JA-5_Appx_4_Tab_02 _Recommendations.pdf

PDF 8 KB Posted

Attached to
Maintain Turbine-Generator #3
Solicitation number
FA5004-15-R-C008_FTQW_16-1026_Maintain_Turbine
Issued by

About this file

JA-5 Appx 4 Tab 2

View the file

Other files

File Type Posted
JA-1_Specifications_13_Jul_15.pdf PDF
FA5004-15-R-C008-0002.pdf PDF
Site_Visit_Attendance_Sheet_24_July_15.pdf PDF
0001_Q A__1.pdf PDF
JA-5_Appx_4_Tab_17 _Control_Panel.pdf PDF
JA-5_Appx_4_Tab_13 _Generator.pdf PDF
JA-5_Appx_4_Tab_08 _Diaphragms_Part_1.pdf PDF
JA-5_Appx_4_Tab_12 _Control_System.pdf PDF
JA-5_Appx_4_Tab_09 _Packing _Seals _Air_Ejection_ _Gland_Seal_Cond.pdf PDF
JA-5_Appx_4_Tab_08 _Diaphragms_Part_3.pdf PDF
JA-6_Past_Performance_Evaluation_Cover_Letter.pdf PDF
JA-11_AF_Form_66.pdf PDF
JA-5_Appx_4_Tab_10 _Oil_System.pdf PDF
JA-5_Appx_4_Tab_07 _Turbine_Rotor.pdf PDF
JA-12_AF_Form_3000.pdf PDF
JA-7_Past_Performance_Questionnaire.pdf PDF
JA-9_Financial_Reference_Sheet.pdf PDF
JA-2_Appx_1 _Inspections.pdf PDF
JA-3_Appx_2_-_Photos_w_notes_v2.pdf PDF
JA-13_AF_Form_3064.pdf PDF
JA-10_Wage_Determination.pdf PDF
JA-5_Appx_4_Tab_06 _Case _Cond_Level_ _Atm_Relief.pdf PDF
JA-5_Appx_4_Tab_14 _Alignment.pdf PDF
JA-5_Appx_4_Tab_15 _Start-up.pdf PDF
JA-5_Appx_4_Tab_01 _cover_ _contents.pdf PDF
JA-5_Appx_4_Tab_04 _T T_ _Non-return_Valves.pdf PDF
JA-5_Appx_4_TG_3_READ_ME.pdf PDF
JA-5_Appx_4_Tab_11 _Bearings.pdf PDF
JA-1_Specifications_13_Jul_15.pdf PDF
FA5004-15-R-C008_13_July_15.pdf PDF
JA-4_Appx_3 _TG3_O M_Excerpts.pdf PDF
JA-5_Appx_4_Tab_05_V-1_ _V-2_Valves.pdf PDF
JA-5_Appx_4_Tab_03 _Vibration_ _Run-out.pdf PDF
JA-5_Appx_4_Tab_08 _Diaphragms_Part_2.pdf PDF
JA-5_Appx_4_Tab_16 _Hot_Well_Pumps.pdf PDF
JA-8_Past_Performance_Worksheet.pdf PDF
JA-14_AF_Form_3065.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TETRAD Services Inc. 960 Diamond Ave. Red Bluff CA. 96080

RECOMMENDATIONS

1. Repair of torn insulation blankets. DONE

2. Repair of the steam lube oil pump bearings and journals. DONE

3. Repair erosion on the gland seal condenser heads. DONE

4. Repair to the atmospheric relief valve sealing face. DONE

5. Repair the condensate pump impeller clearance. DONE

6. Trim the covers on the last two stages of the turbine rotor. DONE

7. Skim cut the popit valves on the V-1 valve rack. DONE

8. Repair the spare journal bearings for the turbine and generator. DONE

9. Manufacture spare exciter journal bearings. DONE

10. Replace the buckets and covers in the reversing ring. DONE

11. Repair the dints dings cracks and erosion on the diaphragms. DONE

12. Manufacture a new inactive thrust bearing for a spare. DONE

13. Repair the erosion and cracked welds in the turbine shell. DONE

14. Manufacture a new non-return valve stem to repair the erosion in the packing area. DONE

15. Manufacture a new collector ring to repair the grounding short. DONE

16. Repair the broken lube oil strainer. DONE