Atch1_SOW AC_DC Power upgrade at Sasebo_240906 revised.pdf

PDF 2 MB Posted

Attached to
AC/DC Power Upgrade at 374 CS Sasebo Naval Base Site Japan
Solicitation number
FA520924Q0056
Issued by

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to replace existing Rectifier, Inverter, AC/DC Breakers and Power Distribution Units (PDUs) at the 374th Communications Squadron Sasebo Naval Base site in Japan. The contractor shall provide all necessary personnel, supervision, management, tools, equipment, transportation, materials and any other items or services to complete the work in accordance with the SOW and commercial/local standards.

The key requirements include removing the existing Rectifier and Inverter, installing a new 800A Rectifier, a new 5kVA Inverter, new AC breaker panels and PDUs. The work must be completed in two 30-minute power outages, with temporary power and batteries installed. The contractor shall provide an installation plan, one-line drawing, and work schedule for government approval prior to starting work. The contractor shall warrant the work and any provided equipment for one year. The government will provide facility power drawings, use of existing conduits, and designate a Government Representative. Safety management and on-site safety measures are detailed in the SOW.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ# FA520924Q0056-0002

Attachment 1

STATEMENT OF WORK

FOR

AC/DC POWER UPGRADE

AT

374CS SASEBO SITE

6 Sep 2024

374 CS/SCXR

TABLE OF CONTRNTS

SECTION 1: Description

SECTION 2: Safety Management

SECTION 3: On-Site Safety Measures

SECTION 4: Appendix Site location and Drawings

SECTION 1: Description

1. DESCRIPTION OF SERVICES. The Contractor shall provide all necessary personnel, supervision, management, tools, equipment, transportation, materials and any other items or services necessary to replace existing Rectifier in bldg1536A, Inverter and 9 each of PDUs in Bldg1536 374th Communications Squadron Sasebo Naval base site, in accordance with (IAW) this Statement of Work (SOW) and in accordance with commercial practice and local standards.

1.1. DESCRIPTION OF REQUIREMENT.

1.1.1. The Contractor shall perform the work as outlined in section 1.2. and 1.3. to remove, install, and set-up Rectifiers, Inverter and PDUs at the specified locations.

1.1.2. The Contractor shall provide an installation plan, one-line drawing and work schedule that is subject to Government approval, prior to commencement of work.

1.1.3. The Contractor shall ensure that the job site is ready and available for performance of the work prior to the commencement of the replacements.

1.1.4. The Contractor shall warrant this work and any contractor-provided equipment for One year from the date of the acceptance by the Government.

1.1.5. The Government shall provide equipment facility power drawings and the use of preexisting data and power conduits. The Contractor can use existing power and cables in conduits if desired.

1.1.6. Government Representative (GR):

The authorized primary GR for this contract is Mr. Akihiro Kobayashi, 374 Communications Squadron (CS) /SCXR, DSN: 315-225-7791, akihiro.kobayashi.1.jp@us.af.mil.

Mr. Kobayashi shall be the quality assurance inspector and provide the Contractor with required information and assistance for this project.

1.1.7. New Rectifiers

The New Rectifiers shall be meet the following requirements.

Manufacture Any (GS Yuasa Battery, Model No: PR-FW TWRU 4100X8 or Equivalent)

AC input Phase: 3ph 3w Frequency: 60Hz Voltage: 208V + or – 10% Max input capacity: 26.5kVA

Rating Cooling system: Forced air convection Control system: Transistor switching mailto:akihiro.kobayashi.1.jp@us.af.mil

DC Output Float charge voltage: 53.5V + or – 2% Rated current: 800A (100A x 8units, Max capacity 400A redundant system) Dropping current: Rated current x 110% or less Ripple voltage: 200mV or less Efficiency: 85% or more Power Factor: 98% or more

Load Voltage Compensator System: Silicon dropper Input voltage: DC53.5V Max Load current: DC10A ~ 400A

1.2. Remove Existing Rectifier and Inverter

The Contractor shall remove old systems as shown below.

Rectifier: Furukawa Battery type, DP5048-400/0800SMNS Inverter: Sanyo Denki SANUPS DA10SR

1.2.1. Temporary Rectifier

Contractor shall install temporally rectifier and batteries to meet the current site load during the replacement.

1.2.2. New Inverter

The New inverter shall meet the following requirements.

Manufacture Any (SANUPS DA10SR or Equivalent)

DC input Voltage: 48V (40.5V ~ 51V) Input current: 115A Max Input current: 135A

Rating Cooling system: Forced air convection

AC out put Capacity: 5kVA Voltage: 120V + or – 5% Power factor: 0.9

1.2.3. New Panel and Breakers

The new panel and breakers shall meet the following requirements.

Manufacturer (AC Panel) Any (Eaton CCHPM124 Main Breaker Load center or equivalent)

Manufacture (AC Breakers) Any (Mitsubishi WS-V series or equivalent)

New breakers are

a. A/C breaker panel for new Inverter

i. 1x 100A main breaker

ii. 10x 20A breakers for each new PDU/rack

1.2.4. PDUs

Manufacture Any (EATON EBA201-10 or Equivalent)

Outlet type: NEMA 5-15R or 5-20R Outlets: 12 (minimum) Voltage: 120/240V 24A Form Factor: 0U, Vertical

Note:

The PDUs must be mounted in the rear of each rack with at least 12 outputs. The PDU input can be hardwired directly to the panel or a plug. If the PDUs use plugs, individual outlets will have to be run to each rack from the panel. Input outlets must have a locking receptacle such as a NEMA L5-30R. The PDUs should not be software managed.

1.2.5. Power outage

Power outages will be allowed 2 times 30 minutes during the construction period.

1.2.6. Turn-in old Rectifier

The contractor shall turn-in old Rectifier to DRMO office located in Building 323 Sasebo.

1.3. Steps of the replacements

The Installation procedure shall be;

a. Install New inverter next to the existing inverter units.

b. Install AC breaker panel next to the existing AC breaker panel in bldg. 1536.

c. Install new PDUs for each rack.

d. Install new wires from new AC breaker panel to each PDUs.

e. Install temporally rectifier and batteries on to the front of main panel in bldg. 1536A.

f. 1st Power outage (30 minutes)

g. Re-wire existing AC input to new AC bleaker panel and DC input to new inverter and re-wire existing DC load to the temporally rectifier. (new inverter and PDUs installation have completed)

h. Unplug from old PDUs to new. (Done by Government personals)

i. Commercial power back online. (1st power outage is over)

j. Remove existing 400A rectifier.

k. Install New 800A where 400A was.

l. 2nd power outage (30 minutes)

m. Re-wire DC load from temporally rectifier to New 800A rectifier.

n. Commercial power back online. (2nd power outage is over)

o. Remove temporally rectifier and batteries.

1.4. RESPONSIBILITY FOR DAMAGES. Any damages caused to U.S. Government property during the course of performing this contract shall be restored, replaced and/or repaired to its original condition at no additional cost to the U.S. Government by the Contractor.

1.5. DISPOSAL MATERIAL. All work shall be performed in a safe and orderly manner. All old wires, conduits, old fuel line debris, trash and leftover materials, etc., shall be removed from the job-site by the Contractor in accordance with Japanese regulation, Article 3 of “Law of Disposal and Clearing of Waste (Haikibutsu no shori oyobi seisou ni kansuru horitsu)” and local regulations.

1.6. UTILITIES. Water, electricity, and sewage, where available from existing work sites, will be provided to the Contractor without cost.

1.7. HOURS OF OPERATION. The Contractor shall perform the service from 0730 to 1600, Monday through Friday including Japanese Legal Holidays, but excluding the following U.S. Legal Holidays. Holiday falling on a Saturday may be observed on the preceding Friday. Holidays falling in Sunday may be observed on the following Monday

U.S. HOLIDAYS:

1 January New Year's Day 3rd Monday of January Martin Luther King, Jr’s Birthday 3rd Monday of February Washington's Birthday Last Monday of May Memorial Day

19th June Juneteenth National Independence Day 4th July Independence Day 1st Monday of September Labor Day 2nd Monday of October Columbus Day 11th November Veterans Day 4th Thursday of November Thanksgiving day 25th December Christmas Day

SECTION 2: Safety Management

374CS/SCXR will take responsibilities in establishing the environment in which the contractor can develop and successfully manage the occupational safety and health program focusing on reduction of occupational fatalities, injuries and illness. The safety and health management for the construction sites will be maintained and ensured by conducting proper and solid daily activities of safe construction cycle operations.

We are aware of the importance in providing the construction service in which the requirements of Army Corps Engineering Manual 385-1-1, Japanese Safety and Health Regulations, and local regulations are strictly complied. Thus, we prepare and implement the site specific plans, understanding requirements for health control and management, training practice, requirements for equipment, requirements for facility, and assigning of work qualified personnel for each work. In the management of safety and health at the construction site, we have emphasized following point of concerns;

• Preparation of safety and health management plan

• Reformation of excessive multi-subcontracting -Clarification of who is responsible for conducting an occupational accident prevention activity.

-Acknowledgement by prime contractor of the subcontracting company and the workers.

• Preparation of work procedure plan.

• Installation and operation of council organization.

-Coordination and communication between two or more construction.

• Patrol of project site.

• Initial site administrative training.

• Pre-construction meeting for safety and health.

• Implementation of safe construction cycle operations

• Installation of supervisor (competent person) meeting.

• Responsibilities of subcontractors (involvement to preparation of work procedure plan, installation and operation of council organization)

At the construction site of contract projects, multiple contractors of prime contractor, sub- contractors, and secondary sub-contractors are conducting each task mixed at the same location, it makes safety and health management more difficult and complicated;

therefore, we are committed to prevent the occupational accident be attributed by such conditions. The safe construction cycle operation (SCCO) is to be applied to daily work of site construction. As for the management in providing safety and health environment throughout the entire projects, 374CS/SCXR is also committed to implement the systematic construction management procedures. All the project staff including the sub-contractors has responsibility to meet at once before the construction starts, and discuss a work flow and schedule.

COMPLIANCE WITH FEDERAL OHSA AND EM 385-1-1.

A compliance with the requirements will be ensured by entire workforce of the company. 374 CS/SCXR has been conducting various projects for the 374CS in the past. We have been studying the requirements, developing the safety management system and training the employees on the accident prevention planning. As a result, we have successfully completed past performances without any severe occupational injury or fatality. Therefore, this company is dedicated to remove such an event by strictly complying with the OHSA and EM385-1-1. Requirements.

SECTION 3: On-site safety measures

For Workers All the works are executed in accordance with EM 385-1-1, Safety and Health Requirements Manual.

Meeting is held each day before starting work to ensure safety and health of workers.

Workers shall wear/put work clothes properly for the prevention of injury.

For Working Site All the works are executed in accordance with NFPA 241, Safeguarding Construction, Alteration, and Demolition.

Working site shall be ensured for the protection of passersby.

For Storage Space All the materials including ladders and tools are covered by a curing sheet after completion of daily work.

For Ladder Hold the ladder when worker access the ceiling.

For Welding & Sanding Hot work permit is required prior to conducting work.

Watch man is assigned to monitor the site for 30 minutes after the completion of work to make sure of safety.

For Vehicle Use All of our contractors while driving vehicles on Fleet Activities SASEBO must follow the traffic rules.

Environmental Protection Materials are covered and protected by barricade to prevent third party entry.

Waste materials are disposed of in accordance with Japanese law and applicable laws.

Section 4: Appendix Site Location and Drawings

BLDG1536

Detailed Site Location

Appendix 1: Drawing AC DC panel locations

DC Panel C

DC Panel A

DC Panel B

AC Panel

AC/DC panel location

Appendix 2: Inverter location

Inverter

Inverter Location

Appendix 3: Rectifiers location

U.S. HOLIDAYS:
For Workers
For Working Site
For Storage Space
For Ladder
For Welding & Sanding
For Vehicle Use
Environmental Protection

File details come from the government source that posted it. Updated .