Davis-Monthan Air Force Base, Arizona FBNV 12-0013A & D, Consolidation (Cons Curbing) & (Demo) 10 th Street, Fac. 85142 08 JAN 2012

01011-1

SECTION 01011 - DESIGN REQUIREMENTS

1. PROJECT DESCRIPTION.

1.1. General. This request for proposal (RFP) provides

for the design, specifications, and sustainment of several pavements throughout Davis-Monthan airfields. Work will include but is not limited to, demo/milling and repaving of asphalt roadway pavements, restriping pavement markings, placing ceramic traffic dots, removing concrete curbing, installing concrete curbing, raising utility valve covers (with concrete encasement), landscaping (decorative rock & planting), light pole removal and realignment and various street sign removal.

1.2. Location. The project site is located on the

Airfield Restricted Area, Davis-Monthan Air Force Base (Tucson), Arizona.

1.2.1. Site Layout. The site will be located off Craycroft

Road and east of intersection at Comanchi and terminate at Davenport. All project documents and drawings will reflect this cardinal direction for the sake of uniformity and clarification.

1.3. Project Programming. Government programming requirements, classification of work, project approval levels, and funding appropriation have defined the requirement for execution of this project. The Contractor shall work the project as a whole. The Contractor shall maintain documentation to include, but not limited to, progress reports, requests for payment, change orders, modifications, and any other contractual (cost) documents for each project’s scope of the total project. All design and engineering costs shall be incorporated into this project.

1.4. Codes, Standards, and References.

1.4.1. The Davis-Monthan Air Force Base Design Compatibility Guidelines (DCG) are incorporated by reference into the project specifications. All provisions of the DCG shall be complied with unless specifically deleted by the project documents.

1.4.2. Equipment, materials, assemblies, spare parts, meters, monitors, controls, and any other articles of construction that are required to communicate with, connect to, operate with, or supplement existing base systems shall be 100% compatible in installation, configuration (including software), maintenance, repair, and operation or the item will not be considered equal and will be disapproved by the Government.

1.5. Design and Construction Schedule. The Contractor shall provide as part of their proposal a preliminary design and construction completion schedule for the Government’s review and approval. As a minimum, the proposed schedule shall incorporate the required milestone events as shown in the table on the following page.

The number of days shown are the Government’s estimated completion schedule. Should the contractor desire to perform the contract design and construction work in a different, more truncated, schedule, the contractor’s quote shall include this proposal and documentation to support the change. The Government will evaluate contractor proposed days based on the best interest of the project execution and the Governments requirements. However, the intent of all Davis-Monthan AFB Design-Build projects is to progress from Notice-To-Proceed (NTP) to construction completion and beneficial occupancy in NO MORE THAN 30 calendar days, excluding the 5 days shown for project closeout and completion. All days listed below are calendar days and include all Contractor actions such as design, construction, travel, mobilization, drawing and construction material submittal periods, etc.

Contractor shall submit an AF Form 66, Schedule of Material Submittals; and prepare material submittals and cutsheets to be submitted with the 65% design submittal in order to allow the Government to review/approve major construction materials and, with the Government’s approval, order construction material after being given the construction NTP. Contractor shall be given the construction NTP, at the Contracting Officer’s discretion, at the time of the 65% design approval to begin mobilization, site work, and demolition concurrently with 100% completion of the design package.

Insert Site Plan Here

01011-2

1.6. Project Specific Design and Construction Requirements. The Contractor shall incorporate as part of their design and include in the construction the following requirements in accordance with all regulations, requirements, and standards identified in this RFP.

1.6.1. General Requirements.

1.6.1.1 Not Used

1.6.1.2. The contractor shall be solely responsible for verification and validation of existing conditions, coordination of existing conditions in parallel with proposed requirements, and above and below grade condition assessment.

Use of existing condition data provided by the Air Force does not relieve the Contractor of liability associated with performance of work as Engineer of Record.

1.6.1.3. The project shall conform to all applicable Federal, State and local laws, regulations and base-specific standards and applicable Unified Facilities Criteria (UFC). Where there is a conflict between the referenced standards the most stringent shall take precedence

1.6.2. Not Used

1.6.3. Civil Requirements:

All asphalt for this project shall be in accordance with the UFGS edited specifications for Hot-Mix Asphalt (HMA) for Street’s, no recycled material will be used in the asphalt mix design.

All the milling on the project shall be done per UFC 3-250-03 Standard Practice Manual for Flexible Pavement, the cold milling process is described in the Chapter 7 Recycling of this manual. Millings for this project shall be stockpiled in a location directed by the government; milled material will not be recycled into new pavement.

2. DESIGN SUBMITTAL REQUIREMENTS.

Task

Start

Day

Finish

Day

Duration

(Days)

1 2 3 4 5 6 7 8 9 1

Notice to Proceed to Design

Charrette 1 1 1

Design Charrette Conference 2 8 7

Concept Design Review and

Acceptance 9 9 1

NTP to 65% Design 10 10 1

65% Design Complete/Submittal

(w/ Material Submittal Cut Sheets) 11 40 30

65% Design Government Review 41 54 14

65% Design Review Conference 55 57 3

Construction NTP (Based upon

65% Drawings) for Demo/Sitework 58 58 1

Demo/Sitework Construction 59 118 60

NTP to 95% Final Design (Based upon approval of 65% Design) 57 57 1

95% Design Complete/Submittal 58 78 21

65% Design Government Review 79 92 14

NTP to 100% Final (Based upon approval of 95% Design) 93 93 1

100% Final Back-Check 94 100 7

Construction Documents

Complete 101 101 1

Construction NTP for Remainder of

Project 102 102 1

Construction Period 103 357 255

Beneficial Occupancy 358 358 1

Project Closeout, As-Built Dwgs, O&M Manuals, Facility System

Training & Other Submittals 359 388 30

Project Complete 389 389 1

WeekRequired Milestones/Submittals (In Calendar Days)

01011-3

2.1. Standards, Documents, and Criteria. The design requirements within Section 01011 represent the minimum quality and quantity acceptable for the proposals and project submittals. The standards, documents, and criteria referenced within this RFP, although not all attached to or included in this RFP document shall be the most current version. Contractor shall be responsible for obtaining any documents not attached to or included in this

RFP but referenced as criteria for the project. Requirements of this RFP may add to, delete, modify, revise, or substitute to the extent indicated for criteria contained in the referenced standards and documents; and this section shall be deemed the governing authority of any changes to the other-referenced standards, documents and criteria.

2.2. Design Standards. Equipment, hardware, and materials shall be standard manufactured items unless otherwise specified. Replacement parts shall be standard and readily available through commercial means.

Discontinued products will not be accepted unless approved by the Contracting Officer. No equipment or materials being removed from the project shall be reused. All salvaged equipment shall become the property of the contractor and removed from the project site. The Davis-Monthan AFB Design Compatibility Guidelines, this RFP, the base guide specifications, and all applicable codes, laws, and guidance included therein will govern all design and construction of this facility and the Contractor shall include all code and DCG requirements in his bid. The

Contractor SHALL conform all design and construction work to the base DCG and shall assume that no waivers to the stipulations included therein shall be granted.

2.3. Design Units. This project shall be designed in English inch-pound (I-P) units.

2.4. Drawings. Drawings which may be provided as a part of this RFP are provided for reference only and only provide information for the Contractor’s use and incorporation into the design. Any drawings so provided shall not be considered complete and approved concept plans for this project. These drawings may be provided to give information on the types of renovations that are required to be included in the design and construction for the project, and shall be used in the design of the facility to the extent necessary to construct a complete and usable facility. These drawings may include, but are not limited to, information addressing renovation of interior spaces;

installation of an exterior, split-face concrete masonry wainscot; replacement of exterior windows and doors;

installation of a standing-seam metal roof (including substructure required); replacement/installation of mechanical, plumbing and fire protection; and electrical (interior, distribution, exterior, communications, local area networks, fire detection, etc.) systems. It is the Contractor’s responsibility to ensure the finished construction meets all of the requirements of this RFP. Drawings which may be provided as a part of this RFP may be available in electronic file format (AutoCAD).

2.4.1. Design Examples, References, and Preliminary Design Drawings. Design drawings and examples provided by the Government are for reference only and shall not be considered completed and approved concept plans for this project. Additional coordination of the design, in conjunction with the specific inputs from the

Customer and base pesonnel during the required Design Charette, will be required to develop the approved concept plan and design development through the creation of construction documents, and construction (reference

Part 5, ARCHITECTURAL DESIGN of this RFP).

2.4.2. Field Information. Base utility information which may be provided for this RFP is the best information available and would be provided to assist the Contractor during the design of this project. The Contractor is solely responsible for field verifying all information given. The Contractor is also responsible for obtaining all information necessary to properly design and construct the project. Information gathering during the design shall be coordinated through the Contracting Officer. Any field surveying required to provide utility locations, manhole inverts, verification of existing grades and features, etc., shall be the responsibility of the Contractor and shall be tied into the base surveying datum.

2.4.3. Design Details and Standards. The Contractor shall provide a design and construction package that uses the design details given or referenced in this RFP and the base DCG. Additional details shall be created by the

Contractor as required, but shall conform to the requirements of this RFP and are subject to approval by

Government.

2.5. Specifications. The Contractor shall provide a design and construction package which includes standard specifications (which may be provided upon contract award). The Contractor will edit the standard specifications as needed and as required for the project, and submit the edited specifications with each design submittal.

2.6. Investigation Report. The Contractor is responsible for the following as part of the project investigation:

01011-4

2.6.1. The following investigative services shall be included, if applicable to the project:

Investigation services shall include a plan check by the Contractor’s consultants of existing “as-built” drawing files, as applicable. Copies of requested as-built drawings may be furnished by the Government;

however, it is the responsibility of the Contractor’s consultants to search the drawing files for applicable drawings. The Government does not guarantee the accuracy or completeness of any as-built drawings.

In addition, as may be required by this RFP, the Contractor’s consultants will meet with the affected base agencies to gather information pertinent to this project.

Investigation services for projects that affect existing facilities shall also include at least one field trip by the

Contractor’s consultants to verify the existing conditions at the site.

2.6.2. Items to be reported on include but are not limited to the applicable portions of the following paragraphs:

Existing interior and exterior physical conditions applicable to the project.

Accuracy and completeness of reference data furnished by the Government.

Architectural, communications, electrical, fire protection, mechanical, seismic, structural, utility, UFAS/ADA

Accessibility Guidelines, International Building Code or other special system requirements.

Availability and adequacy of existing structure, utilities, or systems to support requirements identified above.

Brief description of existing drainage problems, and proposed solutions or design options.

Soil boring test results (including CBR tests or sub-grade modulus tests as necessary).

Site plans showing topography, soil test locations, existing utility lines showing points-of-connection, and areas of required site work.

Special design problems or interferences with existing conditions, e.g., asbestos and/or lead-based coatings abatement, and proposed solutions or design options.

Problems anticipated with constructing the project within budget, and proposed solutions or options and the anticipated costs.

2.7. Design Analysis. The Contractor is responsible for the following as part of the project Design Analysis:

2.7.1. The following computations must be included, if applicable to the project:

Seismic, using the USGS Seismic hazard maps in lieu of the International Building Code, and structural loads and foundation design.

Pavement loads and drainage calculations.

2.7.2. The Contractor shall include, as a separate index in the Design Analysis at each submittal, the review comments received from the previous Air Force design reviews. Every review comment shall be annotated by the

A-E to indicate the disposition, i.e., whether the review comment is incorporated into the design documents; and, when incorporated, the location where the review comment is incorporated. If an exception to the incorporation of a review comment is proposed by the Contractor, he shall coordinate and resolve the exception with the Contracting

Administrator and Base Project Manager; and, if the exception is approved, indicate same. If the exception is not approved, the A-E shall annotate the disposition and the location of the review comment as described before.

2.8. Design Submittal Package Requirements. The Contractor shall submit to the Government the following copies of the contract drawings, specifications, and other contract documents at each design stage.

2.8.1. Not Used

2.8.2. Not Used

2.8.3. Not Used

2.8.4. Not Used

2.9. Codes. The design, materials, equipment, and installation shall be in accordance with, but not limited to, the requirements of the Davis-Monthan AFB Design Compatibility Guidelines and all addendums, all listed codes and design manuals listed therein, and with the requirements of this section with the listed codes, guides, and manuals. All references shall be assumed to be the most recent revision unless specifically noted otherwise.

Although the references have been listed by engineering discipline for ease of citation, this does not preclude their

01011-5 requirement to be used for work within any other discipline. When there is a conflict between any listed code, guide or reference, the most stringent requirements shall apply.

2.9.1. Civil References.

UFC 3-230-17FA, Drainage Areas for Other Than Airfields.

UFC 3-240-07FA, Sanitary and Industrial Wastewater Collection - Gravity Sewers and Appurtenances.

Pima County Arizona, Hydrology Manual for Engineering Design and Flood Plain Management.

Unified Facilities Criteria (UFC) 3-120-02 – Design POV Site Circulation and Parking.

UFC 3-210-01A - Design: Area Planning, Site Planning, and Design.

UFC 4-010-01, DoD Minimum Antiterrorism Standards for Buildings.

Manual of Uniform Traffic Control Devices, U.S. Department of Transportation, FHWA.

UFC 3-250-18FA, General Provisions and Geometric Design for Roads, Streets, Walks, and Open Storage Areas.

UFC 3-250-03 Standard Practice Manual for Flexible Pavements

UFC 3-250-06 Repair of Rigid Pavements Using Epoxy Resin Grouts, Mortars and Concretes

UFC 3-250-08FA Standard Practice for Sealing Joints and Cracks in Rigid and Flexible Pavments

UFC 3-270-04 Concrete Repair

UFC 3-270-03 Concrete Crack and Partial-Depth Spall Repair

UFC 3-270-01 Asphalt Maintenance and Repair

UFC 3-270-02 Asphalt Crack Repair

UFC 3-250-03 Standard Practice Manual for Flexible Pavements

UFC 3-260-02 Pavement Design for Airfields

2.8.2. Geotechnical References.

Arizona Department of Transportation (ADOT), Standard Specifications for Road and Bridge Construction.

Air Force Instruction (AFI) 32-1023, Design and Construction Standards and Execution of Facility

Construction Projects.

AFMAN 88-3, Ch. 7, Soils and Geology Procedures for Foundation and Design of Buildings and Other

Structures (Except Hydraulic Structures).

UFC 3-250-08FA, Standard Practice for Sealing Joints and Cracks in Rigid and Flexible Pavements.

AFMAN 88-6, Ch. 8, Standard Practice for Concrete Pavements.

AFMAN 88-6, Ch. 9, Bituminous Pavements – Standard Practice (Including C1.

UFC 3-250-01FA, Pavement Design for Roads, Streets, Walks, and Open Storage Areas

UFC 3-220-01A; Design: Deep Foundations

UFC 3-220-02; Design: Pile Driving Equipment

UFC 3-220-03FA; Design: Soils and Geology Procedures for Foundation Design of Building and Other

Structures - Except Hydrolic Structures

UFC 3-220-04FA; Design: Backfill for Subsurface Structures

UFC 3-220-05; Design: Dewatering and Groundwater Control

UFC 3-220-06; Design: Grouting Methods and Equipment

UFC 3-220-07; Design: Foundations in Expansive Soils

American Concrete Institute (ACI) Manual of Concrete Practice.

2.8.3. Not Used

2.8.4. Not Used

2.8.5 Not Used

2.8.6 Not Used

2.8.7. Not Used

2.8.8. Not Used

http://www.hnd.usace.army.mil/techinfo/UFC/UFC3-220-01A/UFC3-220-01A.pdf http://www.hnd.usace.army.mil/techinfo/UFC/UFC3-220-02/UFC3-220-02.pdf http://www.hnd.usace.army.mil/techinfo/UFC/UFC3-220-03FA/UFC3-220-03FA.pdf http://www.hnd.usace.army.mil/techinfo/UFC/UFC3-220-03FA/UFC3-220-03FA.pdf http://www.hnd.usace.army.mil/techinfo/UFC/UFC3-220-04FA/UFC3-220-04FA.pdf http://www.hnd.usace.army.mil/techinfo/UFC/UFC3-220-05/UFC3-220-05.pdf http://www.hnd.usace.army.mil/techinfo/UFC/UFC3-220-06/UFC3-220-06.pdf http://www.hnd.usace.army.mil/techinfo/UFC/UFC3-220-07/UFC3-220-07.pdf

01011-6

3. CIVIL DESIGN.

3.1. Project Site Survey. A survey of the site shall not be provided by the Government. The Contractor shall generate/contract a current site survey which shall include the topography of the site, surface features of the site

(including but not limited to, walks, parking lots, utility poles, transformers, valves, manholes, landscaping, etc.) and underground utilities. Underground utility line locations on the survey shall be developed from base mapping and from surface features found in the field. Existing manhole rim and invert elevation information for the sanitary sewer and storm drain systems is not provided. The Contractor shall field survey all sanitary sewer and storm drain system manholes involved in the design/construction of this project to obtain actual rim and invert elevations. The area to be surveyed shall encompass all areas required for the design and construction of all features included within the scope of this project; and shall, as a minimum, address on-site, through-site, and off-site flows to insure that downstream facilities are not adversely affected or degraded. Gathering topographic and planimetric map data shall be accomplished by field methods, using Global Positioning System (GPS), total station methods, or a combination thereof. Base utility drawings are available for the Contractor’s use; however, these drawings may not reflect current conditions. It is the responsibility of the Contractor to obtain additional mapping from the base if needed.

3.1. Project Site Survey. A survey for the site shall not be provided by the government. The Contractor shall generate/contract a current site survey which shall include the topography of the site, surface features of the site (to include walks, parking lots, utility poles, transformers, valves, manholes, landscaping, etc.) and underground utilities. Underground utility line locations on the survey shall be developed from base mapping and from surface features found in the field. Existing manhole rim and invert elevation information for the sanitary sewer and storm drain systems is not provided. The Contractor shall field survey all sanitary sewer and storm drain system manholes involved in the design/construction of this project to obtain actual rim and invert elevations. The area to be surveyed shall encompass all areas required for the design and construction of all features included within the scope of this project. Gathering topographic and planimetric map data shall be accomplished by field methods, using Global Positioning System (GPS), total station methods, or a combination thereof. Base utility drawings are available for the contractor’s use. These drawings may not reflect current conditions. It is the responsibility of the surveying contractor to obtain additional mapping from the base if needed.

3.2. Borrow & Waste Areas. Any required borrow shall be obtained by the Contractor from an off-site borrow source. Demolition and construction waste from the project shall be disposed of at an off-base location approved by the Contracting Officer.

3.3. Site Utilities. All utility installations (including sizes and materials) shall comply with the Base DCG. Utility services are available and are adjacent to the site. See Section 1.6.3.

3.4 Haul Route. The primary haul route for this project is through Swan Gate as shown on sheet 1 of attached plans. Swan Gate is normally open from 0530 to 1830, Monday thru Friday. It is not open at night or on weekends, holidays or military “down days”. If the contractor is permitted to work at times when the Swan Gate is closed, they will be required to use Craycroft Gate.

3.5. Contractor's Storage Yard. The requested size of the Contractor's storage and staging area shall be proposed as part of the design, with the location of the yard being within the boundary of the CES/Contractor

Storage Yard off of Yuma Rd. A temporary security fence shall be provided by the Contractor at storage yard boundaries.

3.6. Not Used

3.7. Not Used

3.8. Permits. The Contractor is responsible for obtaining all necessary Federal, state, county, and local permits required to complete the construction of this project. The Contractor is responsible for paying all fees associated with obtaining the permits and performing all work as required within the permits at no extra cost to the

Government.

3.8.1. The Contractor shall comply with the Arizona General Construction Permit. The Contractor shall prepare a

Storm Water Pollution Prevention Plan (SWPPP) in accordance with and with final approval of the State of Arizona.

A copy of the contractor’s SWPPP and Notice of Intent (NOI) shall be provided to the Contracting Officer prior to

01011-7 any site work covered within the SWPPP. A Notice of Termination (NOT) must be provided to the Contracting

Officer prior to project close out.

4. Not Used

5. Not Used

6. Not Used

7. Not Used

8. Not Used

End of Section 01011

Other files for this federal contract opportunity

Other files attached to DMAFB Multiple Award Construction Contract (MACC), newest first.
File Type Posted
Appendix D - —
Project Package 1 - Section 01011 - Design Requirements - Revised.pdf PDF
Project Package 2 - As-Built Drawings —
Project Package 1 - As-Built Drawings —
Project Package 3 - As-Built Drawings - Facility 145.zip ZIP file
Project Package 3 - As-Built Drawings - Facility 81.zip ZIP file
Project Package 1 - As-Built Drawings —
Project Package 2 - As-Built Drawings —
Project Package 1 - As-Built Drawings —
Project Package 1 - As-Built Drawings - Facility 4101.zip ZIP file
Project Package 2 - Electrical-Comm Site Plan.pdf PDF
Project Package 1 - Project Drawings - Revised.pdf PDF
Project Package 1 - As-Built Drawings - Facility 4455.zip ZIP file
Project Package 3 - Building 81 Communications Removal and Replacement.pdf PDF
Project Package 3 - Project Drawings —
Project Package 3 - Section 01011 - Design Requirements —
Project Package 1 - Section 01011 - Design Requirements —
Appendix D - Davis-Monthan AFB CIP Data Contour Data.zip ZIP file
Appendix E - DoD Minimum Antiterrorism Standards for Buildings - UFC 4-010-01.pdf PDF
1 - MACC Pre Proposal Conference - Record of Meeting - Sign In Sheet.pdf PDF
2 - MACC Pre-Proposal Conference - Power Point Presentation.ppt PPT presentation
Arizona Transaction Privilege Tax Ruling - TPR 99-1.pdf PDF
ID2 - Davis Monthan - Jan11.pdf PDF
Project Package 4 - Wage Determination - Construction Type —
Project Package 2 - Section 01010 - Summary of Work —
Project Package 1 - Section 01011 - Design Requirements —
Project Package 4 - MACC Bid Schedule Seed Project 4.xlsx XLSX spreadsheet
Appendix A- Design Compatibility guidelines —
Project Package 3 - Section 01010 - Summary of Work —
Project Package 3 - MACC Bid Schedule Seed Project 3.xlsx XLSX spreadsheet
Project Package 3 - Project Drawings —
Project Package 4 - Project Drawings.pdf PDF
FA4877-12-R-0008 MACC.pdf PDF
Project Package 3 - Wage Determination - Construction Type —
Project Package 3 - Project Drawings —
Wage Determination 05-2025 —
Project Package 3 - Project Drawings —
MACC Statement of Work.pdf PDF
Project Package 1 - MACC Bid Schedule Seed Project 1.xlsx XLSX spreadsheet
Project Package 1 - Wage Determination - Construction Type —
Project Package 3 - Project Drawings —
Project Package 1 - Airman Leadership School Design Guide.pdf PDF
Project Package 3 - Project Drawings —
Project Package 1 - Project Drawings.pdf PDF
Past Performance Questionnaire MACC.doc DOC document
Project Package 4 - Section 01010 - Summary of Work —
Project Package 3 - Project Drawings —
Project Package 2 - Wage Determination - Construction Type —
Appendix C- 355 CES EMO Civ Contractor Environmental Guide.pdf PDF
Project Package 1 - Section 01010 - Summary of Work —
Show all 50

DMAFB Multiple Award Construction Contract (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .