SOW HQ Charette Report - Redacted.pdf

PDF 19 MB Posted

Attached to
Repair SOW Ops Facility B3524 Federal contract opportunity
Solicitation number
FA527025R0015
Issued by
Department of the Air Force Pacific Air Forces

About this file

This Planning Charrette Report (PCR) details a repair project for the SOW OPS Facility B3524 at Kadena Air Base in Japan. The comprehensive renovation involves completely rebuilding the concrete roof with new anchoring and seismic improvements, installing interior wall and roof slab insulation, and replacing mechanical, electrical, and fire protection systems throughout the single-story, 38,875 square foot building constructed in 1967.

The project encompasses three potential courses of action (COA): 1) roof replacement with minimal wall changes, 2) roof and wall repairs, and 3) complete rebuild. Key scope elements include addressing extensive concrete spalling, replacing HVAC and electrical systems, relocating the central communications room, repairing concrete masonry unit load-bearing walls, and updating interior finishes. The facility currently experiences significant structural deterioration due to age and environmental exposure, with concrete carbonation making the structure vulnerable to potential failure during events like typhoons or earthquakes. The estimated project cost is anticipated to be between $25-100 million, with a performance period of approximately 1,100 calendar days.

View the file

Other files for this federal contract opportunity

Other files attached to Repair SOW Ops Facility B3524, newest first.
File Type Posted
SOW Ops Facility B3524_Site Visit Reservation Form Rev.pdf PDF
SOW Ops Facility B3524_Site Visit Reservation Form.pdf PDF
DRAFT SOW LXEZ201072 Repair SOW Repair HQ B3524_Redacted.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA5890321D0012 / FA521523F0011 Kadena Air Base – Tranche 1 Repair SOW OPS Facility, B3524 06 September 2024

TABLE OF CONTENTS

CHAPTER 1 INTRODUCTION

1-1 PURPOSE

1-2 AUTHORIZATION

1-2.1 Scope of Work

1-3 APPLICABLE CRITERIA

1-4 PROJECT DESCRIPTION

1-4.1 COA 1: Roof Replacement 1-4.2 COA 2: Roof and Wall Repairs 1-4.3 COA 3: Complete Rebuild

1-5 PROJECT SITE

1-5.2 Functional Objective 1-5.3 Post-Construction Considerations 1-5.4 Personnel and Equipment

1-6 ECONOMIC SUMMARY

1-6.1 Project Cost:

1-6.2 Source of Funds:

1-6.3 Construction Area Cost Factor:

1-6.4 Pricing Data Source:

1-6.5 Execution Agent:

1-6.6 Estimated MILCON Replacement Cost:

1-6.7 Repair-To-Replacement Ratio:

CHAPTER 2 CIVIL

2-1 GENERAL

2-2 APPLICABLE CODES

2-3 BASIC DESIGN INFORMATION

2-4 CALCULATIONS

CHAPTER 3 ARCHITECTURAL

3-1 GENERAL

3-1.1 Applicable Codes

3-2 BASIC DESIGN INFORMATION

3-2.2 COA 1: Roof Replacement 3-2.3 COA 2: Roof and Wall Repairs

3-2.4 COA 3: Complete Rebuild

CHAPTER 4 STRUCTURAL

4-1 GENERAL

4-1.1 Existing Conditions 4-1.2 New Work 4-1.3 Applicable Codes

4-2 BASIC DESIGN INFORMATION

4-2.1 COA 1: Roof Replacement 4-2.2 COA 2: Roof and Wall Repairs 4-2.3 COA 3: Complete Rebuild 4-2.4 Load Data

CHAPTER 5 MECHANICAL

5-1 GENERAL

5-2 FUNCTIONAL AND TECHNICAL REQUIREMENTS

5-2.1 Applicable Codes 5-2.2 Design Temperatures 5-2.3 Environmental Considerations

5-3 DESIGN OBJECTIVES AND PROVISIONS

5-4 CALCULATIONS

5-5 COORDINATION WITH INSTALLATION OR OUTSIDE AGENCIES

CHAPTER 6 ELECTRICAL

6-1 GENERAL

6-1.1 Existing Conditions 6-1.2 New Work 6-1.3 Applicable Codes

6-2 CALCULATIONS

6-3 COORDINATION WITH INSTALLATION OR OUTSIDE AGENCIES

6-3.1 Telecommunications Node 6-3.2 Other Coordination Considerations

CHAPTER 7 FIRE PROTECTION AND LIFE SAFETY

7-1 GENERAL

7-2 EXISTING CONDITIONS

7-2.1 Fire Flow Test Results

7-2.2 New Work

7-2.3 APPLICABLE CODES, STANDARDS, AND GUIDELINES

7-3 FUNCTIONAL AND TECHNICAL REQUIREMENTS

7-3.1 Fire Sprinkler System 7-3.2 Fire Flow 7-3.3 Fire Department Vehicle Access 7-3.4 Service Lateral Size 7-3.5 Fire Department Connection 7-3.6 Connection to Fire Alarm System 7-3.7 Backflow Prevention 7-3.8 Hydraulic Calculations 7-3.9 Backflow Device Test Heade 7-3.10 Seismic Design 7-3.11 Fire Sprinklers 7-3.12 Portable Fire Extinguisher 7-3.13 Fire Alarm and Mass Notification System 7-3.14 HVAC Duct Smoke Detection System 7-3.15 SCIF Requirements and Planning 7-3.16 Building Egress System 7-3.17 Applicability of Building and Life Safety Codes 7-3.18 Cybersecurity 7-3.19 Hazardous Materials 7-3.20 Surge Suppression (SPD 7-3.21 Power

7-4 DESIGN OBJECTIVES AND PROVISIONS

7-5 COORDINATION WITH INSTALLATION OR OUTSIDE AGENCIES

APPENDIX A – CONCEPT DRAWINGS.........................................................................A APPENDIX B – COST ESTIMATE..................................................................................B APPENDIX C – DRAFT DD1391.....................................................................................C APPENDIX D – SITE VISIT PHOTOGRAPHS................................................................D APPENDIX E – HYDRANT FLOW TEST ........................................................................E APPENDIX F – MEETING MINUTES ..............................................................................F

FIGURES

Figure 1-1 Kadena Air Base Project Location (Image Source: Google Earth) Figure 1-2 SOW OPS Facility, B3524 (Image Source: Google Earth)

CHAPTER 1 INTRODUCTION

1-1 PURPOSE

The purpose of this project is to develop a Planning Charrette Report (PCR) to meet the funding vector checks as required by current AFCEC Business Rules. This PCR will include updates to the current PCR for Kadena Air Base (KAB), meeting minutes identifying requirements, development, DD1391, and a Class III Cost estimate.

The major items within the scope of the repairs identified in this project will include replacement of the facility roof and mechanical and electrical upgrades.

1-2 AUTHORIZATION

1-2.1 Scope of Work

This project will repair the facility’s structural concrete spalling, roof, and mechanical and electrical systems. The concrete roof will be completely rebuilt, including an anchoring system and seismic improvements. Insulation will be installed on the interior side of the exterior walls and below the roof slab. The electrical, ventilation, air conditioning, and fire protection systems will be replaced throughout the building. The central communication room will be relocated to another facility. The project also includes the patching and repair of concrete spalling, structural repairs to the concrete masonry unit load-bearing walls, and repairs to finishes including gypsum and drop ceilings.

Temporary facilities are not needed during execution.

1-3 APPLICABLE CRITERIA

The most current references listed below at the time of design will apply.

DAFI 32-1020 Planning and Programming Built Infrastructure Projects, with Change 1, 19 January 2022

FY25-29 AFCAMP Business Rules UFC 1-200-01 DoD Building Code, with Change 3, 26 February 2024 UFC 1-200-02 High Performance and Sustainable Building Requirements, with

Change 2, 01 June 2022 UFC 1-300-02 Unified Facilities Guide Specifications (UFGS), with Change 3, 18

May 2021 UFC 3-101-01 Architecture, with Change 4, 08 January 2024 UFC 3-110-03 Roofing, with Change 5, 12 June 2024 UFC 3-120-01 Sign Standards, with Change 4, 08 January 2024 UFC 3-201-01 Civil Engineering, with Change 6, 20 December 2022 UFC 3-210-10 Low Impact Development, with Change 3, 01 June 2015 UFC 3-220-01 Soils Investigation Sampling, 1 November 2012 UFC 3-301-01 Structural Engineering, with Change 1, 02 October 2023

UFC 3-401-01 Mechanical Engineering, with Change 1, 01 October 2015 UFC 3-410-01 Heating, Ventilating, and Air Conditioning Systems, With Change

9, 09 January 2024 UFC 3-420-01 Plumbing Systems, 01 April 2021 UFC 3-501-01 Electrical Engineering, with Change 2, 15 December 2023 UFC 3-520-01 Interior Electrical Systems, with Change 2, 12 April 2021 UFC 3-530-01 Interior and Exterior Lighting Systems, with Change 5, 09 February

UFC 3-560-01

UFC 3-580-01

Operation and Maintenance: Electrical Safety, with Change 1, 24 July 2017 Telecommunications Interior Infrastructure Planning and Design, With Change 1

UFC 3-600-01 Fire Protection Engineering for Facility, with Change 6, 06 May

UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings with Change 3, 24 May 2024

UFC 4-021-01 Design O&M: Mass Notification Systems, with Change 1, 01 January 2010

ABA Architectural Barriers Act ASCE 7-16 Minimum Design Loads and Associated Criterial for Buildings and

Other Structures ASCE 41-17 Seismic Evaluation and Retrofit of Existing Buildings ASHRAE Energy Standard, 2019 Edition ECB 2018-17 New Requirements for Visual Notification for Mass Notification

Systems, with Revision 3, 31 August 2023 EM 1110-2-2502 Engineering and Design Retaining and Flood Walls, 29 September

HDS-5 Hydraulic Design of Highway Culverts Third Edition, April 2012 IBC International Building Code, 2021 IEBC International Existing Building Code, 2021 IMC International Mechanical Code, 2021

IPC

Kadena Air Base

Internation Plumbing Code, 2021 Design Guide, 07 February 2020

NFPA 1 Fire Code, 2024 Edition NFPA 13 Standard for the Installation of Sprinkler Systems, 2022 Edition NFPA 24 Standard for the Installation of Private Fire Service Mains and

Their Appurtenances, 2022 Edition NFPA 30 Flammable and Combustible Liquids Code, 2024 Edition NFPA 70 National Electrical Code, 2023 Edition NFPA 70E Standard for Electrical Safety in the Workplace, 2024 Edition NFPA 72 National Fire Alarm and Signaling Code, 2022 Edition

CHAPTER 2 CIVIL

2-1 GENERAL

Per observed drainage patterns of the existing topography and tributary area delineation, significant offsite runoff, and runoff from the east side slope of the building is collected in the existing swale running along the north side of B3524. The 5 feet width x 3.5 feet height earthen berm with masonry wall adjacent to the swale functions as a floodwall diverting the offsite runoff downstream. There are three (3) openings along the earthen berm for access to the building. The finish grade of the opening is flush with the adjacent grade of the slope, enabling off-site runoff to enter the site. Installing barrier berms at the openings would be a cost-effective flooding control measure to eliminate additional off-site runoff entering the site and accumulating in the existing swale.

Observed watermarks appear at the open area between the edge of the building and the earthen berm north of the building. Temporary ponding of stormwater occurs in the area due to limited capacity of the existing earthen swales and drainage system.

In addition to stormwater detention at existing swale, the adjacent B3531 located downstream has flooding issues during major storm events. The downstream storm drains discharge to a nearby creek next to Halyburton Street, and watermarks are observed at the catch basins at the parking lot upstream of the discharge point.

Most likely, the downstream storm drains are undersized to handle the peak flows, and the surcharged storm drain reached its capacity causes stormwater detention within the local depressed area between the building and the sloping berm.

2-2 APPLICABLE CODES

See Section 1-3.

2-3 BASIC DESIGN INFORMATION

Hydrology and hydraulic analysis shall be performed to estimate the peak flows that contribute to the site for storm drain system upgrade and flood control.

Evaluate and determine the Best Management Practice (BMPs) system with onsite stormwater detention system, flow diversion, or increase storm drain system capacity downstream.

2-4 CALCULATIONS

Topography survey data for drainage area delineation (both off site/on-site).

Perform hydrology analysis for peak flows estimation of targeted design storm events per

TR-55.

Perform hydraulic analysis to determine/verify capacity of existing storm drain system per

HDS-5.

CHAPTER 4 STRUCTURAL

4-1 GENERAL

4-1.1 Existing Conditions

The existing structure was constructed around the year 1967. It is a one-story building with a low sloped reinforced concrete roof supported by concrete beams and columns.

The perimeter walls and most interior walls are CMU load bearing shear walls. The walls bear on shallow concrete strip footings. Shallow spread footings support concrete columns and are connected to adjacent wall strip footings with tie beams. There is a large ground floor mechanical room with exterior access, and three mechanical rooms in CMU-walled penthouses on the roof. The portion of roof above the auditorium is constructed of long span concrete beams, upturned so the tops of the beams extend up above the roof slab. The center section of the building is similarly covered by upturned concrete beams.

In addition, that roof slab was constructed to be lower than the surrounding roof, with sloping surface and drainage holes through the upturned beams all leading to one center drain. A corrugated galvanized steel roof was added in 1982 above that roof to shed water.

The existing structure has extensive concrete spalling in the roof slab due to corrosion expansion of reinforcement. The spalling is significant in the un-conditioned mechanical room, and in Rooms 188 and 120-121. There are smaller spalls and concrete delamination at several other locations. Fiberboard insulation is fastened to the underside of the roof slab, holding moisture to the roof, and hiding any spalling. Most interior spall locations were observed located below small roof penetrations, areas with ponding, and/or rooftop equipment anchor points. The spalling appears to be limited to the roof slab, with minimal spalling observed in beams and columns. The exception to this is the concrete beams in non-conditioned spaces, such as the mechanical room and penthouses were observed to have significant deterioration and spalling. The CMU shear walls appear to be in structurally acceptable condition. The slab-on-grade appears to be in satisfactory condition with one exception where the slab appears to be cracked and bulging up.

The spalling issue has caused the occupants of the building to be evacuated to other locations and the building is mostly vacant. Samples of the roof slab concrete at this building were obtained in January 2024 and have undergone laboratory testing to determine the concrete properties. Testing of the samples includes chloride content, petrography, compressive strength, and carbonation. A testing report has been produced for this investigation which states the structural deterioration is mainly attributed to carbonation of the concrete. The concrete has become carbonated due to the age of the structure, a poor building envelope, prolonged exposure to the elements and a lack of preventative maintenance. The process of carbonation is irreversible and difficult to stop in the presence of moisture. For perspective, it could take approximately two years for the roof slab to dry out if the roof envelope is repaired and the underside of the roof slab concrete is exposed to conditioned air. As such, additional spalling and deterioration is anticipated.

These spalls can injure occupants and equipment below. In addition, this loss of concrete thickness and reinforcement cross section results in a loss of flexural and shear capacity of the concrete slab. Over time such loss will progress to cracking, allowing more water penetration and deterioration, leading to additional concrete section loss. This increases the chances of a possible failure of the structural system during an event such as a heavily loaded maintenance repair, typhoon, or earthquake.

In addition to the concrete spalling issues, there is significant cracking in the CMU at the three rooftop penthouses. There is also significant leaking where the lowered center section roof meets the walls at the surrounding hallway.

The roofing is a reinforced, fluid-applied membrane. The roofing membrane exhibited signs of wear, brittleness, and has reached the end of its useful life.

4-1.2 New Work

Structural work will vary based on the COA that is chosen. See section 4-2 below. Scope will involve designing and detailing new concrete, steel, and CMU construction, and repairs to any existing to remain. Nonstructural systems including Ceilings, Piping, and Mechanical systems will require seismic bracing.

4-1.3 Applicable Codes

See Section 1-3.

4-2 BASIC DESIGN INFORMATION

Due to the spalling issues, New Work can involve:

4-2.1 COA 1: Roof Replacement

Demolish the entire roof and concrete beams down to top of existing CMU walls - leaving walls, slab on grade, and footings in place. Where wall heights vary, new CMU or concrete can be added to achieve a consistent elevation. The roof will be rebuilt while keeping existing concrete columns and CMU shear walls in original locations above existing grade beams and footings.

The roof can be replaced with a new cast-in-place concrete slab; precast structural elements, such as hollow core slab or double tees topped with a concrete topping; or steel joists and metal deck. New connections and rebar will be doweled into the existing CMU and concrete, using an adhesive anchoring system.

The design and construction of the existing CMU walls, concrete columns, and footings will be evaluated to ensure that they are not overloaded and can meet the lateral load capacity requirements of IEBC, AISC 41, and RP 10. New shear walls, columns and footings may need to be added as required by the Code. Select interior walls can be demolished as needed by Architectural requirements, but for the most part the existing wall layout will remain. The existing mechanical penthouses will be demolished and

CHAPTER 5 MECHANICAL

5-1 GENERAL

The SOW Operations Building, B3524, is experiencing major structural degradation.

There are three (3) COAs that are being evaluated for addressing the structural issues and all three (3) COAs involve the complete replacement of the HVAC and Plumbing systems in the existing facility or providing all new HVAC and Plumbing systems in a new facility. Based on the current condition of key HVAC and plumbing components, the replacement of much of these systems is indicated, regardless of the structural situation.

Although some components have been replaced recently, those components will likely be repurposed at other facilities based on the timeline for reconstructing or replacing this building. Currently, there are four air handlers on the roof in penthouse structures. There is a desire to move all air handling units to the ground, for ease of maintenance and protection during storms. This will require the construction of ground level Mechanical Rooms, either within the existing building footprint or as additions to the building. There is no available space on the ground on the south and west sides of the existing building footprint for new additions, and there is limited space on the east side of the building. Most of the new Mechanical Room construction is limited to the north side of the building or new Mechanical Room space can be set aside within the existing building footprint.

5-2 FUNCTIONAL AND TECHNICAL REQUIREMENTS

5-2.1 Applicable Codes

See Section 1-3.

5-2.2 Design Temperatures

HVAC loads should be based upon the local design weather values. For Kadena Air Base on Okinawa, Japan the following values are recommended:

Outdoor Design:

Summer Conditions: 91.3°F dry bulb ASHRAE 1% DB 80.3°F wet bulb ASHRAE 1% MCWB

Winter Conditions: 50.3°F dry bulb ASHRAE 99.6% DB

Indoor Design:

Summer: 78°F dry bulb 50% relative humidity

Winter: 68°F dry bulb

0-50% relative humidity side. There are existing issues with sewer flow within the building, with some underfloor sanitary sewer lines suspected of having sunk into the ground causing back-ups. There are currently Men’s and Women’s group toilets in the building’s southwest area, but only a single Men’s room in the northeast area. Based on system condition, age and the proposed COAs extensive construction impacts, all existing plumbing within the building footprint will be removed, including all under floor piping.

Any redesign should address the inequity of restrooms available for all occupants.

Domestic and sanitary sewer connection points will be provided from the utilities surrounding the building. All new domestic cold and hot water piping will be provided below the floor, in walls and above the ceilings. All new sanitary sewer piping will be provided below the floor, in walls and above the ceilings, with venting through the roof. All restroom fixtures will be new in any restoration and modernization of the existing building, including water closets, urinals, lavatories, and showers. New water fountains will be provided at restroom locations. New electric tank type or instantaneous water heaters will be provided where hot water is required.

Seismic restraints will be required for equipment, piping, and ductwork in the building. The Seismic Design Category, Risk Category and Site Class as determined by the Structural Engineer must all be considered when determining which components need seismic restraints.

Provide complete O&M information at the end of the project, including warranty information for all new equipment.

5-4 CALCULATIONS

A detailed analysis of the building is required to determine the final sizing of the new HVAC equipment. This analysis will use local weather data and information about the number of people, equipment, and lighting in each room. The building envelope construction will be updated as part of the building reconstruction and used in the HVAC load calculations.

The detailed analysis will determine the equipment size required, and the appropriate distribution of the cooling to all areas of the building. Loads will be calculated using a computerized program that uses ASHRAE Fundamentals methods of calculation. High Performance and Sustainable Building (HPSB) practices, as outlined in UFC-1-200-02, must be followed.

5-5 COORDINATION WITH INSTALLATION OR OUTSIDE AGENCIES

The building will have a DDC system that communicates using the BACnet protocol and will communicate to the base-wide Energy Monitoring and Control System (EMCS) over the Base CE VLAN to Building 1474 (B1474). Cybersecurity will be integrated into the DDC system, especially for the tie-in to the EMCS. Utility meter monitoring will be included per the requirements of the Kadena Design Guidelines.

CHAPTER 6 ELECTRICAL

6-1 GENERAL

6-1.1 Existing Conditions

The facility's existing electrical system consists of a 120/208V, 3 Phase, 4 Wire, 2000A switchboard powered from a 500 kVA unit substation with a 1200A circuit breaker located just outside of the building.

The switchboard consists of Bus A, for normal building loads, and Bus B, for emergency building loads. Bus A is powered from the 500 kVA unit substation via a 1600A main circuit breaker in the switchboard. Bus A is connected to a 208V, 600A, 4 Pole, 60 Hz, automatic transfer switch (ATS) via a 600A circuit breaker.

This ATS is connected to a 150 kW, 120/208V, 3 Phase, 4 Wire, 60 Hz, diesel emergency standby generator and to the Bus B side of the switchboard via lugs only.

Switchboard Bus A provides power to a wire gutter, which provides power to rooms 116, 135, 178, and 193, and to motor control center (MCC) MCC A, which powers chiller units, chilled water pumps, and an air handling unit.

Switchboard Bus B provides power to several panelboards and air handling units, and provides power to MCC B, which provides power to the fire alarm system, roof vent, and a few existing loads. Bus B is the facility’s emergency circuit, providing power to all areas of the SCIF and parts of the JAOC area and HVAC system. Unfortunately, not all areas of the JAOC and HVAC system are powered from the emergency circuit, as would be preferred.

The switchboard, MCC A, and MCC B are in extremely poor condition and pose a serious safety hazard for any personnel working on or near the equipment. The equipment is covered in rust with large holes in the front plates. Exposed electrical wires, circuit breakers, and more can be seen and easily reached. Some electrical compartment doors on the motor control center are unable to close.

It is unclear exactly how old the switchboard and MCCs are, but they are over 30 years old and may be around 50 years old. Modifications in 2011 replaced the old generator with the current 150 kW Caterpillar generator and 600A Caterpillar ATS. Based on visual inspection and age, the ATS and generator appear to be in fair condition and could be reused or repurposed. The 1,000-gallon diesel fuel tank, located outside, was not replaced during the modification project.

Panelboards throughout the facility appear in acceptable condition due to being in a climate-controlled environment but are likely close to the end of their useful life.

While light controls appear older, during the site visit, it appears all fluorescent lights were replaced with LED lights.

6-3.2 Other Coordination Considerations

Coordination with the electrical utility is required to turn off the upstream unit substation circuit breaker prior to construction, demolish from and reconnect to the new system, and reenergize the system once construction is complete.

7-2.3 APPLICABLE CODES, STANDARDS, AND GUIDELINES

See Section 1-3.

7-3 FUNCTIONAL AND TECHNICAL REQUIREMENTS

7-3.1 Fire Sprinkler System

The building must be provided with complete wet pipe automatic sprinkler protection with full coverage throughout the facility in accordance with Section 9-7.2.1.1 UFC 3-600-01.

Accordingly, all single-story Type I or II construction facilities greater than 15,000 feet2 (1,394 m2) gross floor area must be provided with sprinkler system. The occupancy classification for sprinkler system in offices, administration, and public areas will be light hazard and for electrical and mechanical rooms must be considered as ordinary hazard occupancies. Facilities requiring sprinkler protection must be provided with systems that are designed using the area/density method of NFPA 13, except the discharge requirements for non-storage occupancies must be in accordance with Table 9-3, unless otherwise specified in the UFC 3-600-01.

7-3.2 Fire Flow

In accordance with Section 9-2.1, the fire flow provided for sprinklered buildings must be 1000 gpm at 20 psi. Per the latest test results, the fire flow for B3524 narrowly meets the code requirements. This issue must be further investigated and analyzed on the succeeding design and engineering stages.

7-3.3 Fire Department Vehicle Access

In accordance with UFC 3-600-01, Section 9-1, all Facilities greater than 5000 ft2 (465 m2), or more than two stories in height, must have at least one means of all-weather ground access to allow emergency vehicles unimpeded access to the Facility. All weather ground access roads are present functioning properly.

7-3.4 Service Lateral Size

In accordance with Section 9-3.3.2, minimum size Service Lateral for fire sprinkler systems must be not less than 6-inches. (150 millimeters) in diameter.

7-3.5 Fire Department Connection

Facilities with fire department connections for fire suppression systems must be provided with suitable all-weather ground access surface for any apparatus within 150 feet (45 m) of such fire department connections. In addition, at least one hydrant must be located within 150 feet (45 m) of the fire department connection.

7-3.6 Connection to Fire Alarm System

The fire sprinkler system must be connected to the fire alarm system for transmission of alarms, supervisory and trouble signals. Fire sprinkler system water control valves and system riser must be provided with electric supervisory devices for monitoring the status of devices and must be reported to the building fire alarm system for potential system tampering as well as water flows indicating fire alarm in the system.

7-3.7 Backflow Prevention

The backflow prevention device must be provided in accordance with UFC 3-600-01 Section 9-6.6. The horizontal backflow preventer must be installed so that the bottom of the assembly is no greater than 24 in. above the finished floor. For vertical backflow devices, upper operating handwheel must be no more than 6 feet above the finished floor.

The hydraulic pressure loss due to presence of the backflow device must be accounted in the hydraulic calculations.

7-3.8 Hydraulic Calculations

The preparer of the shop drawings must perform hydraulic calculations in accordance with the applicable NFPA standard (NFPA 13), demonstrating that the design will provide an adequate supply for the fire suppression systems.

7-3.9 Backflow Device Test Heade

The new fire sprinkler systems must include test valves installed downstream of the backflow preventer for the purpose of backflow forward flow tests directed by NFPA standard. These valves must be angle or globe valves with 2.5-inch male National Standard Hose Threads with cap and chain. For each 250-gpm system flow rate, one 2.5-inch valve must be provided.

7-3.10 Seismic Design

The QFPE must coordinate with the Structural Engineer to determine the proper seismic design category for the project, in accordance with the IBC or ASCE guidelines. Seismic restraint is not required for Seismic design category A or B, except as otherwise required in UFC 3-600-01. For additional data, UFC 3-301-01 must be consulted.

7-3.11 Fire Sprinklers

Fire Sprinkler systems must be provided in the new electrical and mechanical rooms regardless of the fire resistance rated separation. The sprinkler k-factor must not be less than k-5.6 for the light hazard areas, including offices and admin rooms, and k-8.0 for all ordinary hazard areas, counting electrical and mechanical rooms, for the proposed Wet system.

7-3.12 Portable Fire Extinguisher

Must be provided in accordance with UFC 3-600-01, NFPA10, and NFPA101 requirements.

7-3.17 Applicability of Building and Life Safety Codes

The occupancy classification as it relates to fire/smoke resistance rating of interior non-load bearing partitions (other than occupancy separation), means of egress, interior finish, features of fire protection (including vertical openings) and associated requirements must be compliant with requirements of NFPA 101. The IBC must be utilized to determine the occupancy classification as it relates to allowable construction type, building height, building area, building separation distance, occupancy separation and associated requirements.

7-3.18 Cybersecurity

In accordance with Section 1-13 UFC 3-600-01 all control systems (including systems separate from an energy management control system) must be planned, designed, acquired, executed, and maintained in accordance with DoD Instruction 8500.01, DoD Instruction 8510.01, and as required by individual Service Implementation Policy.

7-3.19 Hazardous Materials

Requirements of Section 3-4 of UFC 3-600-01 must apply. For the purpose of occupancy classification, the maximum allowable quantities (exempt amounts) noted in NFPA 400 must be used except for ammunition and explosives, for which the maximum allowable quantity noted in IBC Chapter titled “Occupancy Classification and Use” must be used.

7-3.20 Surge Suppression (SPD

Provide primary power in accordance with Provide SPD on all 120 Vac circuits to control panels, subpanels, transmitters, amplifier panels, and booster panels. SPD must have both a UL 1449 and UL 1283 listing and must be located in an adjacent hinged terminal box.

7-3.21 Power

Provide primary power in accordance with UFC 3-520-01. This includes the provision of a lock-on circuit breaker. For secondary power, provide rechargeable batteries per NFPA 72 to operate the fire alarm system under supervisory conditions for 48 hours and all alarm devices for an additional 15 minutes. Where the fire alarm system also serves as a mass notification system, refer to UFC 4-021-01 for additional requirements.

7-4 DESIGN OBJECTIVES AND PROVISIONS

A complete fire sprinkler system in accordance with requirements of NFPA13, IBC, and UFC 3-600-01 must be provided throughout the building. The earthquake sway bracing for riser and overhead piping must be provided.

A complete fire alarm and MNS system in accordance with requirements of NFPA70, 72, IBC, UFC 3-600-01, UFC 4-021-02, and UFC must be provided.

A duct smoke detection system for new HVAC duct smoke monitoring per requirements of NFPA 90A and UFC 3-600-01 must be provided.

Interconnection between fire sprinkler system alarm and supervisory equipment with building fire alarm system in compliance with NFPA and UFC requirements must be provided.

The preparer of the shop drawings must perform hydraulic calculations in accordance with the NFPA13 standard to demonstrate that available water supply source can provide an adequate amount of flow and pressure to cover fire suppression system demand needs.

In addition, all items indicated in previous Section 7-3 must also be considered in design objectives.

7-5 COORDINATION WITH INSTALLATION OR OUTSIDE AGENCIES

The fire protection scope of work requires coordination between the fire sprinkler system supervision and alarm equipment with building fire alarm and monitoring system, and with air base remote supervising and fire stations, for transmitting alarm, supervisory, and trouble signals. The sprinkler piping, sway bracing, and hangers require coordination with structural, electrical raceways, mechanical AHU, and ductwork construction.

A-1

APPENDIX A – CONCEPT DRAWINGS

1 2 3 4 5

C

B

A

AHU-1

AHU-5

AHU-2

AHU-4

AHU-3

CWP-1

CWP-2

CWP-3

CH-1

CH-2

AHU-1

1 2

D

1.

2.

3.

4.

5.

THE EXISTING CHILLERS (CH) SHALL REMAIN AND BE

REUSED. REMOVE ALL EXTERIOR CHILLED WATER PIPING.

REMOVE EXISTING CHILLED WATER PUMPS (CWP) AND

ALL CHILLED WATER PIPING.

REMOVE EXISTING AIR HANDLING UNIT (AHU) AND ALL

ASSOCIATED DUCTWORK.

THE ROOF STRUCTURE IS BEING REMOVED. ALL

INTERIOR CHILLED WATER PIPING, DUCTWORK,

CONTROLS AND ALL APPURTENANCES ASSOCIATED WITH

THE HVAC SYSTEM SHALL BE REMOVED.

EXISTING INFORMATION TRANSFER NODE (ITN) ROOM TO

REMAIN DURING COA-1 AND COA-2 WORK. PROVIDE

TEMPORARY HVAC DURING BUILDING RENOVATION

WORK.

SCALE: 1/16" = 1'-0"A4 HVAC FLOOR PLAN DEMOLITION

1. EACH HVAC UNIT SERVES THE HATCHED AREA INDICATED.

EXISTING EQUIPMENT SCHEDULE-OLD

MARK MANUFACTURER MODEL SIZE AGE

AHU-1 CARRIER 39MN21 10,300 CFM 2005

AHU-2 CARRIER 39LA21 11,000 CFM 2011

AHU-3 CARRIER 39MN10 5,000 CFM 2005

AHU-4 CARRIER 39MN10 5,000 CFM 2005

AHU-5 CARRIER 39MN10 5,000 CFM 2005

CH-1 CARRIER 30RAP060 60 TONS 2023

CH-2 CARRIER 30RAP060 60 TONS 2023

CWP-1 TACO FI1509 110@65', 5HP 2019

CWP-2 TACO FI1509 110@65', 5HP 2019

CWP-3 TACO FI1509 110@65', 5HP 2005

TR

U

E N

PLAN

NORTH

SHEET NOTES

KEYNOTES#

1 3 5 7 92 4 6 8 10

G

E

C

A

F

D

B

SHEET ID

AI

R

F O

R C

E

IN

ST

AL

LA

TI

O N

A N

D

M

IS

SI

O

N S

U

PP

O R

T C

EN

TE

R D

ET

AC

H M

EN

T

(P

AC

AF

JB

PH

H

, H I

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

AN

SI

D

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

D

AT

E M

AR

K

D

ES

C R

IP

TI

O N

Fi le

P at h:

Pl ot D at e:

PO

N

D C

D M

S M

IT

H

J V

LP

P ar kw ay L an e

Su ite

Pe ac ht re e C or ne rs G eo rg ia

KA

D

EN

A

AI

R

B

AS

E O

KI

N

AW

A, J

AP

AN

R

EP

AI

R S

Q O

PS

F

AC

IL

IT

Y, B

PA

C

AF

F

SR

M (D

N A)

T R

AN

C

H E

S

EP

FA

F0

FA

D

PO

N

D

Au to de sk

D oc s:

//1

-P

AC

AF

-K ad en a

B

/1

_K ad en a_ B3

4_

BL

D

G M

EC

H

_v

.rv t

8/

/2

1:

:5

PM

MD101

H

VA

C F

LO

O

R P

LA

N

D

EM

O

LI

TI

O

N

M

PM

G

VL

AL

R

FI

N

AL

5% D

ES

IG

N

B3524

EM

G

SCALE:

8' 16' 32'0

1/16" = 1'-0"

B

A

AHU-5

AHU-3

AHU-4

AHU-2

1 D

SCALE: 1/16" = 1'-0"A4 HVAC ROOF PLAN DEMOLITION

1.

2.

THE ROOF STRUCTURE IS BEING REMOVED. ALL CHILLED

WATER PIPING, CONDENSING UNITS AND ALL

APPURTENANCES ASSOCIATED WITH THE HVAC SYSTEM

SHALL BE REMOVED.

REMOVE AIR HANDLERS LOCATED IN PENTHOUSES ON

ROOF, INCLUDING ALL PIPING, CONTROLS, DUCTWORK,

ETC.

TR

U

E N

PLAN

NORTH

KEYNOTES#

1 3 5 7 92 4 6 8 10

G

E

C

A

F

D

B

SHEET ID

AI

R

F O

R C

E

IN

ST

AL

LA

TI

O N

A

SI

O

N S

U

PP

O R

T C

EN

TE

R D

ET

AC

H M

EN

T

(P

AC

AF

JB

PH

H

, H I

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

AN

SI

D

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

D

AT

E M

AR

K

D

ES

C R

IP

TI

O N

Fi le

P at h:

Pl ot D at e:

PO

N

D C

D M

S M

IT

H

J V

LP

P ar kw ay L an e

Su ite

Pe ac ht re e C or ne rs G eo rg ia

KA

D

EN

A

AI

R

B

AS

E O

KI

N

AW

A, J

AP

AN

R

EP

AI

R S

Q O

PS

F

AC

IL

IT

Y, B

PA

C

AF

F

SR

M (D

N A)

T R

AN

C

H E

S

EP

FA

F0

FA

D

PO

N

D

Au to de sk

D oc s:

//1

-P

AC

AF

-K ad en a

B

/1

_K ad en a_ B3

4_

BL

D

G M

EC

H

_v

.rv t

8/

/2

1:

:5

PM

MD102

H

VA

C R

O O

F

PL

AN

D

EM

O

LI

TI

O N

M

PM

G

VL

AL

R

FI

N

AL

5% D

ES

IG

N

B3524

EM

G

SCALE:

B

A

3" COLD WATER

3" SANITARY SEWER

WATER

HEATER

4" SANITARY

SEWER

4" SANITARY SEWER

4" SANITARY SEWER

2" COLD WATER

WATER

HEATER

D

SCALE: 1/16" = 1'-0"A4 PLUMBING FLOOR PLAN DEMOLITION

1.

2.

3.

4.

5.

DOMESTIC WATER ENTRANCE TO THE BUILDING SERVING

SEVERAL SETS OF RESTROOMS. REMOVE ALL OVERHEAD

DOMESTIC COLD WATER PIPING FROM THE CONNECTION

POINT IN THE STREET TO ALL FIXTURES AND WATER

HEATERS.

DOMESTIC WATER ENTRANCE TO THE BUILDING SERVING

FIRE PROTECTION AND ONE SET OF RESTROOMS.

REMOVE ALL OVERHEAD DOMESTIC COLD WATER PIPING

FROM THE CONNECTION POINT IN THE STREET TO ALL

FIXTURES AND WATER HEATERS.

RESTROOM WITH WATER HEATER. REMOVE ALL

PLUMBING FIXTURES, WATER HEATERS AND ALL HOT

WATER PIPING.

SANITARY SEWER PIPING FROM FLOOR DRAINS TO

CONNECTION OUTSIDE OF BUILDING. ALL UNDERFLOOR

SANITARY SEWER PIPING AND ALL ABOVE FLOOR VENT

PIPING SHALL BE REMOVED.

SANITARY SEWER PIPING FROM RESTROOMS TO

CONNECTION OUTSIDE OF BUILDING. ALL UNDERFLOOR

SANITARY SEWER PIPING AND ALL ABOVE FLOOR VENT

PIPING SHALL BE REMOVED.

TR

U

E N

PLAN

NORTH

KEYNOTES#

1 3 5 7 92 4 6 8 10

G

E

C

A

F

D

B

SHEET ID

AI

R

F O

R C

E

IN

ST

AL

LA

TI

O N

A

SI

O

N S

U

PP

O R

T C

EN

TE

R D

ET

AC

H M

EN

T

(P

AC

AF

JB

PH

H

, H I

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

AN

SI

D

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

D

AT

E M

AR

K

D

ES

C R

IP

TI

O N

Fi le

P at h:

Pl ot D at e:

PO

N

D C

D M

S M

IT

H

J V

LP

P ar kw ay L an e

Su ite

Pe ac ht re e C or ne rs G eo rg ia

KA

D

EN

A

AI

R

B

AS

E O

KI

N

AW

A, J

AP

AN

R

EP

AI

R S

Q O

PS

F

AC

IL

IT

Y, B

PA

C

AF

F

SR

M (D

N A)

T R

AN

C

H E

S

EP

FA

F0

FA

D

PO

N

D

Au to de sk

D oc s:

//1

-P

AC

AF

-K ad en a

B

/1

_K ad en a_ B3

4_

BL

D

G M

EC

H

_v

.rv t

8/

/2

1:

:5

PM

PD101

PL

U

M

BI

N G

F

LO

O R

P

LA

N D

EM

O

LI

TI

O N

M

PM

G

VL

AL

R

FI

N

AL

5% D

ES

IG

N

B3524

EM

G

SCALE:

B

A

D

3" COLD WATER

3" SANITARY SEWER

2" COLD WATER

4" SANITARY

SEWER

4" SANITARY

SEWER

1.

2.

3.

4.

5.

6.

PROPOSED NEW MEN'S AND WOMENS RESTROOM

LOCATION. PROVIDE NEW WATER HEATER IN A CLOSET

IN THE SAME AREA AS NEW RESTROOMS.

PROVIDE NEW DOMESTIC WATER ENTRANCE IN SAME

LOCATION AS EXISTING. EXTEND TO NEW SET OF

RESTROOMS AND PROVIDE MAKE-UP WATER FOR THE

CHILLED WATER SYSTEM.

PROVIDE NEW SANITARY SEWER ENTRANCE IN SAME

LOCATION AS EXISTING. SANITARY LINE SHALL SERVE

THE MECHANICAL ROOM.

PROVIDE NEW SANITARY SEWER ENTRANCE IN SAME

LOCATION AS EXISTING. SANITARY LINE SHALL SERVE

THE NEW SET OF RESTROOMS.

PROVIDE NEW SANITARY SEWER ENTRANCE. SANITARY

LINE SHALL SERVE THE RESTROOM.

NEW HVAC EQUIPMENT IN EXISTING OR NEW MECHANICAL

ROOM. PROVIDE FLOOR DRAINS.

SCALE: 1/16" = 1'-0"A4 PLUMBING FLOOR PLAN NEW WORK

TR

U

E N

PLAN

NORTH

KEYNOTES#

1 3 5 7 92 4 6 8 10

G

E

C

A

F

D

B

SHEET ID

AI

R

F O

R C

E

IN

ST

AL

LA

TI

O N

A

SI

O

N S

U

PP

O R

T C

EN

TE

R D

ET

AC

H M

EN

T

(P

AC

AF

JB

PH

H

, H I

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

AN

SI

D

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

D

AT

E M

AR

K

D

ES

C R

IP

TI

O N

Fi le

P at h:

Pl ot D at e:

PO

N

D C

D M

S M

IT

H

J V

LP

P ar kw ay L an e

Su ite

Pe ac ht re e C or ne rs G eo rg ia

KA

D

EN

A

AI

R

B

AS

E O

KI

N

AW

A, J

AP

AN

R

EP

AI

R S

Q O

PS

F

AC

IL

IT

Y, B

PA

C

AF

F

SR

M (D

N A)

T R

AN

C

H E

S

EP

FA

F0

FA

D

PO

N

D

Au to de sk

D oc s:

//1

-P

AC

AF

-K ad en a

B

/1

_K ad en a_ B3

4_

BL

D

G M

EC

H

_v

.rv t

8/

/2

1:

:0

PM

P-101

PL

U

M

BI

N G

F

LO

O R

P

LA

N N

EW

W

O R

K

M

PM

G

VL

AL

R

FI

N

AL

5% D

ES

IG

N

B3524

EM

G

SCALE:

D-1

APPENDIX D – SITE VISIT PHOTOGRAPHS

Repair SOG OPS Facility, B3524 06 September 2024

D-2

Appendix D – Site Visit - Photographic Documentation

E-1

APPENDIX E – HYDRANT FLOW TEST

File details come from the government source that posted it. Updated .