Text version
DEPARTMENT OF THE AIR FORCE
35TH FIGHTER WING (PACAF)
MISAWA AIR BASE, JAPAN
7 Nov 2017
MEMORANDUM FOR ALL PROSPECTIVE OFFERORS
FROM: 35th Contracting Squadron, Construction Flight
Bldg. 656, Misawa Air Base
Misawa-shi, Aomori-ken, Japan
SUBJECT: Pre-proposal Conference Minutes & Record of Site Visit, RFP No. FA520518R0001, Simplified Acquisition of Base Engineer Requirements (SABER) Indefinite-Delivery /
Indefinite-Quantity (IDIQ) Contract, Misawa AB, Japan
1. This is a minutes of the pre-proposal conference for subject solicitation, including record of site visit, as conducted on 7 Nov 17 by the 35th Contracting Squadron IAW the solicitation provisions AFFARS
5352.215-9001 Notice of Pre-bid/Pre-proposal Conference and FAR 52.236-27 Site Visit
(Construction). 11 firms’ representatives, totaling 31 individuals attended this conference/site visit.
The following are names of the firms and the Government representatives attended:
Firms (in alphabetical order)
Government
American Engineering Corporation.
Mr. Yamamoto, Director of Contract Policy, 35 CONS/CCE
Aptim
Mr. Nogawa, Chief, Construction Flight, 35 CONS/LGCA
Fujimoto Kensetsu, K.K. Mr. Kawahara, Buyer, 35 CONS/LGCA
Kamikita Kensetsu Co., Ltd.
Mr. Nakamura, Buyer, 35 CONS/LGCA
Nihon Urban Development Project Corporation. Mr. Ishikawa, Buyer, 35 CONS/LGCA
Nippo Corporation Mr. Fujioka, Civil Engineer, 35 CES/CENM
Nishimatsu Construction Co., Ltd. Mr. Anzai, Electrical Engineer, 35 CES/CENM
Oyama Kensetsu Co., Ltd Mr. Harada, Mechanical Engineer, 35 CES/CENM
Seikitokyu Kogyo Co., Ltd. Mr. Nakanowatari, Architectural Engineer, 35 CES/CENM
Suzuki Kensetsu Kogyo Co., Ltd. Mr. Matsunai, Government Inspector, 35 CES/CENM
Tanakagumi Co., Ltd.
2. Pre-proposal conference.
a. The conference was opened by Mr. Kawahara/Buyer at 1300 hours, who explained the scope and requirements, and remarks/filling instruction of the solicitation by presenting the Slide Show, Attachment 1. All attendees were allowed to ask questions at any time during the session.
Highlights of the explanation:
General Requirements
Price Coefficients and Task Order Pricing
Task Order Issuance Procedure (Task Order based contract)
Contract clauses and solicitation provisions
Other contract requirements
Fill-ins, representations, and certifications
Preparation of technical proposal, price proposal and past performance information
Evaluation factors and procedures
Written question submission due date/time
Proposal submission due date/time
b. Technical briefing was made by Mr. Fujioka/Civil Engineer with regard to the technical specifications and unit price book.
Highlights of the technical briefing:
(i) Technical Specifications.
Section 01010, General
Cross Reference between Technical Specifications and Unit Price Book (para. 1.2)
Unit Price Book (para. 1.3)
Non-Price Items (para. 1.4) – minimum use, historically 1 or 2 items per year
Hours of Operation (para. 4.1)
Legal Holidays (para. 4.2)
Availability of the Base Entry Gate (para. 4.5)
(ii) Unit Price Book.
Structure of Unit Price Book
Regular Time/Non-Regular Time Unit Price
Demolition Rates
c. Question and Answer: See Attachment 2, Summary of Questions & Answers.
3. Site Visit. Following the pre-proposal conference ended at 1400 hours, the site visit was conducted at the project sites on-going and previously completed.
a. Mr. Fujioka made on-site briefing to all attended prospective offerors in regard to the typical
SABER construction requirements.
b. No particular questions were arisen during the site visit.
4. At the end of the site visit, Mr. Kawawhara reminded all attendees that the terms of the solicitation including all attachments remain unchanged unless the solicitation is amended in writing. The prospective offerors’ question(s) for this solicitation, if it may arise after this pre-proposal conference and the site visit, must be submitted to 35 CONS in writing no later than 1100 hours on 10 Nov 17. The proposal submission closing date/time is at 1400 hours of 30 Nov 17 Japan Standard Time (JST). The site visit was adjourned at 1445 hours on 7 Nov 17.
KAZUAKI KAWAHARA
Buyer
SATOSHI NOGAWA
Chief, Construction Flight
2 Attachments:
1. Slide Show, 23 Slides (6 pages).
2. Summary of Questions & Answers, 1 page.
People – Mission – Security
I n t e g r i t y - S e r v i c e - E x c e l l e n c e
35th Fighter Wing
Pre-Proposal Conference / Site Visit
Simplified Acquisition of Base Engineer Requirements (SABER) IDIQ Contract
RFP No. FA520518R0001
Starting 1300 hrs, 7 Nov 2017
Bldg. 656, Misawa AB, Japan
1 People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Summary
Scope & Requirements General Requirement / Pricing Structure
RFP
CONS remarks for solicitation / filling Instructions
CES tech briefing (Specs and UPB)
Q & A session
Site Visit
People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Description Work:
Broad range of construction (maint/repair, minor const) at Misawa AB, per Task Order.
Place: Misawa AB and locations within 40km radius from Misawa AB, including Draughon Range & Hachinohe Fuel Terminal.
Contract Type: Fixed-Price with Economic Price Adjustment (FP-EPA), Indefinite-Delivery/ Indefinite- Quantity (IDIQ) Contract.
Type of Award: Single Award
3 People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Period: 1 Basic Period + 4 one-year Options with 6 Months Option to Extend Services
Basic Year: 19 Jun 2018 to 18 Oct 2019
Option Year One: 19 Oct 2019 to 18 Oct 2020
Option Year Two: 19 Oct 2020 to 18 Oct 2021
Option Year Three: 19 Oct 2021 to 18 Oct 2022
Option Year Four: 19 Oct 2022 to 18 Oct 2023
Value: Guaranteed Minimum ¥50,000 ($449) Contract Maximum Limit
¥6,000,000,000 ($53.9M)
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Fill-in
5 People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Section B, Page 3
Price Coefficients Fill-in
People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Task Order Pricing Base on the L/I prices in the Unit Price Book (UPB)
(A) Extended Price: L/I price x Qty
(B) Total Direct Cost: The sum of (A)
(C) Price Coefficient: Select Coefficient for (B)
(D) Grand Total of the Project (TO Amount):
(B) x (C)
4 People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Sample Scope of Work
Project Title: PARKING APRON DEMOLITION &
REPAIR
1. Repair parking aprons.
2. Remove five existing concrete slabs and replace with 3,000 PSI concrete.
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
UPB Calculation Samples
4 People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Section F:
52.211-12 Liquidated Damages
@¥41,882 (1st day ) & @¥15,161 (2nd day ~ ).
Section I:
FAR 52.223-3 Hazardous Material
Fill-in
People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Section J
Exhibit / Attachment Table Atch 1 Other Contract Requirements
Atch 2 Volume I, Technical Specifications
Atch 3 Volume II, Unit Price Book
Atch 4 Task Order Procedure Flow Chart
Atch 5 Historical Data
Atch 6 Past Performance Questionnaire
13 People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Other Contract Requirements (RFP Atch 1) B001 Description of Work
All TOs to be issued on a Japanese Yen Basis
SABER focused task-force organization
H002 Required Insurance Property Damage ¥2,000,000
H003 Performance Bond Required 100% of TO > $150K.
Required add’l if Mod > $10K.
Submit <= 21 CD from TO / Mod award.
H004 Task Order Issuance Procedures
H006 Economic Price Adjustment (EPA)
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Section K FAR 52.204-8 Annual Representation Cert 52.204-17 Ownership or Control of Offeror 52.204-20 Predecessor of Offeror
FAR 52.209-7 Responsibility Matters Info
DFARS 252.247-7022 Transportation by Sea
Other Contract Requirements K001 Tax Exemption under SOFA
K002 Contractor’s Cert
Fill-in
Fill-in
Fill-in
Fill-in
Fill-in
Fill-in
Fill-in
14 People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
(Other Contract Requirements cont’d)
K003 CONSTRUCTION CONTRACTOR LICENSE
Offeror shall submit “special construction license” under the Japanese Construction Business Law together with offer, to demonstrate compliance with FAR 52.236-7 as modified & DFARS 252.225-7042.
Joint venture or Partnership - the special construction license of each member of the JV or each partner of the partnership must be submitted together with offer.
Such offeror that fails in representation of the above required license will not be considered for award.
Submit
People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Section L L-100 Proposal Preparation Instructions Offer required to meet all sol. requirements, terms & conditions, reps & certs, & tech requirements.
Prepare & Submit:
Tech Proposal: 1 Original + 4 copies Sub-factor 1: Special Const. License issued by the GOJ or its subdivision, for offeror and each member of the JV if formed (See
Atch 1, Other Contract Requirements, paragraph 8, K003)
Sub-factor 2: Resumes and Licenses of Project Manager
Sub-factor 3: Resumes and Licenses of CQC System Manager
(See M-900.A. for minimum qualifications)
16 People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
(Sec L cont’d)
Price Proposal: Submit 1 Original + 2 copies
Past Performance Information (PPI): 1 Original + 4 copies No more than 5 pages per contract.
(a) Quality and Satisfaction Rating of Contracts
(b) Questionnaires (RFP Atch. 6)
POC submit directly to the Gov’t – NOT BACK TO THE
OFFEROR
Ensure POC be reachable by phone and/or e-mail, Gov’t will contact them.
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
(Sec L cont’d)
PPI, continued
(c) Past Performance Information:
List of no more than 5 most relevant contracts.
Recency: Within 3 years from the RFP issue date (30 Oct 2017).
Relevancy: Similar scope, magnitude of effort, and complexities to that required by RFP.
18 People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Section M
M-900 Basis of Award & Evaluation
Weight of Importance:
Combined Past Performance and Technical Acceptability is approximately equal to price.
Evaluation Process:
Technical
Acceptability – Acceptable or Unacceptable
Risk – Low, Moderate, High or Unacceptable
People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
(Sec M cont’d)
Evaluation Process, continued
Price – Fair and Reasonable
- See M-900.C. Gov’t will evaluate offers by adding all options.
Past Performance – Recency and Relevancy
20 People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Civil Engineer Technical Briefing
Attachment 2: Technical Specifications Attachment 3: Unit Price Book
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Questions
22 People – Mission – Security
RFP No. FA520518R0001 SABER IDIQ - Pre-Proposal Conference
Let’s move on to Site Visit but please remind
RFP Closing Date / Time:
30 Nov 2017 / 14:00
Questions shall be submitted to 35 CONS/LGCA by NLT 10 Nov 2017 / 11:00.
SUMMARY OF QUESTIONS AND ANSWERS
RFP No. FA520518R0001
SABER IDIQ Contract, Misawa AB, Japan
Attachment 2 to Pre-Proposal Conference Minutes & Record of Site Visit
Questions and Answers at Conference:
Q1: When the contractor estimates the project construction cost based on the Unit Price Book
(UPB), should every single work item be selected for each work?
A1: The UPB provides 10,076 pre-priced work items for single work as well as combination of works. For selection of the work items, the contractor will be required to refer to applicable sections of the specifications that are corresponding to the UPB.
Selection of the work items is negotiable per individual project, but not the UPB item prices.
Q2: Are the prices in the UPB based on the
U.S. materials?
A2: The work item prices in the UPB are generally based on Kensetsu Bukka (Construction and Material
Costs in Japan, published by the Construction
Research Institute, a nonprofit organization registered to the Government of Japan) as adjustments have been made for local area. When the U.S. materials are required in the project(s), the list will be provided to the contractor, and such work item prices in the
UPB are based on the U.S. materials.
Q3: The submission due date for questions to this solicitation is 10 Nov 17 on the U.S. legal holiday. Is the date correct?
A3: Yes, 35th Contracting office will be opened by
1100 hrs on 10 Nov 17, the due date and time indicated in RFP. Submission of the questions via e-mail is acceptable. (For submission of proposals, refer to RFP, Section L, para. L-100.)
| 2017-11-16T09:03:43+0900 | |
| NOGAWA.SATOSHI.1288348037 |
| 2017-11-16T08:53:21+0900 | |
| KAWAHARA.KAZUAKI.1288488637 |