01_Statement_of_Work_-_Hanger_Pinch_Points.pdf

PDF 39 KB Posted

Attached to
Paint Hanger Pinch Points
Solicitation number
FA487719Q0441
Issued by

About this file

Statement of Work

View the file

Other files

File Type Posted
03_DANGER_Sign.pdf PDF
Paint_Hanger_Pinch_Points_-_RFQ.pdf PDF
02_AFMAN_91-203.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 1

STATEMENT OF WORK

Hangar Pinch Points, Fac 5430 and 4809

15 Aug 2019

This project will paint clear zones at the hangar door pockets and “DANGER” signs on the floor visible from all sides when approaching the hazard areas. All plant, labor, equipment and materials shall be furnished by the Contractor. No alterations, additions, or deletions shall be made without prior approval by the Contracting Officer. The contractor shall not begin any work under this project until a notice to proceed is issued through the base contracting office. All work must be in accordance with this Statement of Work and the base’s 2017 Design Compatibility Guidelines. The project includes, but is not limited to the following work elements. The period of performance for this work is 7 days.

Item 1 – Contractor shall prep chemical resistant urethane finish system on the hangar and/or maintenance bay floor to receive new signage / paint lines. Any damage to the concrete surface and/or joints during prep shall be repaired by the Contractor at no expense to the government. Damage is defined as spalling or cracking, and is not intended to include shot blast marks or overlap lines. Some Hangar Floors may contain metal shake. Water based materials shall not be used to prep these floors.

Item 2 – Portable equipment and materials in the hangar and/or maintenance bay shall be relocated by government personnel prior to the contractor beginning work. Existing air handling units at floor level will remain. Contractor shall protect intakes from paint, dust, and coating fumes during application.

Item 3 – The contractor shall paint 14” by 20” or larger “DANGER” signs at each pinch hazard area per AFMAN91-203. Place the signs so they can be read when approaching the hazard area. The word “DANGER” shall be printed on top with white letters with a message below stating: “HAZARDOUS AREA – STAND CLEAR DURING DOOR OPERATIONS.” The contractor shall use oil based enamel paint. Sign details will comply with standard proportions listed in AFMAN91-203. Locations will be provided.

Item 4 – The contractor shall mark clear zones with yellow/black hash marked lines, 2” to 3” wide at all hangar door pockets and recessed areas IAW AFMAN91-203. Clear zone shall be 5’ if space allows, around hazardous areas.