Site_Visit_Questions.pdf
PDF 11 KB Posted
- Attached to
- Land Clearing and Grubbing Federal contract opportunity
- Solicitation number
- FA5004-19-Q-A004
About this file
Site Visit Questions
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Blair_Lakes_Hydroaxe.pdf | ||
| Attachment_2_SOW_REVISED.pdf | ||
| Q&A.pdf | ||
| Attachment_2_SOW_REVISED.pdf | ||
| Attachment_2_SOW.pdf | ||
| Attachment_1_Pricing_Schedule.pdf | ||
| Attachment_3_Wage_Determination.pdf | ||
| Attachment_2_Statement_of_Work.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Visit Questions
1. When is this project due to start? As soon as the contract gets awarded the project can start, the sooner the better due to weather.
2. Is there a requirement for crew size? No
3. Is there a time frame? From contract award date to 1 Mar , I don’t know what the weather is going to do, putting the Gov’t at risk is not something we should do.
4. How would you get the equipment out there? That will be the route that we take this morning for the site visit.
ALL OTHER QUESTIONS MUST BE SUBMITTED BY 14 JAN 2019 AND WILL BE
POSTED NO LATER THEN 16 JAN 2019.