This Statement of Work (SOW) details the requirements for a wash rack installation and removal project at Andersen Air Force Base in Guam. The project involves two primary components: 1) removing the existing wash rack with dimensions of 45ft x 30ft x 9ft, including disconnecting power, dismantling ramps and collection racks, and disposing of the infrastructure, and 2) installing a new wash rack with specific technical requirements. The new wash rack must have drive-through capabilities, a center shovel trough, minimum 2ft center rack width, fit within a 60ft x 50ft area, include 4ft overspray walls, and be rated to support at least 20,000lbs. Additional specifications include a galvanized steel construction, automated closed-loop filtration system, oil water separator, 3000 PSI pressure washer, external control box, and a 12-month on-site preventative maintenance warranty.
The SOW also outlines critical operational and security parameters for the contractor. Normal work hours are 0730-1630, Monday through Friday, excluding holidays. The contractor must provide a point of contact who can respond on-site within 1 hour during duty hours and 2 hours during non-duty hours. Strict security protocols are mandated, including compliance with base traffic regulations, prohibition of weapons, proper identification procedures, and adherence to controlled/restricted area entry requirements. The government will provide emergency medical transportation if needed, with the contractor responsible for reimbursing medical service costs. The project is managed by the 36th Munitions Squadron (36 MUNS), with the SOW signed by Staff Sergeant Paul D. Lambert, MSEM Production Supervisor.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
36 MUNS Wash Rack
ON
ANDERSEN AFB, GUAM
Table of Contents
1. DESCRIPTION OF SERVICES
1.1 REQUIREMENTS:
1.2 LIABILITY:
1.3 GOVERNMENT FURNISHED SERVICES:
2. GENERAL INFORMATION
2.1 HOURS OF OPERATION:
2.2 CONTRACTOR PERSONNEL:
3. SECURITY
3.1 PASS AND IDENTIFICATION ITEMS:
3.2 RETRIEVING IDENTIFICATION MEDIA:
3.3 TRAFFIC LAWS:
3.4 WEAPONS, FIREARMS, AND AMMUNITION:
3.5 FOR OFFICIAL USE ONLY (FOUO):
3.6 REPORTING REQUIREMENTS:
3.7 PHYSICAL SECURITY:
3.8 CONTROLLED/RESTRICTED AREAS:
3.9 MILITARY EXERCISES:
1. DESCRIPTION OF SERVICES
1.1 REQUIREMENTS:
Installation of new wash rack and removal/disposal off base of existing wash rack:
1. Current wash rack removal and disposal
a. Provide equipment and trucking for disassembly and removal
b. Current wash rack dimension: L=45ft, W=30ft, H=9ft
c. Provide all labor, cleanup site and removal of all potential FOD
d. Disconnection of power: 200A / 240Vac
e. Dismantle of ramps and collection rack
f. Packaging/securement of all items for removal
2. New wash rack requirements
a. Provide equipment and trucking for delivery and assembly
b. Provide all labor, cleanup site and removal of all potential FOD
c. Connection of power to 200A / 240Vac
d. Drive thru systems (ramps on both ends) or drive on – back off wash rack platforms
e. Center shovel trough rack on ramp for removal of solid waste
f. Minimum center rack width 2ft
g. Must fit in available area: L=60ft, W=50ft
h. Minimum 4ft overspray walls on sides
i. Rack system rated to at least 20,000lbs
j. Rack system must be constructed of at least heavy duty steel which must be 100% galvanized for rust protection
k. Automated closed loop filtration system and oil water separator for waste water recycle and treatment system with recovery pump to cycle water from rack
l. Minimum 3000 PSI pressure washer with soap dispersion
m. External control box by pressure hose for system control and emergency shut off
n. 12 Months on-site preventative maintenance, parts and labor warranty provided by support staff, all filters included
1.2 LIABILITY:
The contractor shall be liable for any damages resulting from any carelessness or failure to follow proper safety, installation, engineering, or maintenance procedures and standards.
1.3 GOVERNMENT FURNISHED SERVICES:
The government will provide emergency medical transportation and treatment if required. The contractor shall reimburse the Government for the cost of these medical services at current rates.
2. GENERAL INFORMATION
2.1 HOURS OF OPERATION:
The normal hours of operation for the project are from 0730 to 1630, Monday through Friday, excluding holidays and PACAF Family days.
2.2 CONTRACTOR PERSONNEL:
The contractor shall provide point of contact (POC) for all contractual matters during all hours of operation. The POC shall respond on-site within 1 hour during normal duty hours of operation and within 2 hours during non-duty hours to discuss concerns with government personnel designated by the CO to discuss problem areas.
3. SECURITY
3.1 PASS AND IDENTIFICATION ITEMS:
The contractor shall ensure the pass and identification items required for contract performance are obtained for employees.
3.2 RETRIEVING IDENTIFICATION MEDIA:
The contractor shall return all identification media and/or visitor passes from employees who depart for any reason before the contract expires; i.e. terminated for cause, reassignment, retirement, etc.
3.3 TRAFFIC LAWS:
The contractor and its employees shall comply with base traffic regulations. Traffic regulations include, but are not limited to:
· Employees shall wear seatbelts when operating or riding in any vehicle (military, company or private owned) while on installation.
· Speed limits on Andersen AFB are 25 MPH unless otherwise posted. Be aware of reduced speed limits and exercise caution when driving in base housing and school zones.
· All vehicle operators on the installation shall not use cell phones unless the vehicle is safely parked or they are using a 100% hands free device. The wearing of any other portable headphones, earphones or other listening devices while operating a motor vehicle is prohibited.
3.4 WEAPONS, FIREARMS, AND AMMUNITION:
Employees are prohibited from possessing weapons, firearms, or ammunition on themselves or within vehicles (military, contractor-owned, or privately owned) while on Andersen AFB.
3.5 FOR OFFICIAL USE ONLY (FOUO):
The contractor shall comply with DoD 5400.7-R, Chapter 4, DoD Freedom of Information Act (FOIA) Program, requirements. This regulation sets policy and procedures for the disclosure of records to the public and for marking, handling, transmitting, and safeguarding FOUO material.
3.6 REPORTING REQUIREMENTS:
Contractor personnel shall report to an appropriate authority any information or circumstances of which they are aware may pose a threat to the security of DoD personnel, contractor personnel, resources, and classified/unclassified defense information. Employees shall be briefed by their immediate supervisor upon initial on-base assignment.
3.7 PHYSICAL SECURITY:
The contractor shall be responsible for safeguarding all Government property and controlled forms provided for contractor use. At the end of each work period, all Government facilities, equipment and materials shall be secured.
3.8 CONTROLLED/RESTRICTED AREAS:
The contractor shall implement local base procedures for entry to AF Controlled/Restricted areas where contractor personnel will work. An AF Form 2586, Unescorted Entry Authorization Certificate, must be completed and signed by 36 MUNS security manager before restricted area badges (RAB) will be issued. Employees must have a completed and favorable NACI investigation before receiving a RAB. Interim access can be granted in accordance with AFI 31- 501, Personnel Security Program Management.
3.9 MILITARY EXERCISES:
No compensation will be claimed for any delays resulting from re-entry procedures due to exercises.
PAUL D. LAMBERT, SSgt, USAF MSEM Production Supervisor