Attachment 3- Revised Performance Work Statement.pdf

PDF 342 KB Posted

Attached to
Hydro Axe Removal Services
Solicitation number
FA500425Q0043
Issued by

About this file

This Performance Work Statement (PWS) outlines brush and tree clearing services for Eielson Air Force Base and Birch Lake Military Recreation Camp in Alaska. The contractor must provide labor, equipment, and materials to clear approximately 25-50 acres of power line and pipeline right-of-ways, creating 60-foot wide corridors at Eielson AFB (30 feet on each side) and 40-foot wide corridors at Birch Lake (20 feet on each side). The primary objectives are to prevent trees from contacting high-voltage overhead power lines, maintain power line right-of-ways, and ensure access for JP8 pipeline maintenance supporting flying missions.

Key performance requirements include cutting trees 6 inches in diameter and larger at 4 feet above ground, stripping and stacking larger trees in designated locations, and mulching remaining vegetation to no more than 2 inches in diameter. The work is to be performed between August 1-September 30, 2025, with daily operations from 0700-1900 hours. The solicitation is set aside for small businesses under NAICS code 561730 (Landscaping Services), with a mandatory site visit scheduled for July 14, 2025, and proposal submissions due by July 22, 2025. Contractors must comply with base security protocols and obtain proper access passes for working in different security zones within Eielson Air Force Base.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PEFORMANCE WORK STATEMENT FOR

BRUSH AND TREE CLEARING

Performance Work Statement

Brush and Tree Clearing at Eielson Air Force Base, Alaska

1 June 2025 a

Section I Description of Needs

1. Introduction:

1. Description of Service. Contractor to furnish all labor, transportation, materials, engineering and equipment to perform brush and tree clearing services on Eielson AFB to include services at Birch Lake Military Recreation Camp.

1a. Eielson AFB and Birch Lake has approximately 25 acres, not to exceed 50 acres of power line and pipeline, right of ways, that require hydro axed to prevent trees from coming into contact with the high voltage overhead power lines and to keep power line right of ways clear for maintenance purposes. Additionally, maintenance access needs to be made to conduct maintenance and repairs to the JP8 pipeline fueling systems supplying fuel to the flying missions. These rights of ways need to be hydro axed to an overall width of 60ft, 30ft on each side of the pole or pipeline, with the exception of Birch Lake Military Recreation Camp.

That area will be 20 feet on each side of the lines. These sections around Eielson, which will be included in the map section, are around power lines or future power lines and pipelines that require hydro-axing. The total area for the service is approximately 25 acres, not to exceed 50 acres between the two locations. See attachment, Maps, for required land coverage.

1.2. Scope of Work. Eielson AFB Power Line Utility Right-of Ways- All trees 6 inches in diameter and larger at 4 feet above the ground shall be cut, stripped (de-limbed) and stacked in a Government specified location near the site. That area will be marked to identify its location. For all locations, the wood will be placed within each cutting section safely off the road and placed so it will not hinder base operations. All other vegetation (tops, branches, stumps and brush) that can be cleared shall be mulched and pulverized to no more than 2 inches in diameter and left spread on site (see appendix 6.1 A for pictures). The contractor shall ensure that mulched and pulverized (no shavings larger than 2 inches in diameters) material has been leveled. The hydro axing must follow the power lines, unless otherwise marked, with no deviations to the route permitted. The map will be followed, and any questions will be clarified before cutting any trees.

Any debris tossed onto the roads from contractor machinery must be cleared off the roads by the end of the workday. The contractor must make every effort so that no trees are damaged outside the tree cutting line. The contractor will be responsible for removing any damaged trees outside the cutting line upon Government inspection at no additional cost to the Government.

The contractor shall use industry standard means to include the use of, but not limited to, heavy equipment (excavator, dozer, skid steer, trucks, etc.) and handheld equipment (chain saws, grinders, handheld tools, etc.) to perform brush and tree clearing services. The contractor will furnish all equipment and personnel needed to remove any debris from paved areas during hauling or clearing activities.

Government Special Instructions, Terms and Conditions

2. Government Furnished Equipment/Property:

2.1. Government Furnished Equipment and Property. The Government will not furnish any facilities or equipment for any work that needs to be accomplished in this Performance Work Statement. The contractor shall furnish all the supplies needed to fulfil this contract according to all its terms.

2.2. Emergency Service. The government will provide emergency services and emergency medical treatment for Contractor personnel who are injured or become critically ill while at Eielson AFB. The contractor will be required to transport injured or ill personnel to the appropriate medical treatment facility. Treated personnel will be responsible for reimbursing the government for the cost of medical treatment and patient transportation. For all emergencies using an on-base phone, please dial 911. If using a cell phone, please dial (907) 377-5130 (Security Forces Law Enforcement Desk/BDOC). Fire emergencies/routine calls can also be reported to the aforementioned phone numbers.

2.3. Telephone. The government shall not provide telephone services. If available, the contractor may use government phones in case of emergencies during field and site work. No long-distance telephone calls will be authorized.

3. General Information:

3.1. Hours of Operation. Working hours for the contractor shall normally be between the hours of 0700-1900, 7 days a week, excluding Federal Holidays. If the Contractor desires to work during periods other than above, a government representative may need to be present. The Contractor shall make his/her request to the Contracting Officer five (5) calendar days in advance of his/her intention to work during other periods to allow assignment of a government representative. If such force is reasonably available from assigned contract administrators or quality assurance personnel, the Contracting Officer may authorize the contractor to perform work during periods other than normal duty hours/days.

3.2. Disposition of Waste, Excess, Scrap, and Salvage Materials. The title to all waste, excess, and scrap generated as a direct result of this contract is vested in the Contractor - unless specifically identified below. Further (unless listed below in exceptions), these materials shall be disposed of off the Base by the Contractor in accordance with all applicable Federal, State, and Local Regulations.

Following is a list of materials (Exceptions) that will be generated as a result of this contract and shall be turned-into the Government at a location at Eielson AFB designated by the Contracting Officer.

Exceptions: All trees 6 inches in diameter and larger at 4 feet above ground shall be cut, stripped (de-limbed) and stacked in a Government specified location near the site.

3.3. Power Lines. If the contractor breaks any of the power lines, or power line hardware in the area, the work will stop immediately, and the contractor must contact the customer at (907) 377-2100. All work must cease in the general area until the power lines are repaired.

3.4. Clean Up. The Contractor shall, at all times, keep the construction site and storage area(s) free from accumulation of waste, rubbish, or construction debris.

All loose or lightweight materials shall be secured to prevent blowing or scattering. The burning of trash or construction debris is strictly prohibited. Prior to final inspection, the Contractor shall remove all construction debris, tools, equipment, and materials that are not the property of the Government. Upon completion of the work, the Contractor shall leave the work site and storage area(s) in a clean, neat and workmanlike condition satisfactory to the Contracting Officer.

3.5. Hazardous Materials. The contractor shall comply with base regulations regarding Hazardous Material (HAZMAT) for all issues of hazardous material, and ensure procedures meet all applicable policies, publications, and protocols in this contract. Provide Bio-Environmental Engineer Service with a Material Safety Data Sheet (MSDS) on all first-time purchases of hazardous items obtained through local sources of supply and obtain approval prior to purchase.

3.6. Government Remedies. The contracting officer shall follow the requirements of FAR 52.212-4, Contract Terms and Conditions for Commercial Items (Feb 2007), for contractors’ failure to correct nonconforming services.

4. Security Requirements:

4.1. Levels of Security. Eielson AFB security may be viewed as being one of three broad levels, the level in effect being dependent on the location or AREA of Eielson AFB in question.

4.1.1. The lowest level of security exists in “GENERAL ACCESS” areas.

These areas are all Eielson AFB outside of the "USAF Controlled" and "USAF Restricted" areas.

4.1.2. “USAF Controlled” access areas are the mid-level security areas.

Presence within the CONTROLLED ACCESS AREA is by authorization;

however, the movement of authorized personnel in and out of these AREAS is generally not impeded.

4.1.3. The highest level of security on Eielson AFB is that within the “USAF RESTRICTED AREAS”. These areas are subdivided to be known as Protection Level 1, 2 or 3 AREAS. Work schedule requests or changes to existing schedules for work to be performed in a “USAF RESTRICTED AREA” shall be submitted at least 7 calendar days in advance for approval and coordination of Eielson AFB Security Forces.

4.2. Base Access. The Contractor shall be responsible for and shall pay for obtaining all necessary clearances, cards, passes, decals, or other items required for access of Contractor personnel and vehicles to the base or other areas where work will be performed. The Contractor shall be required to apply for vehicle and personnel identification media at the Base Pass and Registration Section (Visitor Control Center). Upon Completion or termination of the contract, the Contractor shall ensure all vehicle and personnel identification media are surrendered to the Base Pass and Registration Section (Visitor Control Center). The Contractor shall obtain the following pass and identification items: Eielson AFB Vehicle Pass.

For all further inquiries, please contact the Visitor Control Center at (907) 377- 3807. The Contractor will be responsible for contacting U.S. Army Range Control at (907) 353-1266, prior to and leaving the work site each day and for access to the Yukon Training Area.

4.2.1. The Contractor shall maintain a current listing of employees. The list will include employee names, last four digits of social security numbers, and driver license numbers. This list shall be provided to the Contracting Officer (CO), and servicing Security Forces organization. An updated listing shall be provided upon change of employees. The Contractor must provide all names, last four digits of social security numbers and duty hours of all personnel who will be on site at the start or anytime during this project for identification purposed in case of emergencies to base security.

4.3. Employee Listing. The contractor shall maintain a current listing of employees. The list will include employee names and date of birth. This list shall be provided to the contracting officer and servicing security forces organization.

An updated listing shall be provided upon change of employees. The contractor must provide all names, social security numbers and duty hours of all personnel who will be on site at start or anytime during this project.

4.6. Performance of Services During Crisis Declared by the National Command Authority or Overseas Combatant Commander. During times of crisis or national emergency, the contractor shall continue to provide services as scheduled, with minimal disruption of services if directed by a contracting officer.

5. Miscellaneous:

7.1. Use of cell phones while operating any motor vehicle on base is strictly prohibited. Driving privileges will be suspended for 30 days for the first violation.

7.2. The on-base speed limit while passing military troops performing physical training is 10 MPH and is strictly enforced.

7.3. REAL ID: The contractor will maintain a current list of employees. The list will include employee names along with information required in the REAL ID.

REAL ID compliance information website:

https://www.dhs.gov/real-id-enforcement[1]brief

This list is required to be provided to the Contracting Officer and the servicing Security Forces organization, to include updated copies for any changes during the duration of the contract

6. Appendices: