Revised Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site_Visit_Attendees.pdf | ||
| PD2_Amend_1.doc | DOC document | |
| Plan_Set_-_CZQZ_10-0009_-_Repair_HVAC_B198_-_28_Aug_2013_(2).pdf | ||
| Bldg_198_Questions_ _Answers.doc | DOC document | |
| Att_4_-_Wage_Determination.pdf | ||
| Att_3_-_Schedule_of_Materials.pdf | ||
| Att_6_-_DDC_Requirements_Guide.pdf | ||
| Att_1_-_Statement_of_Work.pdf | ||
| Att_2_-_Specifications.pdf | ||
| Att_5_-_Drawings.pdf | ||
| FA4855-13-B-0002_-_Solicitation.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
Repair HVAC System Bldg 198
Project Number: (CZQZ10-0009)
Cannon Air Force Base, New Mexico
28 August 2013
Description of Work: The work elements for this project scope are listed below:
General
a) The Contractor shall submit a phasing plan for approval prior to beginning work. The building must be occupied during construction. The contractor must supply temporary heat and power to keep the building functioning in seasonal weather.
b) Contractor shall verify all existing conditions to ensure accuracy of plans.
c) Meet with the base EMCS technicians during final troubleshooting to ensure the facility is working properly.
d) Contractor must contact Bioenvironmental Engineering (784-4063) 3 business days prior to anything involving the potable water lines, whether taking the building off the system or if there is any "exposure to the elements" of the distribution system.
Mechanical Room
e) Boiler - Replace the current boiler in the mechanical room with a high efficient condensing boiler. Utilize existing sensors from the old boiler and install on new boiler to the maximum extent possible. Connect all sensors to the building EMCS.
f) Heating/Cooling Coils – thoroughly clean heating and cooling coils in AHU-1so they are free from debris and any film that would cause premature clogging of the coils.
g) Replace plates covering the ends of AHU-1 heating and cooling coils and seal to prevent leakage.
h) Replace all HVAC plumbing in mechanical room of various sizes. Insulate pipe according to 23 07 00 – HVAC Insulation. Reuse motorized actuators and valves.
i) Install insulation on chilled water piping in the mechanical yard according to 23 07 00 – HVAC Insulation. Ensure the new insulation is protected from the elements.
j) Install new pressure and digital temperature gauges to replace existing gauges.
k) Create a new penetration in the roof on the mechanical room for an exhaust air duct. Install a roof hood to cover the new opening.
l) Demolish existing supply fan motor and replace with premium efficiency motor. Supply a new drive belt for supply fan.
m) Demolish existing air compressor and air dryer in the mechanical room. Properly dispose of equipment.
n) Demolish existing chilled/heating water pumps and replace with new pumps with premium efficiency motors.
FA4855-13-B-0002 REVISED 28 August 2013 Page 1 of 3
o) Demolish existing AHU-2 and associated pluming and ductwork as shown in the contract documents.
p) Repair the existing filter section, in AHU-1, by installing new weather stripping. Ensure air does not bypass the filters. Provide new filters at the beginning and end of the project.
q) Turn the fire suppression valve stack riser to ensure gate valve wheels are parallel to the mechanical room wall facing the entrance. Current configuration is a safety hazard. Reroute plumbing to accommodate new configuration.
r) Clean out floor drains to ensure proper drainage of water.
EMCS
s) Install sensors as shown in the contract documents. Reuse sensor to the maximum extent possible.
t) Replace the current filter pressure switch with a pressure transducer on AHU-1.
u) Connect new fan coils to existing Alerton EMCS as shown in drawings.
v) Program points for all equipment in accordance with the Cannon AFB DDC General Requirements Guide.
Interior
w) Demolish ductwork, plumbing, air handling equipment, dampers and thermostats as indicated on drawings.
x) Install new ductwork, plumbing, air handling equipment, dampers and thermostats as indicated on drawings.
y) Remove PMB-19 from existing location and install in new location as PMB-26.
z) Inspect and clean reheat coil and dampers in existing VAV boxes to ensure proper air flow and damper operation (24 VAV boxes). If VAV boxes are deemed inoperable, the Contractor shall report findings to the Contracting Officer, and a determination will be made to ensure new VAV boxes are supplied and/or installed as necessary.
aa) Deconstruct and preserve all suspended grid ceiling parts for reinstallation after modifications are complete. Replacements for damaged ceiling grid parts shall be supplied and installed by the Contractor as necessary at no additional cost to the government.
bb) Move thermostats as shown in contract plan set.
cc) Install a ductless split system air conditioner in the communications room per the equipment schedule. Repair the return duct and seal to prevent leakage. Provide the proper drain, route condenser plumbing to existing mechanical yard.
dd) Install 3 fan coils in the area previously serviced by AHU-2.
ee) Install new chilled and hot water lines to new fan coils.
ff) Install an outside air duct to each fan coil. Duct shall include a motorized damper and filter. A weatherproof hood is required on the exterior opening and must be 10’ above ground level.
gg) Create an opening in the wall separating the main building from the addition located in the plenum space to allow air flow back to AHU-1.
FA4855-13-B-0002 REVISED 28 August 2013 Page 2 of 3
hh) Install an “Emergency HVAC System Shut-off Switch”. The switch shall be a maintained contact push button type with a lift plate to prevent accidental switching. Include an engraved stainless steel plate to label the switch.
ii) Test and Balance - Perform a test and balance to set up the building HVAC system to provide airflow indicated on the drawings.
jj) Commission building to check programming logic and ensure sequence of operations is followed. Submit a report to outline deficiencies and actions taken to correct deficiencies.
1.1. PERIOD OF PERFORMANCE: This work is to be completed in 200 calendar days or less after NTP. All weekend and federal holiday work may not be permitted unless otherwise approved by the Contracting Officer.
1.2. MEETINGS: The contractor shall conduct one project kickoff meeting within one week of Notice to Proceed. The contractor shall prepare and distribute meeting minutes from each meeting held on site.
GOVERNMENT FURNISHED PROPERTY: Upon the Contractor’s request, the Government will provide electronic and/or hard copies of available documents and correspondences pertinent to the Work.
In addition, the Government will provide assistance with base passes, identification badges, and registrations.
SUBMITTALS: The Contractor shall submit for approval all technical data and material samples for all proposed building materials and equipment in accordance with Section 01 33 00: Submittal Procedures as per attached Schedule of Material Submittals.
FA4855-13-B-0002 REVISED 28 August 2013 Page 3 of 3