BUILDING 785 - FLOOR PLAN - MECHANICAL - DEMOLITION

View the file

Other files

File Type Posted
Amendment_0001.pdf PDF
758_Asbestos.pdf PDF
785asbestos.pdf PDF
01_57_20.00_ENVIRONMENTAL_PROTECTION_26_Mar_13_corrected.pdf PDF
01_00_00_GENERAL_REQUIREMENTS_9003_26_Mar_13correted.pdf PDF
Infrared_Heaters_Repair_Questions_(3).pdf PDF
02_41_00__DEMOLITION_AND_RECONSTRUCTION.pdf PDF
m-1.pdf PDF
23_11_23.00_10_GAS_PIPING_SYSTEMS.pdf PDF
Bidders_Checklist.doc DOC document
m-3.pdf PDF
e-3.pdf PDF
m-2.pdf PDF
SITE_VISIT_CONFERENCE_RESERVATION_FORM.docx DOCX document
Lobby_Activities_Form.pdf PDF
01_45_01_CONTRACTORS_QUALITY_CONTROL.pdf PDF
01_00_01_SPECIFIC_REQUIREMENTS__MAFB.pdf PDF
01_00_00_GENERAL_REQUIREMENTS.pdf PDF
e-2.pdf PDF
23_52_00_HEATING_BOILERS.pdf PDF
Title_Page TOC_ _COVER_SHT.pdf PDF
01_62_35_RECYCLED__RECOVERED_MATERIALS.pdf PDF
01_31_01_PROJECT_MANAGEMENT.pdf PDF
e-1.pdf PDF
m-5.pdf PDF
Architectural_electrical_Design_Analysis.docx DOCX document
23_07_00_THERMAL_INSULATION_FOR_MECHANICAL_SYSTEMS.pdf PDF
01_78_23_OPERATION_AND_MAINTENANCE_DATA.pdf PDF
01_35_29_SAFETY_AND_OCCUPATIONAL_HEALTH_REQUIREMENTS.pdf PDF
Contractor_Information.rtf RTF text file
IFB_solicitation.doc DOC document
m-7.pdf PDF
01_35_00_SPECIAL_PROVISIONS_FOR_WORKING_ON_OR_NEAR_THE_AIRFI.pdf PDF
X-1_VICINITY_MAP _INDEX_OF_DRAWINGS.pdf PDF
01_57_20.00_ENVIRONMENTAL_PROTECTION_.pdf PDF
m-6.pdf PDF
Question_Form.docx DOCX document
AF_Form_66.xls XLS spreadsheet
01_78_00_TASK_ORDER_CLOSE_OUT_REQUIREMENTS.pdf PDF
23_54_16.00_10_HEATING_SYSTEM__GAS-FIRED_HEATERS.pdf PDF
01_33_00_SUBMITTAL_PROCEDURES.pdf PDF
01_55_01__SECURITY_REQUIREMENTS.pdf PDF
Wage_Determination.docx DOCX document
01_04_00_Unit_Price_Book_and_Software_Requirments.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUILDING 785 - FLOOR PLAN - MECHANICAL - DEMOLITION

1/8" = 1'-0"

NOTES:

1. MECHANICAL CONTRACTOR SHALL REMOVE EXISTING HOT WATER UNIT HEATER, PIPING, HANGERS, CONTROLS, ETC. AS INDICATED THIS SHEET.

2. MECHANICAL CONTRACTOR SHALL REMOVE EXISTING ELECTRIC UNIT HEATER, HANGERS,

CONTROLS, ETC. AS INDICATED THIS SHEET.

NOTE 1 NOTE 1 NOTE 1 NOTE 1

NOTE 1NOTE 1NOTE 1NOTE 1

NOTE 1

NOTE 1

NOTE 1

NOTE 1

NOTE 1

NOTE 1

NOTE 1

NOTE 1NOTE 1

NOTE 2 NOTE 2

NOTE 1

CAP CAP CAP

NOTE 1

NOTE 1

NOTE 1

CAP

NOTE 3

HWP-1

NOTE 3

BOILER-1

3. MECHANICAL CONTRACTOR SHALL REMOVE EXISTING BOILER (BOILER-1), EXISTING HOT WATER PUMP (HWP-1)

AND PIPING AS INDICATED THIS SHEET.

6"1"

6"

1"

6"

EXISTING BOILER VENT

UP THRU ROOF WITH

ROOF FLASHING, STORM

COLLAR AND VENT CAP

NOTE 3

NOTE 3

NOTE 3

CAPE

1674 Headland Avenue

Dothan, AL 36303

(334) 793-2790

Fax: (334) 671-7157

Engineering H 1214 1st Avenue Suite 210

Columbus, GA 31901

(706) 596-1840

Fax: (706) 596-9233

File details come from the government source that posted it. Updated .