STATEMENT_OF_WORK_SCBA_COMPRESSOR.pdf
PDF 13 KB Posted
- Attached to
- SCBA Air Compressor
- Solicitation number
- FA500419QA020
About this file
contractor shall follow SOW.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Salient_Characteristics_SCBA_COMPRESSOR.pdf | ||
| Solicitation_-_FA500419QA020.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
The contractor shall provide all tools, equipment, labor, materials, and transportation necessary to provide these requirements.
1. LOCATION:
The equipment shall be supplied FOB destination, Eielson AFB, AK. The vendor shall be responsible for freight cost to Eielson AFB, AK. The vendor shall be responsible for system startup & training by a factory-certified technician on site at Eielson AFB
2. SUPPLY:
Contractor shall supply tools/equipment for requested trainer for Eielson Fire Department.
3. INSTALLATION:
The contractor shall install all necessary equipment to complete the requirement. A Government POC for 354 CS will be supplied by upon contract award. The installer shall validate the system performance is in full working condition upon completion of the contract. The contractor shall liaise and coordinate with the government POC – Marc Hughes, 354 CES/CEF. Contact details shall be given upon award.
4. DELIVERY:
Delivery and Installation shall take place during the scheduled times and dates coordinated with the Government POC. Delivery and Installation shall be completed within 60 calendar/ business days from contract award, in building 1206, Eielson AFB.
5. QUALITY ASSURANCE/COMPLIANCE:
The government shall periodically inspect the contractor during installation. Any discrepancies discovered will be reported to the contractor for remedial action. Any remedial action will be carried out prior to the performance period ending or earlier depending on the nature of the discrepancy. The government representative will have the final decision on the acceptance of work carried out and any remedial action conducted.
6. GENERAL INFORMATION:
The contractor and the government representative will work closely to ensure that the final installation of the equipment is fully operational and is 100% compatible of meeting the department needs.
The contractor shall provide all tools, equipment, labor, materials, and transportation necessary to provide these requirements.