QUESTIONS AND ANSWERS

FOR

SOLICITATION # FA5270-18-Q-B065

Question 1: Is onsite training/setup and installation assistance desired on this project?

Answer: No, this requirment does not require onsite training, setup and installation assistance.

However, pre-configuration before shipping of power supply (3 phase, 208VAC, 125 Amp) is required as written on the RFQ’s salient characteristics.