QSEU 12-2002, Repair Infrared Heaters
Solicitation number
FA4830-13-B-0002
Issued by

About this file

Questions and Answers

View the file

Other files

File Type Posted
Amendment_0001.pdf PDF
758_Asbestos.pdf PDF
785asbestos.pdf PDF
01_57_20.00_ENVIRONMENTAL_PROTECTION_26_Mar_13_corrected.pdf PDF
01_00_00_GENERAL_REQUIREMENTS_9003_26_Mar_13correted.pdf PDF
02_41_00__DEMOLITION_AND_RECONSTRUCTION.pdf PDF
m-1.pdf PDF
23_11_23.00_10_GAS_PIPING_SYSTEMS.pdf PDF
Bidders_Checklist.doc DOC document
m-3.pdf PDF
e-3.pdf PDF
m-2.pdf PDF
SITE_VISIT_CONFERENCE_RESERVATION_FORM.docx DOCX document
Lobby_Activities_Form.pdf PDF
01_45_01_CONTRACTORS_QUALITY_CONTROL.pdf PDF
01_00_01_SPECIFIC_REQUIREMENTS__MAFB.pdf PDF
01_00_00_GENERAL_REQUIREMENTS.pdf PDF
e-2.pdf PDF
23_52_00_HEATING_BOILERS.pdf PDF
Title_Page TOC_ _COVER_SHT.pdf PDF
01_62_35_RECYCLED__RECOVERED_MATERIALS.pdf PDF
01_31_01_PROJECT_MANAGEMENT.pdf PDF
e-1.pdf PDF
m-5.pdf PDF
Architectural_electrical_Design_Analysis.docx DOCX document
23_07_00_THERMAL_INSULATION_FOR_MECHANICAL_SYSTEMS.pdf PDF
01_78_23_OPERATION_AND_MAINTENANCE_DATA.pdf PDF
01_35_29_SAFETY_AND_OCCUPATIONAL_HEALTH_REQUIREMENTS.pdf PDF
Contractor_Information.rtf RTF text file
IFB_solicitation.doc DOC document
m-7.pdf PDF
01_35_00_SPECIAL_PROVISIONS_FOR_WORKING_ON_OR_NEAR_THE_AIRFI.pdf PDF
X-1_VICINITY_MAP _INDEX_OF_DRAWINGS.pdf PDF
01_57_20.00_ENVIRONMENTAL_PROTECTION_.pdf PDF
m-4.pdf PDF
m-6.pdf PDF
Question_Form.docx DOCX document
AF_Form_66.xls XLS spreadsheet
01_78_00_TASK_ORDER_CLOSE_OUT_REQUIREMENTS.pdf PDF
23_54_16.00_10_HEATING_SYSTEM__GAS-FIRED_HEATERS.pdf PDF
01_33_00_SUBMITTAL_PROCEDURES.pdf PDF
01_55_01__SECURITY_REQUIREMENTS.pdf PDF
Wage_Determination.docx DOCX document
01_04_00_Unit_Price_Book_and_Software_Requirments.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Infrared Heaters Repair Questions and Answers

QSEU 12-2002

1. Building 758 appears to have HW piping to be removed marked in orange indicating it contains asbestos. The specifications nor drawings indicate the contractor’s responsibility to abate any hazardous materials. Will this be abated prior to this work beginning? If not, please provide a copy of the asbestos survey for each building so we may price the abatement.

a. As the project requires demo of existing heating system the remediation will be the contractor’s responsibility and should meet all base, state, and federal requirements. So the Air force has knowledge of asbestos in two of the building.

b. Buildings in question for asbestos as part of possible demo are:

Project qseu 12-2002: 645, 758, and 785 645,this bldg was blt in 1997. We have no asbestos records for this facility 758, Please see attached document labeled 758 Asbestos, 785, Please see attached document labeled 785 Asbestos

2. There was a lot of mention of providing gas metering for each building under this project that will connect to the Siemens EMCS. However, there is nowhere in the documents that indicate this to be required. Two of the building do not currently have EMCS, so a new control panel, power, and comm drop would need to be added just to monitor the one meter. Please confirm this project does require gas meter monitoring through the EMCS.

a. It is a federal requirement that buildings be metered. It is a base standard that the meters report to the base master EMCS system. If the gas meter is not there it needs to be installed and if it does not report it needs to be upgraded. If the meter can just report over the base network without a dedicated EMCS unit in the building this is acceptable.

3. Section 01 00 00 of the specifications references and explains a lot of criteria for a RFP/negotiated project, like a BOA project. This does not seem to apply to this project.

Please verify.

a. Updated Specifications 01-57-20.00 Environmental Protection 26 Mar 13.

4. Section 01 14 00 of the specifications references and requires E-4clicks software, like would be required for a SABER contract. This is a open bid project and this section does not seem to apply to this project. Please verify.

a. E-4 Clicks not required.

5. Section 0157 20 of the specifications refers to a lot of environmental requirements that do not apply to this project. This seems to be a canned specification, with reference to storm water retention, water runoff, etc., that has nothing to do with this project. Please verify and delete paragraphs that do not apply to this project.

a. Updated Specifications 01-00-00 General Requirements 26 Mar 13.

6. The location of the heaters in building 758 conflict with existing structures and utilities.

They can’t be located high because the heaters will burn elements underneath and there is not a direct path for routing. If they are mounted underneath the structure, they will create shadows from the lights. Also, there are rows of radiant heaters shown on interior walls. This is normally not recommended by the heater manufacturers and would likely perform better if located along two shorter and one longer exterior wall in each bay.

Please verify location and height of heaters.

a. Because the building has overhead trolley cranes, the heaters were located in the only spaces available

7. Building 785 shows a new 1” gas line going from the mechanical room into the corridor. There is already a 1” gas pipe in this location that looks very new. Is it the intent to re-use this pipe and connect the new heaters to it over the corridor?

a. The intent was for the new 1" (2 psig) gas line to connect to the existing gas piping in the Mechanical Room as indicated on the plans

File details come from the government source that posted it. Updated .