Please see attached
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q&A-CMU_Bldg_690.pdf | ||
| General Specifications.pdf | ||
| Wage Determination.pdf | ||
| Solicitation - FA500019QA113.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Repair CMU Parapet wall and cap flashing
Buckner Gym Water Park Roof Building 690
JBER, Alaska 99506
1. Contractor is to furnish all labor, materials and equipment to accomplish the following work. Contractor shall field verify all (if any) dimensions provided by the Government. This project includes but is not limited to the following tasks:
2. GENERAL SPECIFICATIONS:
a. All work will be accomplished in accordance with all applicable building, mechanical, electrical, and fire codes in effect at the time of award of contract.
b. During the job the Contractor is responsible for compliance with all OSHA standards for each operation.
c. The Contractor is responsible for completing a 3rd Wing Form 3, Base Civil Engineering Work Clearance
Request. Complete and submit this form to the Contracting Officer prior to start of work. The lead time will be at least one week.
d. Prior to beginning any open flame/welding operation (arc/gas welding, oxyacetylene cutting, soldering or brazing) the Contractor is responsible to contact the Base Fire Department Technical Services Section at 552-2620/4644 to be issued or trained to write an AF Form 592, USAF Welding, Cutting and Brazing Permit. Permit is to be available on the work site for inspection during the workday.
e. Working hours shall be 0730 to 1630 weekdays only, excluding federal holidays.
f. Job site is to remain clean at all times, debris shall be removed by the Contractor and disposed of off base.
g. During performance of this work the Contractor is responsible for repairing any damage incurred to existing Real Property/Grounds due to poor workmanship at no cost to the Government. Repair any damage caused by construction operations. Take all precautions necessary to safely protect the building and its occupants during the construction period.
h. Limit use of the premises to work in designated work areas. Do not disturb adjacent areas beyond the work site. Only the Governments right to perform work limits the Contractors’ use of the premises.
i. The Government will occupy the site and existing building during the entire construction period.
Coordinate with the Government during the construction to minimize conflicts and facilitate Government usage. Perform the work so as not to interfere with Government operations.
j. Keep driveways and entrances serving the premises clear and available to Government employees, customers, and emergency vehicles at all time. Do not use these areas for parking or storage of materials.
Schedule deliveries to minimize space and time for storage of materials and equipment site.
k. Contractor will maintain the existing building in a weather tight condition throughout the construction period and ensure within the project area that the building is secure during non-working hours.
l. Additional items as necessary. The Contracting Officer will notify Contractor of any additional items.
3. SYNOPSIS:
a. Service location; Building 690, JBER, Alaska 99506, (Buckner Gym Water Park Roof). Repair CMU parapet wall and metal flashing on Southwest side of the water park roof area. The Contractor shall dispose of all debris and associated components off base.
4. SPECIFIC REQUIREMENTS:
a. Service location; Building 690, JBER, Alaska 99506, (Buckner Gym Water Park Roof). Repair Repair CMU parapet wall and metal flashing on Southwest side of the water park roof area. The Contractor shall dispose of all debris and associated components off base.
Repair parapet CMU and flashing on southwest roof area Specifications:
• Remove damage area of Southwest parapet wall that was damaged from the wind storm
• Remove any CMU that’s not structurally in place or that’s loose
• Install CMU that were damaged from the wind storm, grouting CMU cell with mortar & rebar every 2 feet to strengthen top 2 course
• Install metal grating, EPDM and flashing as needed to finish repairs
• Clean up work area and remove any debris or material from work zone
b. Special equipment required, (Either scaffolding or scissor lift capable of reaching the work area with a working platform.
c. No special restrictions apply to this work site.
d. Special procedures are required at this work site.
- Contractor will have a current 3rd Wing Form 3, Civil Engineer Work Clearance Permit on the job site.
- The Contractor will coordinate with the Contracting Officer for additional procedures required when open flame/welding operations are necessary during the performance of this project.
e. Performance Period; Contractor shall receive a notification of contract award for installation. The performance Period will be 7 days from the date notified of the Notice to Proceed and all work must be completed NLT 15 Nov 2019.
f. A site visit shall be coordinated by the Contracting officer for the contractor to determine the scope of work, verify field measurements and location of the work site. Contractor will be notified of date and time of the site visit.
773d Civil Engineer Squadron Point of Contact for this project; Mr. Eugene McCrea or Mr. Phil Schoffstall, 773 CES/CEOHS, Structures Shop, 552-4081 or 552-7778