Responses to Pre-Solicitation/Site Visit Questions – Repair Sanitary Sewers Phase 2

1) Would it be possible to arrange a site visit after the posted site visit?

Gov’t Response: No, the site visit was already scheduled and occurred.

2) Would open cut be considered as an alternate to the CIPP?

Gov’t Response: Product substitution is not anticipated for this project; follow design and specifications regarding CIPP.

3) Can more than one MH be worked on at a time; if so ~how many?

Gov't Response: This is dependent on the contractor ability, means and methods. If outages are required it shall be coordinated through Cannon AFB.

4) Can the MH be dry ice blasted cleaned? (Information Enclosed)

Gov't Response: Product substitution is not anticipated for this project. Follow cleaning requirements per drawings and specs.

5) Will clean water be furnished on site and at what cost if available?

Gov't Response: No government furnished equipment or materials are provided in this contract.

6) As per sheet 3 of 7 (00C101) the following MH listed do not denote any repairs. Please clarify.

Area 1: 103A, 114, 102991, DS 10299

Area 2: 102285, US 102285, 102988, AT Bldg. 724

Area 3: AT Fire Station, SW Bldg. 680

Gov't Response: Follow drawings and specification requirements; Manhole Action Table (MAT) states actions that shall be taken, if nothing is in the MAT no action is required.

7) Please clarify sheet 00C102 pg. 4 of 7

Note 4 states "only remove that segment, assume 5' segment.

Gov't Response: Only remove the part of the pipe that is damaged unless CCTV shows otherwise.

8) On the dwg. it calls out from MH 91 to MH 105 8" VCP and from MH 114 to 115. Is this to mean that you want new pipe from MH 91 to MH 105 and new pipe from MH 114 to 115?

Gov't Response: No, it is point repair; replace the part of the pipe that is damaged unless the CCTV shows otherwise.

9) Sheet 00C103 pg. 5 of 7 Bldg. 726 to MH 113 Excavate and replace

Note 4 States to only remove that segment. Is the segment to be 5'

Gov't Response: No, this is not point repair; it is the entire length of pipe.