Questions & Answers
1. Who is the incumbent contractor?
A. The incumbent contractor is Aloha Waste Systems, Inc.
2. Do the dumpsters have to be green in color?
A. No. The color does not matter.
3. IAW the SOW, do the dumpsters have to be marked with APCSS?
A. Yes. The APCSS may be painted over/removed at the conclusion of the contract. Another type of semi‐permanent sign/decal may be used. There may be other dumpsters on/near site that belong to other agencies and this is to help ensure that the folks at APCSS utilize the correct dumpster.
4. Can the dumpster be locked?
A. No locks on the dumpsters.