Combined Synopsis Solicitation:
DINING HALL FACILITY
This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation;
submissions are being requested and a written solicitation will not be issued.
(ii) The Solicitation Number is: FA542220Q3013
(iii) The solicitation document and incorporated provisions and clauses are those in effect through the following:
Federal Acquisition Circular (FAC): 2020-05 30-Mar-20
DFARS Publication Notice (DPN): 20200408 08-Apr-20
Air Force Federal Acquisition Circular (AFAC): 20191001 01-Oct-19
Size Standard:(iv) NAICS code: 236220
This is a(n) 100% unrestricted, full and open solicitation.
The corresponding index entry is:
(v) Please see attached Pricing Schedule for a list of contract line item number(s) and items, quantities and units of measure, (including option(s), if applicable).
(vi) Description of the Requirement:
The Contractor shall design and construct a semi-permanent facility or pre-engineered building intended for use as the main serving and seating area for the installation’s dining hall.
(vii) Period of Performance or Delivery Date can be found on the Pricing Schedule.
The FOB point is: Destination
Place of Performance ---or---
Delivery Address
Camp Lemonnier, Djibouti, Africa Chabelley Airfield, Djibouti, Africa
(viii) FAR 52.212-1 Instructions to Offerors -- Commercial Items is hereby incorporated by reference, with the same force and effect as if it were given in full text. In addition to any addendum provided via attachment to this Solicitation, all terms and conditions of FAR 52.212-1 remain in effect.
March 2020
(ix) FAR 52.212-2 Evaluation -- Commercial Items this provision has been tailored to this procurement and is provided via attachment to this Solicitation.
October 2014
(x) Each offeror shall ensure the provision at FAR 52.212-3 including its Alternate I, Vendors Representations and Certifications--Commercial Items are updated at www.sam.gov. Failure to obtain SAM registration MAY result in submissions not being considered for award.
October 2018
(xi) The clause at FAR 52.212-4, Contract Terms and Conditions – Commercial Items is hereby incorporated by reference, with the same force and effect as if it were given in full text.
October 2018
(xii) The clause at FAR 52.212-5, Contract Terms and Conditions Required To Implement Statutes Or Executive Orders
– Commercial Items is hereby incorporated by reference, with the same force and effect as if it were given in full text. All provisions and clauses can be found in the Attachments.
March 2020
(xiii) If any warranties are required beyond those customarily provided on a procurement of this nature, they will be specifically mentioned in the Pricing Schedule located within the Attachments.
(xiv) Defense Priorities and Allocations System (DPAS): N/A
(xv) Questions are due by: Monday, June 8, 2020 11:00 AM EAT
$39.5M
Prefabricated commercial building erection
Offers are due: Monday, June 22, 2020 11:00 AM EAT
(xvi) The POC for this solicitation is listed below, all responses, questions and submissions shall be sent to the designee listed below:
POC email: francoise.m.douala.mil@mail.mil
POC Mailing Address: PSC 831 Box 67
FPO, AE 09363
POC Name: Francoise Douala
POC phone: 253-77-077-339
List of Attachments:
Attachment
Number Name of Attachment Attachment
DatePages
1 Pricing Schedule Template 20-May-20
2 PWS
20-May-20
3 Attachment 1: Construction Specifications for CADJ 20-0004
20-May-20
4 Attachment 2: Site Plans / Facility Drawings 20-May-20
5 Attachment 3: AF Form 66, Schedule of Materials Submittals 20-May-20
6 Clauses
20-May-20
Signature
Delivery Date or Period of Performance: ___________________
DUNS:
Printed Name Title
NOTE: The individual signing must have signatory authority for this Entity; signature constitutes agreement to all terms and conditions contained within this solicitation.
CAGE:
Is SAM.gov registration current?
Yes No Unsure
Date
Default NET Terms: 30 Days. List any discount terms offered with pricing.
Pricing Schedule Template FA5422-20-Q-3013Sol. No.
Line Item Description Unit PriceUIQTY Extended Price
Total Price
Submission Expiration: Vendors may, at their discretion provide additional time; however, all submissions must remain valid for at least days after this solicitation closes.30 Expiration Date:
Small Large Woman-Owned Veteran-Owned OtherBusiness Size (select all that apply):
DEPARTMENT OF THE AIR FORCE
776th EXPEDITIONARY AIR BASE SQUADRON
UNITED STATES AIR FORCE
PERFORMANCE WORK STATEMENT
FOR
CONSTRUCT DINING HALL
CADJ 20-0004
CHABELLEY AIRFIELD
8 APR 2020
TABLE OF CONTENTS
Section 1 – General Requirements
Section 2 – Technical Requirements
Section 3 – Attachment 1 – Construction Specifications for CADJ 20-0004
Attachment 2 – Site Plans / Facility Drawings
Attachment 3 – AF Form 66, Schedule of Materials Submittals
SECTION 1
GENERAL REQUIREMENTS
1 SUMMARY OF NEED: The Contractor shall be required to design and construct a semi-permanent facility or pre-engineered building intended for use as the main serving and seating area for the installation’s dining hall. Work to be performed is specified in this Statement of Work, Specifications, Drawings and AF Form 66.
1.1.1 All specified equipment and tasks to be performed shall be at the request of the Contracting Officer (CO), or an authorized Contracting Officer Representative (COR). All work shall be in accordance with terms, conditions, and specifications below. All work will be ordered and directed by the CO in accordance with the Statement of Work, and shall be accomplished within the times specified for each task. The COR has no authority to make any commitments or changes that affect price, quality, quantity, delivery, or other terms and conditions of the contract nor in any way direct the contractor or its subcontractors to operate in conflict with the contract terms and conditions.
1.2 SITING: Location at Chabelley Airfield as depicted in Attachment 2 (Site Plans/Facility Drawings).
1.3 GOVERNMENT PERIOD OF PERFORMANCE: The Government Performance Period to complete all work is 275 calendar days from the Notice to Proceed (NTP). Design performance period shall be 95 days including 2 – 30 day design periods for the contractor to progress from 30% to 60% and 60% to 90% design.
The Government shall have a 10-day review period at the 60% and 90% design period. The contractor shall have 15 days to finalize 100% drawings at the end of the second government design review period.
1.3.2 The Contractor is required to provide a detailed schedule outlining the major work tasks and durations. The Contractor may request approval of an alternate performance period. The request for alternate performance period shall be made in writing with a hard copy of the Contractor’s proposed construction schedule; this request should include a depiction of days and activities.
1.3.3 Progress payment invoices can be submitted every 30 days and shall be based on the approval of Contractor progress reports provided to the USAF for review every 10 days.
1.4 DEFINITIONS: The following United States Air Force (USAF) terms will or may be encountered by the Contractor during the course of executing this contract and are hereby defined for clarification.
1.4.1. Contracting Officer (CO): The U.S. Government CO. The only person authorized to make changes to this contract for the United States Government or the USAF.
1.4.2. Contracting Officer Representative (COR): A person authorized by the CO to represent the CO for limited specific functions, typically the Construction Manager (CM) or Project Manager (PM), primarily to provide technical interpretations of the contract documents and/or construction documents (plans, specifications, etc.) technical information. The COR does not have the authority to change the contract.
1.4.3. Host Nation: Djibouti.
1.4.4. PWS: Performance Work Statement; a Document that describes the minimum requirements, and the terms and condition by which the contractor shall abide.
1.5 WORK HOURS: Normal work hours at Chabelley Airfield are from 8:00 am to 5:00 pm, Monday through Saturday, excluding holidays. Meetings and inspections shall be scheduled during normal work hours. Access to work sites will not be affected by these hours due to work location. Work hours for this requirement will be finalized at the pre-construction conference.
1.6 DEMOLITION: All salvageable items and material removed from the site shall be returned to the USAF. Serviceability of salvaged items and material shall be determined by the CO or COR. The Contractor shall transport the salvaged items and material to a location to be specified by the CO or COR.
1.7 BASE ACCESS: The Contractor will coordinate with CO and COR upon contract award to secure appointments for biometrics and vetting for access to Chabelley Airfield.
1.8 GOVERNMENT FURNISHED PROPERTY: Not Applicable
1.9 CONTRACTOR FURNISHED PROPERTY: The Contractor shall provide all labor, materials, tools, and equipment, required to fulfill all obligations outlined in the contract and/or construction drawings or specifications. Contractor furnished material and equipment shall be of same quality or better than what’s outlined in the specifications. Any deviation must be requested in writing and approved by the Contracting Office or COR.
1.10 SITE CLEAN UP: The Contractor will remove all waste materials generated by any contract requirement from the project sites to an approved off-base dumpsite on a daily basis and in accordance with all local environmental standards or authority having jurisdiction.
The Contractor is responsible for cleanup of any contractor-caused hazardous material produced at the construction site. In the event of a contractor-caused fuel or hazardous chemical spill, the Contractor shall be responsible for the cleanup at their expense and shall comply with local environmental standards as applicable.
1.11 SPECIAL WORK CONSIDERATIONS: The Contractor must coordinate all construction hours of operations, if outside of the normal work hours, through the appropriate Air Force personnel 72-hours in advance.
All dimensions on provided conceptual drawings are approximations. The Contractor will field verify all dimensions.
1.12 SAFETY: The Contractor shall be responsible for ensuring that all work performed under this contract is accomplished in a safe and proper manner.
The Contractor shall follow all of the applicable Djiboutian Safety and Health Requirements.
The Contractor will instruct his employees on accident prevention and safety. Special emphasis is placed on the safe operation of equipment and safe working conditions. The Contractor will train his employees on the appropriate safety measures and ensure his employees are aware of their obligation to obey existing base safety regulations as pointed out by the CO or COR.
The Contractor will provide the following safety equipment and ensure his workers utilize this equipment appropriately during operations on the job site:
Hard Hats Eye and Ear Protection Steel Toe Boots Work Gloves Ear Protection
1.13 TRAFFIC CONTROL: The Contractor shall provide (when necessary) appropriate traffic control measures to include but not limited to; diversions, signage, roadway striping, barriers and lighting as applicable. All traffic control measures will be properly marked in both English and French languages.
Necessity, or lack thereof, shall be determined by the COR and directed by the CO.
The Contractor shall provide material and install temporary construction roads for traffic diversion as applicable or construction of the project. All traffic diversions will be coordinated with the CO or COR one (1) week prior to installation. All traffic diversions shall be maintained to provide a minimum of 1 lane, 4 meters wide, that is free of ruts, potholes, sinkholes, wash boarding or other similar hazards that present danger to human life or vehicles.
1.14 COOPERATION: There may be other contractors and Air Force personnel working within or near the project area. The Contractor shall make every effort to work in a cooperative manner with other activities in the area. If disputes arise or if in the interest of coordination, the CO or COR may call a construction meeting at any time to clear up issues. Additionally, the Contractor will send his site engineer superintendent to all progress and construction-related meetings. The site engineer superintendent must either be able to speak English or have an English-language interpreter to avoid work delays or miscommunications. The Contractor shall ensure that the on-site manager has authority to bind the Contractor.
1.14.1 GENERAL METHOD OF CONSTRUCTION: Refer to the project drawings, PWS, and specifications.
The Contractor must use appropriately certified individuals to engineer structural steel support structures, foundations, and footings. The systems will be constructed in accordance with the documents as given by the Contractor’s qualified engineer as applicable.
1.14.2 Applicable Codes and Standards: Contractor submittals and work shall be in conformance with United Facilities Criteria (UFC) 1-201-01, Non-Permanent DoD Facilities in Support of Military Operations, and all other applicable building codes. UFCs are downloadable from the Whole Building Design Guide webpage at www.wbdg.org.
1.14.3 Operations: Construction of this project shall not interfere with day-to-day operations of nearby facilities. Unless specified by the CO or COR all other base operational activities supersede construction activities should scheduling conflicts arise.
1.14.4 Conflicts: In all cases where conflicts arise between Drawings, General Requirements, Manufacturer’s Instructions, Notes, Contractor-provided documents, applicable Codes, and this PWS, the more stringent shall apply.
1.14.5 On-site Storage: All materials stored on site will be kept clean, off the ground, and protected from weather, sand and debris. Materials deemed unfit for use by the CO or COR for reasons of contamination, rusting, sun damage, water damage, wind damage, general poor condition, quality, or abuse will be replaced as directed by the CO or COR and at the Contractor’s expense for all work, cost and material required to make the correction.
1.14.6 Quality: All components such as doors, door hardware, fasteners, screens, caps, covers and boxes used for construction will be commercially available products unless otherwise instructed and authorized with written communication from the USAF Contracting Office.
1.14.7 Warranty: The Contractor is responsible for ensuring all electrical, utility, and communications system components have manufacturer’s warranties, individually or collectively, and are free from any defects due to workmanship or defective materials for a period not less than one (1) calendar year from date of government acceptance.
1.14.8 Submittals: The Contractor will submit a project schedule (AF Form 3064) to the Contracting Officer for approval within seven (7) calendar days following the 100% design being finalized. For each facet of construction, the Contractor will submit material catalog data, material samples (AF Form 66), design drawings, and related calculations to the Contracting Officer for approval a minimum of three (3) calendar days prior to procurement of that particular material as specified in the Air Force Form 66. Upon review by the Government, the submittals along with any comments will be returned to the Contractor within three (3) calendar days. The Contractor shall modify the submittals per the Government’s comments and resubmit within three (3) calendar days for final approvals. Upon final approval, the Contractor shall commence with the procurement and construction activity accordingly. The contractor shall not procure any materials prior to approval by the Government.
http://www.wbdg.org/
The Government, according to the AF Form 66, may request catalog Cuts. Catalog cuts are all standard drawings, diagrams, illustrations, brochures, schedules, performance charts and instructions submitted by the Contractor pursuant to the requirements of the PWS to illustrate some portion of the Work(i.e., what material or equipment will be used). Catalog references must be clear and legible and have the proposed items highlighted upon submittal.
The AF Form 3000, Material Approval Submittal (Attachment 4), will be used for every submittal provided by the Contractor to the Government. Any notes, submittals or communications not processed through proper USAF Contracting procedure will not be considered approved. The material, equipment, drawing, or method is not approved for the project until the AF Form 3000 has been signed and processed. This submittal process may require multiple submissions of the same item in order to receive a signed, valid approval.
1.15 NOTICE TO PROCEED: Notice To Proceed (NTP) to start work will not be issued until the pre-construction meeting is complete. The NTP will be issued in writing from the CO and establishes the first day for the period of performance.
Any Dig and Welding Permits must be requested no later than five (5) days prior to any related work.
1.16 DRAWINGS: Attachment 2, for site plan and concept drawings.
1.17 QUALITY ASSURANCE: The Government reserves the right to perform inspections and surveillance to evaluate the Contractor’s compliance to the contract terms and performance of the requirements in the PWS. Given the short timeframe for the period of performance, any perceived failure to deliver any of the services outlined in this PWS will be addressed by the COR with the Contractor as soon as is reasonably possible after the perceived failure is identified.
The Contractor and the COR shall attempt to resolve the deficiency on the spot. However, if the COR and the Contractor cannot resolve the deficiency, the Contractor shall immediately notify the CO in writing (email is acceptable). Furthermore, shall the Contractor believe a deficiency does not exist, or if addressing the deficiency would fundamentally alter the terms of the contract (to include the cost/price), the Contractor shall notify the CO and will not make any changes until receiving further direction from the CO.
1.18 ORGANIZATIONAL CONFLICTS OF INTEREST: The Contractor acknowledges that it is familiar with FAR Subpart 9.5, Organizational and Consultant Conflicts of Interest, and agrees to avoid, neutralize, or mitigate such conflicts of interest in accordance with the principles set forth in the FAR. If the performance requires the Contractor (to include subcontractors) to supply technical support related to systems or projects with which the Contractor is already directly concerned, either by prime or subcontract, the Contractor shall immediately inform the CO. The PWS may be withdrawn if a conflict is found. The Contractor shall not undertake performance of any PWS requirements that requires it to supply technical support regarding such systems until the notice is given, and written consent to proceed is issued by the
CO.
1.19 SITE SUPERVISION: An on-site manager shall be provided by the Contractor and must be on site at all times while work is being conducted. The Contractor shall ensure that the on-site manager has authority to bind the Contractor and can speak and understand English.
END OF SECTION 1
SECTION 2
TECHNICAL REQUIREMENTS
2.1 GENERAL INFORMATION: The Contractor shall provide all labor, materials, tools, and equipment required to complete tasks per the Drawings, General Requirements, Notes and this PWS.
Work includes the following:
Design and construction of foundation, dining hall pre-engineered building or semi-permanent facility, and all utility systems including interior electrical, exterior electrical, mechanical, and communications. Design and construction will be performed as specified in this Performance Work Statement, Specifications, Drawings and AF Form 66.
2.2 DINING HALL
2.2.1 Construct a 17-meter by 31-meter (55 feet by 100 feet) pre-engineered or semi-permanent facility intended for serving and maintaining temperature of pre-made meals and seating a minimum of 200 personnel in accordance with this PWS, specifications, and concept drawings and site plan (Attachment 2).
2.2.2 Design: The Contractor shall submit a 30% facility design with their bid package. The submittal will include a foundation plan, floor plan, structural plan, roofing plan, power plan to include rough-in, and HVAC plan. Two (2) sets of design files will be submitted, one compatible with AutoCAD 2017, and one in PDF format.
2.2.2.1 60%, 90%, and 100% designs shall occur after award. The Contractor shall have up to 30 days for the 60%, and 90%, design milestones. The Government shall have 10 days for each design review and comment period. The Contractor shall have 15 days to finalize 100% drawings.
2.2.2.2 The Contractor Architect-Engineer shall assume full responsibility for quality control of his/her work under this contract.
2.2.2.3 All review comments will be sent via email to the Contractor Architect-Engineer. All review comments require a response from the Contractor Architect-Engineer no later than two (2) calendar days after the comments are sent.
2.2.2.4 Architectural Design Requirements: The Architectural systems models may vary in level of detail or individual elements within a model, but at a minimum must include all features that would be included on a ¼-in to 1-ft, 0-in scaled drawing. Additional minimum requirements are:
• Spaces – The model shall include spaces defining accurate net square footage and net volume per client standard, and holding data for the room finish schedule to include room names and numbers. Include Programmatic Information linked to DD1391 or validated program to verify design space against programmed space. This information will be used to validate area quantities for cost.
• Walls and Curtain Walls - Each wall shall be to the exact height, length, width and ratings to properly reflect wall types. The model(s) shall include all walls, both interior and exterior, and the necessary intelligence to produce the floor plans, sections and elevations.
• Doors, Windows and Louvers – Doors, windows and louvers shall be modeled to represent the actual size, type and location. Doors and windows shall be modeled with the necessary intelligence to produce schedules.
• Roof – The model shall include the roof configuration, drainage system, major penetrations, specialties, and the necessary details to produce the roof plan, building sections and generic wall sections.
• Floors – The floor slab shall be modeled in the structural model and then referenced by the architectural models for each floor.
• Ceilings – All ceilings, including soffits, ceiling heights or other special conditions shall be in the model with the necessary details to produce the reflected ceiling plan, building sections and generic wall sections.
• Vertical Circulation – Represents continuous vertical components (i.e., shafts, stairs, handrails and guardrails). Vertical Circulation elements shall be included with the necessary details to produce plans, elevations and sections.
• Fixtures and Equipment – Represents components for Fixtures/Equipment layout requirements. Shall be included as required with the necessary details to produce plans, elevations and sections.
• Schedules – Provide door, window and room finish schedules from the model indicating the materials and finishes used in the design.
2.2.2.5 Structural Design Requirements: The Structural systems models may vary in level of detail for individual elements within a model, but at a minimum must include all features that would be included on a ¼-in to 1-ft, 0-in. scaled drawing. Additional minimum requirements are:
• Foundations – The model(s) shall include all relevant foundation elements with necessary details to produce the foundation plans and elevations.
• Floor Slabs – The model(s) shall include the structural floor slabs with recesses, curbs, pads and major penetrations.
• Structural Framing – The model(s) shall include all columns, primary and secondary framing members, and bracing for the roof and floor systems (including decks), with necessary details to produce the framing plans and building/wall sections.
2.2.2.6 Mechanical Design Requirements: The Mechanical systems models may vary in level of detail for individual elements within a model, but at a minimum must include all features that would be included on a ¼-in to 1-ft, 0-in. scaled drawing. Additional minimum requirements are:
• HVAC – The model(s) shall include all relevant pieces of heating, ventilating, and air-conditioning equipment.
• Equipment clearances shall be modeled for use in interference management and maintenance access requirements.
2.2.2.7 Electrical/Telecommunications Design Requirements: The Electrical systems models may vary in level of detail or individual elements within a model, but at a minimum must include all features that would be included on a ¼-in to 1-ft, 0-in. scaled drawing. Additional minimum requirements are:
• Interior Electrical / Power and Lighting Model – The model(s) shall include all relevant interior electrical components (i.e. lighting, receptacles special and general-purpose power receptacles, special systems and lighting fixtures) with necessary detail to produce the plans. Cable tray routing will be modeled without detail of cable contents.
• Communications Model – The model(s) shall include all relevant existing and new communications service connections, both above ground and underground with necessary details to produce the plans.
• Conduit larger than 1.5” shall be modeled.
• Exterior Building Lighting Model – The model(s) shall include all relevant locations of proposed exterior lighting with necessary details to produce the plans and elevations.
• Electrical Site Model – The model(s) shall include all relevant existing and proposed support utility lines and equipment required with necessary details to produce the plans.
• Equipment clearances shall be modeled for use in interference management and maintenance access requirements.
2.2.3 Siting: Siting shall be in accordance with the provided site plans (Attachment 2), and coordinated with the CO or COR prior to start of work.
2.2.4 Demolition: Remove existing HESCO barriers to ensure 5-meter standoff from the facility. Remove HESCO in a method approved by the CO or COR.
2.2.5 Grading: All site work will be graded to ensure proper drainage of the entire site and no excess water near the entrances/exits of the facility.
2.2.6 Foundation: The Contractor shall design and construct a reinforced concrete slab, approximately 17 meters by 31 meters, grade beams and foundation as required to support the structure. A registered professional engineer shall perform the design. Calculations and drawings shall be in English, and all dimensions shown on drawings shall be in metric. Structural shop drawings for foundations and pre-engineered building shall be submitted and approved by the Government prior to the start of construction. All concrete used in the building construction shall have a minimum compressive strength of 4500 psi at 28 days. Exposed surfaces shall be troweled to a smooth finish.
The structural design shall be in accordance with UFC 3-320-06A, Concrete Floor Slabs on Grade Subjected to Heavy Loads and the International Building Code.
2.2.6.1 Site-Work: The Contractor shall provide a rough leveled site with a compacted, well-graded, crushed-stone base course in accordance with the design approved by a professional engineer.
The compacted base course shall extend a minimum of .06 m (2 ft.) beyond the edges of the concrete on all sides. The base course shall be compacted to 95% compaction. The Contractor will test the base course for compaction once every 100 SM. The Contractor will provide a statement of the test results to the CO and COR.
2.2.6.2 Backfill, Excavate, and Level: The Contractor shall backfill, excavate, level and compact areas as required to achieve grades as necessary for the concrete pad. All removed material will be left at the site and spread by the Contractor. Once the pad is constructed, a base course (soil or gravel) will be backfilled and graded on all edges of the concrete pad to within 5 cm (2 in) of the top of the concrete. The backfilled material will be used to create a 3:1 sloped shoulder alongside the concrete pad. The CO or COR will approve the final layout.
2.2.6.3 Reinforcement: All reinforcement shall be appropriately placed within the slab in accordance with the design approved by a professional engineer. The Contractor, to the Government for review, shall submit the design for the reinforcement. All review comments shall be resolved prior to the Contractor providing material submittals, ordering materials or commencing construction. The reinforcement shall be free of dirt, oil, paint, grease, mill scale and any loose or thick rust that could impair bonding of the steel with the concrete.
2.2.6.4 Formwork: The Contractor shall do all formwork installation. Forms shall be properly aligned, adequately supported, and mortar tight. The form surfaces shall be smooth and free from irregularities, dents, sags or holes.
2.2.6.5 Vapor Barrier: The Contractor shall place a minimum of 5-mil vapor barrier under the slab on grade. Visqueen or plastic sheeting are acceptable vapor barriers.
2.2.6.6 Placement Restrictions: Concrete shall not be placed when the air temperature is below 7°C (45°F) and falling. Concrete may be placed when the air temperature in the shade is 4°C (40°F) and rising. Concrete exceeding 40°C (100°F) shall be rejected.
2.2.6.7 Transit Time: The maximum allowable time between the initial introduction of water into the mix and depositing the concrete in place shall be 60 minutes, unless a water reducing and retarding admixture has been added to the mix, then the maximum allowable elapsed time shall be 90 minutes. If the above time intervals are exceeded, the Contractor shall cut back the previously placed fresh concrete to a point of full depth concrete and install a doweled construction joint.
2.2.6.8 Protection From Weather: Have available at the site, at all times when concrete placement operations are underway, materials for protection of the surface of the concrete. When rain appears imminent, stop all paving operations and have all available personnel cover the surface of the unhardened concrete with the protective covering.
2.2.6.9 Delivery Certification: A delivery ticket shall be furnished with each batch of concrete delivered to the job site. At a minimum, the delivery ticket shall include the quantities of materials incorporated into the batch and the time of initial introduction of water to the mix. The delivery ticket will be signed and dated by the plant manager or his designee. Upon arrival at the project site, the superintendent or foreman shall record the arrival time, and the time at which the concrete is completely discharged from the truck and sign the delivery ticket. The delivery tickets shall be provided to the Contracting Officer or Project Engineer at the earliest opportunity.
2.2.6.10 Placement: Immediately prior to concrete placement, the forms and base material shall be thoroughly dampened. Concrete shall be distributed on the aggregate base course to such depth that, when consolidated and finished, the slab thickness required by the plans will be obtained at all points and the surface will at no point be below the grade specified for the finished surface, within a tolerance of 2 cm (0.79 in). Deposit the concrete in a manner that will require as little re-handling as possible. Any necessary hand spreading shall be done with shovels or other tools designed for distributing concrete, not rakes. Ensure that workers do not walk in the freshly deposited concrete with earth or other deleterious substances on their boots or shoes.
2.2.6.11 Consolidation: Each layer of concrete shall be consolidated by internal vibrating equipment.
Internal vibration shall be systematically accomplished by inserting the vibrator through the fresh concrete in the layer below at a uniform spacing over the entire area of placement.
2.2.6.12 Broom Finish: A broom finish shall be applied to the concrete pad. This shall be done as soon as the surface will support the broom to provide an even, uniformed non-skid surface finish without removing surface paste and fines. Finished surfaces shall be protected from damage during the construction period.
2.2.6.13 Curing: Begin curing immediately after placement and continue for at least 7 days. All concrete shall be cured and protected from premature drying and extremes in temperature. All concrete shall be completely covered with plastic sheeting that is weighted down to ensure it does not blow away in 48.2 km/hr. (26 knots, 30 mph) winds as soon as the concrete is stable enough to hold the plastic but no greater than 3 hours. The weights shall not be placed on the wet concrete.
Burlap mats shall accomplish moisture for concrete surfaces not in contact with forms. Under this method, cover the surfaces to be cured with burlap mats. Thoroughly saturate the mats with water before placing them. Use mats of such dimensions that as laid they extend to at least 5 cm (2 inches) beyond the edges of the strip of concrete placed. Place and weigh down the mats to cause them to remain in intimate contact with the surface being cured throughout the curing period. Maintain the mats fully moist and in position for the entire curing period. Curing shall continue for a period of seven days.
2.2.6.14 Removal of Forms: Do not remove forms from freshly placed concrete until it has set for at least 12 hours. Remove forms carefully to avoid damage to the slab. The Contractor will be responsible for replacing any damaged concrete.
2.2.6.15 Finishing Formed Surfaces: The Contractor will ensure all fins and loose materials are removed, and all surface defects greater than 5 mm (0.2 in) are filled. All honeycomb areas and other defects shall be repaired. All unsound concrete shall be removed and repaired. All concrete edges, joints, and surfaces will be neat, clean, and aesthetically pleasant (based on a standard articulated by the COR). Portions of concrete or joints that are not aesthetically pleasant will be removed and redone by the Contractor.
2.2.6.16 Joints: The Contractor shall install construction joints and contraction joints.
2.2.6.16.1 Steel Dowels: The Contractor shall install dowels along construction joints as specified in the design approved by a licensed professional engineer. All dowels will be straight, smooth, and free from burrs at the ends. One end of the dowel will be painted and oiled to prevent bonding with the concrete. The opposite end will be secured into existing concrete with epoxy prior to pouring the new concrete.
2.2.6.16.2 Expansion Board: The Contractor shall install expansion board for expansion joints at all cold joint locations as specified in the design approved by a licensed professional engineer.
2.2.6.16.3 Longitudinal Construction Joints: No slab may be more than 6m in width, construct longitudinal construction joints in order to achieve this requirement where concrete construction is more than 6m. Where keyways are required, the Contractor may form them by placing an insert of the proper shape along the inside face of the side form.
2.2.6.16.4 Tie Bar Assemblies: Place deformed steel tie bars at the required depth, parallel to the finished surface, at right angles to the joint, and at the uniform spacing specified in the design. Approved devices capable of preventing displacement prior to placing the concrete shall rigidly support them. Do not paint or coat the bars with any material before placing them in the concrete.
2.2.6.16.5 Transverse Construction Joints: Construct transverse construction joints so that no slab is larger than 6m in length to provide planes of weakness created by sawing a groove in the surface of the hardened concrete. Place the groove perpendicular to the surface of the slab. Ensure that the sawing equipment does not damage the pavement and saw the transverse contraction joints as soon as the pavement has hardened to the degree that tearing and raveling are not excessive and before uncontrolled shrinkage cracking begins. Accomplish the joint sawing in two steps.
Make the initial cut 3mm wide by a depth of at least 1/3 of the pavement thickness, and in general, when the concrete is between 4 and 12 hours old. Make a second saw cut to provide the joint dimensions indicated in the plans, as soon as there is no danger of further raveling. After the final sawing, clean the joint, install the bond breaker, and seal the joint.
2.2.6.16.6 Transverse Expansion Joints: Form transverse expansion joints using preformed joint filler, and provide them with dowel load transfer, in accordance with the details shown in the plans.
Form the joints during the placement of concrete by securely staking a metal bulkhead accurately in place at the joint location or by other methods that will securely brace and support the joint filler. The joint filler shall be 45mm below the finished surface.
2.2.6.16.7 Cleaning Joints: Immediately after sawing contraction joints, remove the resulting slurry with a jet of water under pressure. After flushing, blow out the joints with compressed air. Immediately prior to joint seal installation, clean the joints using compressed air to remove all traces of debris and dust within the joint.
2.2.6.16.8 Sealing Joints: The Contractor shall saw cut surface of construction joints, and seal with self-leveling sealant. The Contractor shall saw cut 5 cm (2 in) contraction joints perpendicular to construction joints within 24 hours of concrete placement. Saw cut joints shall be 0.317 cm (1/8
in) wide. The Contractor shall seal all joints with backer rod and self-leveling joint filler to ensure water tightness. All joint cuts shall be cleaned thoroughly before placing sealant to ensure maximum adhesion. Joint sealant depth should be 1/8 inch below, but not protruding above, finished concrete surface grade.
Seal joints in new pavement before allowing any traffic or construction equipment on the pavement. Complete sealing within 72 hours (weather permitting) of sawing. Fill the joint thoroughly with hot poured sealant, ensuring the sealant is recessed below the pavement surface as required, and control the pouring rate to avoid spilling of sealant onto the adjacent concrete surface. If any spilling of sealant occurs, immediately remove and clean the surplus amount from the concrete surface. Place sealant when the ambient air temperature is 10°C (50°F) or greater.
2.2.6.16.9 Sealant: All interior concrete within the dining facility footprint shall be coated with a durable 2-part epoxy textured coating and seal coat. The Government shall approve these materials and the color scheme.
2.2.6.17 Compressive Strength: 4500 PSI (31.0 MPa) after 28 days. Whenever a test result is outside the specification limits, the concrete shall be removed and replaced. Concrete shall be sulfate resistant. Water-cement ratio should not exceed 0.5. Government inspectors can take concrete cylinder samples during slab placement and test them for compressive strength compliance. The Government can reject concrete that is unsatisfactory during placement. The arithmetic average of any three consecutive strength tests equals or exceeds ƒ’c. No individual strength test falls below ƒ’c by more than 500 PSI (3.45 MPa).
The Contractor shall make a minimum of four concrete cylinders for each concrete pour. One-half of the cylinders shall be tested at 7 days and the remaining cylinders at 28 days. All tests shall be reported to the Contracting Officer via material submittal, as listed on the Material Submittal Schedule.
The Contractor shall take cylinders for every concrete pour and report all compressive strength results to the Government. At a minimum, 7-day and 28-day compressive strengths must be reported to the Government. Slump tests must also be conducted onsite during a concrete pour.
Government inspectors can take concrete cylinder samples during slab placement and test them for compressive strength compliance. Slump tests will also be conducted, slump of 10.16-15.24 cm (4-6 in) is required. The Government can reject concrete that is unsatisfactory during placement.
2.2.6.18 Utility Lines: In the event utility lines are uncovered, the Contractor will bury the cable to a depth of .46 m (18 in).
2.2.6.19 Surface Preparation: After an initial cleaning and before epoxy is applied, any voids, cracks, spalls, and joints must be filled with a concrete crack filler to ensure end product is a smooth surface fee of any defects. Filler must be approved by the CO and COR before using.
2.2.6.19.1 The Contractor shall finish the concrete floor with an epoxy, non-slip type of covering for concrete floors. Epoxy shall be a low-maintenance, commercial grade, water/spill proof, oil resistant, easily cleanable, and be applied in accordance with the manufacturer’s instructions. A minimum of two coats should be applied evenly with an end thickness of at least 10 mils. The finish shall be the color approved by the Government. The Government, before purchase by the contractor, shall approve the brand of epoxy and degreaser.
2.2.6.19.2 Before applying any epoxy, the contactor must ensure the floor is completely clean and free of any dirt, grime, and any oil and/or petroleum products. This will require the use of degreasers and cleaning products designed to remove petroleum products as approved by the Government.
Degreasing and cleaning may take several iterations to ensure floor is oil and dirt free. The Contractor will not apply the first coat of epoxy until floor is inspected and approved by the Government.
2.2.7 Dining Hall: The dining facility shall be designed, and constructed, as shown in Attachment 2, and as described in the PWS. The metal building system shall be the product of a single recognized metal building system manufacturer who has been in the field of manufacturing metal buildings of the size and complexity of this project for a period of no less than 5 years. Factory finished, 26 gauge, metal fascia and roofing panels shall be complete with all accessories and flashing. The roof slope shall be a minimum 1:12, or Manufacturer’s standard. The Contracting Office, in concurrence with Manufacturer’s standard color chips, shall approve color.
2.2.8 Countertops: All counters used for serving in the food prep area will be 762 mm (30 inch) wide, installed stainless steel countertops.
2.2.9 Electrical: The drawings indicate the extent and the general location and arrangement of equipment, conduit, and wiring. The Contractor shall become familiar with all details of the work and verify all dimensions in the field so that the outlets and equipment shall be properly located and readily accessible. Lighting fixtures, outlets, and other equipment and materials shall be located to avoid interference with mechanical or structural features; otherwise, lighting fixtures shall be symmetrically located according to the room arrangement when uniform illumination is required, or asymmetrically located to suit conditions fixed by design. Raceways, junction and outlet boxes, and lighting fixtures shall not be supported from sheet metal roof decks or ceiling grids. Type or function and specific unit number shall permanently mark major items of electrical equipment and major components with an identification name to identify the equipment. All electrical work shall be in accordance with the latest editions of the National Fire Protection Association (NFPA), and the National Electrical Code (NEC), all electrical equipment must be UL© or CE© approved.
2.2.9.1 Power Source: Power characteristics will be 120/208 volts, 60 Hertz.
2.2.9.2 Service Entrance Equipment: The main service entrance equipment shall be a wall mounted panel board, equipped with miniature circuit breakers, and shall conform to the requirements set forth in the International Building Code. The main panels will be located as specified in Attachment 2. A minimum of 30% spare ways shall be provided. The total load on any over-current device located in a panel board shall not exceed 80% of its rating. The panel boards installed shall be equipped with 60-Ampere main circuit breakers.
2.2.9.3 Cables and Wires: Cables and wires shall conform to the requirements set forth in the International Building Code. All conductors shall be copper, and a minimum size of 4.0 mm² if less than 20 Amperes, and 6.0 mm² if less than 30 Amperes.
2.2.9.4 Wiring Methods: Wiring shall consist of insulated conductors installed in raceways and cable trays as permitted by the International Building Code. Wire fill in conduits shall be based on the International Building Code for the type of conduit and wire insulation specified. Conduits shall be installed concealed in finished walls and ceilings.
2.2.9.5 Grounding: The main service equipment shall be grounded. A green equipment-grounding conductor shall be provided regardless of the type of conduit. Equipment grounding bars shall be provided in all panel boards. The equipment-grounding conductor shall be carried back to the service entrance grounding connection.
2.2.9.6 Receptacles: Receptacles shall be duplex American Standard, 120 Volt, 60 Hertz, 15 Ampere.
2.2.9.7 Lighting: Design and construct adequate lighting to ensure proper visibility in both the food preparation and seating area. The food preparation area and seating area will be on separate circuits.
2.2.9.8 Testing: The Contractor will conduct tests of all system conductors to determine that the system is free from grounded, shorted, or open circuits. The Contractor will test each function of the main and sub panels. The Contractor will test each circuit and device. The Contractor will conduct complete visual inspection of all wiring connections.
2.2.10 Heating, Ventilation, and Air Conditioning (HVAC): Contractor will install the appropriate number of split system HVAC units as specified in the design. The systems shall be pre-wired for a single point power connection. The systems serving the occupied areas shall also have resistance heating.
The systems shall be sized to maintain indoor conditions of 25 degrees C during the summer and 21 degrees C during the winter.
2.2.10.1 Wall Penetrations: All wall penetrations shall be sleeved. Sleeve shall be of sufficient size to allow a minimum of 25.4 mm (1.0 in) clearance around the duct and insulation. The annular space shall be filled with insulation and sealed to protect the exterior from weather and the interior for appearance.
2.2.10.2 Material: Materials and equipment shall be standard products of a manufacturer regularly engaged in the manufacturing of such products, which are of a similar material, design and workmanship. The standard products shall have been in satisfactory commercial or industrial use for at least 2 years. The 2-year use shall include applications of equipment and materials under similar circumstances and of similar size. Manufacturer of the equipment shall certify that the equipment in compliance with an internationally known standard equal to ARI 360 (Air Conditioning and Refrigeration Institute).
2.2.10.3 Parts, Service and Operations & Maintenance Manuals: Standard Parts, Service and Operations & Maintenance manuals shall be submitted both as a hard copy and an electronic copy to include the following:
2.2.10.4 Manufacturer’s technical catalogues, dimensional drawings and wiring diagrams for each type of equipment installed.
2.2.10.5 Operating instructions for various equipment and systems included in the installation work.
2.2.10.6 Parts, Service and Operations & Maintenance manuals will be provided to the Government for all installed equipment and systems, which require regular and specialized maintenance. These manuals shall include at a minimum, all required scheduled service and a suggested inventory of parts required for the maintenance of the units for a period of 5 years.
2.2.10.7 Testing and Balancing: The Contractor shall submit to the Contracting Officer certified Test Reports as well as Mechanical Commissioning for the HVAC System. Test reports shall comply with the standards, listed below, of the selected test and balance association. NEBB-01:
Procedural Standards for Testing - Adjusting - Balancing of Environmental Systems. AABC:
National Standards for Total System Balance (AABC MN-1). Test and Balance Work shall be in accordance with the standards of the selected test and balance association. The work shall also comply with the recommendations of NEBB-01 pertaining to instruments, measurements and procedures and with SMACNA-07, HVAC Systems - Testing, Adjusting and Balancing. Systems shall be tested at near maximum load conditions. Cooling systems shall be tested in summer;
heating systems shall be tested in winter. After completion of the work, the Contractor shall demonstrate to the CO or COR that the installations are adjusted and regulated correctly to fulfill the function for which they have been designed. The Contractor shall test, adjust, balance and regulate the section concerned as necessary until the required conditions are obtained.
2.2.10.8 Acceptance Tests and Approvals: Acceptance tests shall be performed by the Contractor in the presence of the Contracting Office Representative on all systems installed by the Contractor.
The Contractor shall give three (3) days advance notice prior to testing date of all systems.
2.2.11 Communications: All communications installations will follow the European Industry Alliance/ Telecommunications Industry Alliance (EIA/TIA), BICSI, 31W series Air Force Tech Orders (TO), NEC and NFPA-70 standards, Mil-STD-419K grounding.
2.2.11.1 The Contractor shall…