers are required to have open communications connections to allow the mass notification to be place within the facility.
13. Reference to Attachment 3 - CADJ Drawing GROUND FLOOR PLAN, states that “The bathroom will be removed for construction in Djibouti and the comm, janitorial and electrical rooms will be moved to the space occupied by room 7. The building will be narrowed at room 7 to accommodate only the required width of the room for the addition of the comm, electrical, and janitorial spaces. Room 15, which will also be narrowed in this process will be converted into a hallway with a door leading to the outside, creating a third entrance facility”.
Please confirm if the below orientation described in the above statement is acceptable.
Answer: Yes, that meets the intent.
14. Reference to Statement of work item. 4.5.7.7. states that “All interior wiring & cabling shall be installed in EMT conduit systems concealed in finished spaces (i.e. the office area) in walls or chase or above ceiling unless noted otherwise. Is it mandatory to enclose all electrical cables, conduits, and fittings, or is it acceptable to surface mount wiring and cabling installed in EMT conduits, provided that international codes and standards are respected.
Answer: This section of the SOW is valid. Unless specified otherwise in the SOW, all cables, conduits, and fittings shall be enclosed.
15. Reference to Statement of Work, Section 4.2 Civil, 4.2.4 states “The Contractor shall connect each facility to the nearest electrical and telecommunication utility. For electrical, the Contractor shall be responsible for bringing all electrical connections to the electrical room as shown on the design drawings.” Please provide location/distance of the nearest electrical and telecommunication utility.
Answer: See attached drawings
16. Reference to Section 4.2.8. Concrete, 4.2.8.4 states “The Contractor shall place a 1.2m x 3.65m concrete pad at all exterior doors to include exterior communication and electrical doors. The Contractor shall also place concrete pads for all exterior HVAC split units.” However, in Section 4.4.1. Split Unit (ductless), 4.4.1.3 states, “The outside portion of the split unit shall be installed on a minimum of 610mm high stands. The stand shall be fabricated with 50.8 mm x 50.8mm x 6.35 mm angle iron, sand blasted, primed and painted. The contractor shall submit the split unit stand as a material submittal.” Please confirm if exterior HVAC split units shall be placed in concrete pads or in fabricated high stands.
Answer: Refer to sheet M01 in the attached designs.
17. Reference to Atch 3. CADJ Drawing, Sheet No. A03, drawing legend states “13A, 250V, Single Socket Switched Outlet, IP55” Please confirm if switched outlet is IP55 and not IP65.
Answer: That is correct, it should be an IP65.
18. Reference to Statement of Work, Page 9 of 24, Section 4.5.6 Exterior Power Distribution states that “The main entrance service 120/208V for the facility should be supplied by an existing service feeder provided by others. That feeder is running from a dedicated circuit breaker located at existing distribution substation to the facility location. The contractor should test & protect that service feeder and extend it if required to be tied into the main disconnect of the facility”. Kindly provide the details of existing service feeder (size & type of cable and method of installation) and the additional distance to be considered to tie into the main service entrance for all the buildings in base and option bid.
Answer: Refer to the attached site sheet and the SDC spec sheet.
19. Reference to Statement of Work, Page 16 of 24, Section 4.6.2 Outside Plant states that “MHDS (Man Hole/Duct System) is coordinated with communication sections & CO for purchase. Will the KTR be responsible for the design, supply, and installation of the MHDS system with OSP cables? If yes, please provide a site layout that includes the existing telecom manhole/handhole/cable vault, along with the available fiber optic and copper cables.
Answer: Refer to the attached site map
20. Reference to Statement of Work, Page 7 of 24, 4.4. Heating Ventilation & Air Conditioning (HVAC). There is no reference on the refrigerant gas mentioned in the RFP document provided. Please confirm that the refrigerant gas to be used for the proposed AC unit will be ozone-friendly, such as R410a or R32.
Answer: Yes, use R410a
21. We are preparing a 15% design package for our bid submission. As per the SOW document, “The Contractor shall submit a 15% design with their bid package. The submittal and all subsequent plans shall be IAW EDRC\ITL TR-19-7 and shall include but are not limited to: site survey, site plan, demolition plan, grading plan, and construction plan. All design submittals shall include a Design Analysis. The Contractor shall provide two (2) sets of design files, one (1) compatible with AutoCAD 2023 and one (1) in Portable Document Format (PDF) format. All materials and documents supplied to the Government shall be the sole property of the Government. Please advise on the following two items:
- No topographic survey or geotechnical report was included with the RFP. Can you please provide this so we can complete our initial design documents and construction cost estimates?
- For design drawings to be submitted in the Technical Approach, please confirm if you would like them in PDF or CADD?
Answer: At this time we do not have a topographical survey. Please submit design in PDF format. When the 100% design is submitted, submit the CAD Drawing as well.
22. Please advise what holidays should be included in our schedule as nothing was provided in the SOW or Solicitation.
Answer: The work schedule does not need to specifically take into account holidays.
23. As per the SOW clause 1.2, It is mentioned that there are some existing structures which will be demolished before the start of the construction. Please provide the details that what type of structure they are and are there any utilities that have to be shifted.
Answer: Wooden structures. Transformers in the way will need to be relocated.
24. As per the SOW caluse 1.2.1, Do we have to pause the work after getting the acceptance document of the first facility or after the completion of work and handing over the facility to the government.
Answer: After handing over the facility to the government. The intent is for the government to move into each group of facilities as they are completed to maintain livable space at Chabelley.
25. As per the SOW 2.1, It is mentioned that we have to construct a concrete slab on the graded surface, Do we have to construct this concrete slab on the whole area of 45.7x12.2 meters or at the base of the walls only where we have to anchor the vertical members of the facility structure.
Answer: Reference sheets ST01-ST04 for concrete requirements.
26. As per the SOW 2.1, It is mentioned that we have to construct end walls, sandwich panel siding and roofing structure. Do we have to make the main load bearing structure including the beams and columns with concrete or structural steel. Also the design and details of the same has not been provided in the bid documents therefore will the design of the structural frame is in the contractor's scope?
Answer: See sheet A06 on the full designs for material selections.
27. As per the SOW caluse 2.6, It is mentioed to locate all the utilities in the area of the construction and accomodating or modifing them. Is there any utility plan available mentioning the utilities available in the construction area that might be relocated.
Answer: Please see the site map provided.
28. As per the SOW clause 3.3, Will the waste disposal site for the debris accumulated by the demolition of the existing structures be specified by the client?
Answer: Waste disposal off of the installation is the responsibility of the contractor. If the contractor needs a site to dispose waste temporarily before taking it off of the installation, that space needs to be requested with the laydown area request. This will part of the contractor bid.
29. As per the SOW clause 4.1.2, and the drawings attached, the exterior and interior walls are made up of sandwich panels and gypsum board partition but the main load bearing structure details are not provided. Please clarify?
Answer: Reference sheet ST04. Light gauge steel construction with 600mm on center spacing.
30. As per the SOW clause 4.1.2.3, it is mentioen to construct the inner walls to achieve STC 40 or equivalent sound rating. Do we have to provide the test certificates for the sound rating. Also for sound proofing the doors of the internal quarters have to be aucoustic while in clause 4.1.3.1, it is mentioned that the doors will be made up of metal with metals frame. Please clarify?
Answer: Test certificates are not required, however STC 40 doors are required.
31. Please confirm that the ceiling will be constructed by gypsum board of size 600x600 mm as mentioned in the drawings provide in the bid documents.
Answer: Yes, 600x600 mm gypsum ceiling tiles. Reference sheet A11 for ceiling finishes.
32. DO we have to provide all the doors i.e. exterior and interior doors faire rated or only the internal doors fire rated and outer doors as normal MS doors. Also, Do we have to provide the fire rated doors with the panic bar?
Answer: Follow the door schedule on sheet A09. Please note the locks for interior doors mentioned in the SOW supersede the locks for D2 on sheet A09.
33. As per the SOW clause 4.1.3.5, the clause says " All doors to interior doors to living quarters shall have a minimum of 1 hour fire resistance rating". Please clarify that all doors have to be fire resistance or only the interior doors of the living quarters. Also, Do we have to provide a fire rating certificate as well.
Answer: Refer to the door schedule on sheet A09.
34. As per the SOW clause 4.1.5, we have to provide the metal sign on the facility denoting the building number. Please provide the size of the metals sign that have to be provided.
Answer: The external sign is the responsibility of our maintenance contract. As such, this section is no longer required for the contract.
35. As per the SOW clause 4.2.1, It is mentioned to modify the utility and utility services. Kindly clarify what type of utilities are there and the construction of the concrete pad is for what work.
Answer: Refer to sheets ST01-ST04 for concrete requirements. See the attached site map for the utilities information.
36. As per the SOW clause 4.2.3.1, please provide the as built drawings mentioned in the SOW.
Answer: Attached
37. As per the SOW clause 4.3.1, It is mentioned that we have to provide the structural review of the facilities and design for the installation of the end walls and sandwich panels and roofing structure. Does the design of the main load bearing super structure is also in the contractors scope.
Answer: The contractor is responsible for the final product that is constructed. As such, the contractor shall review the designs and clearly note any changes that should be made in their bid submission. Reference sheet ST04 for more details on the provided design.
38. Please confirm that the super structure will be designed and constructed of the structural steel as per the given loads, wind and seismic conditions.
Answer: The super structure is structural steel and the individual walls are light gauge steel framed.
39. Do we have to construct the facility with the wall framing members or we have to design the structural steel framed structure and the provide the end and interior wall with wall framing members and sandwich panels.
Answer: See sheet A06.
40. As per the SOW, It is mentioned to provide the structural design for the facility, Structural calculations for the design of the foundation and roofing plan. The supply, installation and construction of the facility was not mentioed in the SOW. Therefore do we have to provide only the design or also execute and construct the facility as per the design provided after the approval from the client.
Answer: The contract is for the construction of the facility. A set of construction plans from another project are being provided, and shall be followed to the max extent possible. The Contractor is still responsible for the final design and product, and as such shall note any necessary changes to the designs.
41. Do we have to provide the roofing with the insulated panel or by simple sheeting. Also, if we have to provide the roofing with insulated sandwich panels, please suggest the thickness of the roofing panels.
Answer: See Sheet A06 on the drawing designs.
42. As per the drawings provided, It is mentioned that the bathrooms will be removed from the plan so should we replace the bathroom, toilet area with the rooms and where will be the toilet, shower area will be constructed. Also Please provide the details for the toilets and showers i.e. how many numbers of the same are required. Please clarify?
Answer: There are no plumbing or bathrooms to be constructed in this project. In the space opened up by removing bathrooms, the contractor shall install more dorm rooms.
43. Kindly provide the details for the flooring and floor finishing. What type of flooring we have to provide?
Answer: Refer to sheet A13 on the attached designs.
44. Kindly provide the details of the windows to be provided on the exterior walls and mentioning the material and type of the windows to be used.
Answer: Refer to the window schedule on sheet A09.
45. Kindly provide the details and size of the interior door to be provided for the living quarters Answer: Refer to sheet A09.
46. What would be the distance between the SDC & the new facility?
Answer: Refer to the attached site map.
47. Please provide the BTU or capacity of the split ac unit required here.
Answer: Each split unit shall be a 1 ton unit.
48. Please confirm all the ac units to be provided is split units and not duct units.
Answer: Correct
49. Please confirm that the ceiling we have to provide is the acoustic grid ceiling or normal gypsum board ceiling.
Answer: Refer to sheet A07
50. Where would be the fire alarm system connected to?
Answer: Refer to page E09-1
51. Please provide distances between each facilities Answer: Refer to the attached site plan.
52. The EMT pipe for the inner wiring of the facility to be concealed or exposed?
Answer: Concealed
53. Please, confirm that the design needs to be as similar as possible to the drawings provided (room size, windows size and position, doors position.)
Answer: Correct. Other than moving the Janitor, Comm, and Electrical room and removing all plumbing, the design will match the provided design to the fullest extent. If the contractor identifies changes that would improve the design or decrease price that is permissible provided the contractor clearly defines the deviations. Additionally, in such situations the Government reserves the right to require the original design specs.
54. Please, provide the quantity of rooms to provide in each building. Following the drwgs received, we understand 24 rooms are to be provided, room`s dimension as per drawings A01.
Answer: Correct. Place the third entrance between rooms 14 and 15, the mechanical/janitor/comm space between rooms 6 and 7, and remove rooms 13 and 21.
55. Please, provide floor specifications.
Answer: This question is already answered in the document.
56. Please, provide windows specifications Answer: This question is already provided in the document.
57. Please, provide A/C specifications Answer: Refer to sheet M01.
58. Please, confirm furniture are excluded from this SOW Answer: Correct
59. Please, let us know where the nearest point of connection is, for the electrical utility Answer: Refer to attached site plan.
60. Please, let us know where the nearest point of connection is, for the communication utility Answer: Refer to attached site plan.
61. Offeror requests the Government to consider extending the proposal due date of 10 days to have sufficient time to collect quotations from suppliers/subcontractors and submit a compliant proposal.
Answer: At this time, proposal timelines will not be extended.