Demo Ammo Shop 32448
1. Can it be confirmed that power to Bldg. 32448 has been disconnected so that we do not add cost for this during the bid phase?
A. Contractor will be responsible for utilities. SPECS 3.1.2.2.” Disconnecting Existing Utilities Where designated, remove existing utilities uncovered by work and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area. Remove meters and related equipment and deliver to a location on the station in accordance with instructions of the Contracting Officer.”
2. The concrete slab that will be removed has been painted. Please confirm that if sampling comes back negative for lead paint that it can be disposed of on base or will it need to go to an off-base disposal location regardless of test results?
A. All waste will be disposed of off base.
3. Please confirm that fill material can obtained at the JBER pit and will proctors need to be made available from that source.
A. Fill material will be available from JBER pit at standard pricing. Proctors will not be necessary.
4. SOW 4.1.1. States a 2% slope to allow for drainage. If surface is brought back to existing grade due to the 5’ limitation will this be acceptable? This is due to the structure that will remain next the building to be demolished.
A. This will be acceptable.
5. Concrete aprons outside of Bldg. 32448 extend beyond the 5’ as stated in SOW 3.2.3. Please confirm that these will need removed.
A. Aprons will be removed.
Replace Latrine 36212
6. The existing latrine concrete slab has several cracks apparent at the surface and it is assumed that these cracks may also be present in the vault compromising its integrity. If contaminated soils are encountered at the latrine location will this constitute a change of conditions as it is currently an unknown for bidding purposes?
A. contaminated soils will constitute a change of conditions.
7. Please confirm if the government or the contractor is responsible for pumping the latrine vault prior to demo.
A. The Contractor will be responsible for pumping out vault and disposal of waste.
8. Please confirm if temporary fencing is required at one or both locations.
A. Yes, fencing is required at both locations.